MCLENNAN SH 6 (0049-01-099)

Items: 12

County: MCLENNAN
Length: N/A
Highway: SH 6
District: WACO
Control Number: 0049-01-099
DBE Goal: N/A
Project: STP 2B20(186)HES
Guaranty: N/A
Time: 240 WORKING DAYS
Engineer's Estimate: $9,043,757.00
Date: 08/05/2020 (5 years ago)
Contract Number: N/A
Type: HAZZARD ELIMINATION AND SAFETY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$9,043,757.00
1
$6,830,728.00
Over/Under Est: -24.47% -$2,213,029.00
Over/Under Est: -19.45% -$1,758,853.47
Amt Left: 6.65% $454,175.53
Over/Under Est: -19.03% -$1,720,721.16
Amt Left: 7.21% $492,307.84
Delta: -0.52% -$38,132.31
Over/Under Est: -14.99% -$1,355,507.27
Amt Left: 12.55% $857,521.73
Delta: -4.99% -$365,213.89
$9,485,585.72
Over/Under Est: 4.89% $441,828.72
Amt Left: 38.87% $2,654,857.72
Delta: -23.38% -$1,797,335.99
$11,651,481.80
Over/Under Est: 28.83% $2,607,724.80
Amt Left: 70.57% $4,820,753.80
Delta: -22.83% -$2,165,896.08

Bid Items & Bid Tabulations

12 Total 0 of 12
MCLENNAN  |  SH 6  |  WACO  |  0049-01-099  |  08/05/2020  |  $9,043,757.00  |  STP 2B20(186)HES  |  HAZZARD ELIM AND SAFETY  |  240 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
MASSANA, INC.
GRATIOT CONSTRUCTION, LTD.
CROSS PLUS CONSTRUCTION, LLC
SCR CIVIL CONSTRUCTION, LLC
ALTUS CONSTRUCTION LLC
VANN/ELLI, INC.
BLADING
STA 1,590.100 $150.000 $95.000 $1.000 $75.000 $60.000 $302.650 $290.000
ROLL SODDING
SY 176,763.000 $5.000 $5.250 $4.470 $3.500 $5.750 $7.120 $7.000
VEGETATIVE WATERING
MG 1,434.500 $30.000 $60.000 $63.970 $25.000 $125.000 $35.600 $130.000
RIPRAP (MOW STRIP)(4 IN)
CY 11,778.300 $400.000 $272.000 $357.630 $349.000 $320.000 $368.550 $500.000
MOBILIZATION
LS 1.000 $640,000.000 $452,565.650 $784,149.180 $799,000.000 $590,500.000 $943,311.440 $900,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 16.000 $5,000.000 $16,500.000 $1.000 $3,000.000 $8,700.000 $23,731.110 $14,950.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,500.000 $4.000 $6.750 $3.530 $1.000 $7.350 $4.150 $10.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,500.000 $1.000 $3.000 $1.180 $1.000 $3.300 $1.190 $3.000
CABLE BARRIER SYSTEM (TL-4)
LF 159,006.000 $12.000 $5.750 $6.870 $8.440 $8.830 $8.450 $12.800
CABLE BARRIER TERMINAL SECTION (TL-4)
EA 164.000 $2,500.000 $4,500.000 $1,859.360 $1,500.000 $2,100.000 $2,936.870 $2,900.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $150.000 $18,000.000 $1.000 $1.000 $17,000.000 $8,899.160 $13,000.000
TMA (STATIONARY)
DAY 606.000 $200.000 $70.000 $1.000 $1.000 $165.000 $296.640 $300.000
Totals: $9,043,757.000 $6,830,728.000 $7,284,903.544 $7,323,035.840 $7,688,249.730 $9,485,585.730 $11,651,481.800