Job Info for 0071-02-032

County: MCCULLOCH Highway: US 87 Date: 03/07/2017 (7 years ago) Engineer's Estimate: $445,666 Control Number: 0071-02-032
Project: STP 2017(864)HES District: BROWNWOOD Time: 68 WORKING DAYS Type: PROFILE EDGELINE&CENTERLINE MARKING

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $445,666.21
STRIPE-A-ZONE, INC.   $285,999.99 1
-35.83% | -$159,666.22
TOTAL HIGHWAY MAINTENANCE, LLC   $295,661.70 2
-33.66% | -$150,004.51
3.38% | $9,661.71
D. I. J. CONSTRUCTION, INC.   $323,151.16 3
-27.49% | -$122,515.05
12.99% | $37,151.17
9.30% | $27,489.46
FLAT LINE, INC.   $328,972.00 4
-26.18% | -$116,694.21
15.03% | $42,972.01
1.80% | $5,820.84
L&L COMPANY   $372,108.90 5
-16.51% | -$73,557.31
30.11% | $86,108.91
13.11% | $43,136.90
TRP CONSTRUCTION GROUP, LLC   $378,037.84 6
-15.17% | -$67,628.37
32.18% | $92,037.85
1.59% | $5,928.94
BATTERSON, LLP   $422,820.96 7
-5.13% | -$22,845.25
47.84% | $136,820.97
11.85% | $44,783.12
STRIPE LINES, INC.   $549,790.34 8
23.36% | $104,124.13
92.23% | $263,790.35
30.03% | $126,969.38

Bid Items

Items: 6, 0 filtered
MCCULLOCH US 87  |  BROWNWOOD  |  0071-02-032  |  03/07/2017  |  $445,666  |  STP 2017(864)HES  |  PROFILE EDGELINE&CENTERLINE MRK  |  68 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate STRIPE-A-ZONE, INC. TOTAL HIGHWAY MAINTENANCE, LLC D. I. J. CONSTRUCTION, INC. FLAT LINE, INC. L&L COMPANY TRP CONSTRUCTION GROUP, LLC BATTERSON, LLP STRIPE LINES, INC.
500 6001 MOBILIZATION LS 1.000 $28,763.210 $508.000 $3,300.000 $4,000.000 $1.000 $1.000 $25,000.000 $14,000.000 $15,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 4.000 $1,500.000 $0.255 $500.000 $500.000 $1.000 $1.000 $1,500.000 $900.000 $4,000.000
666 6282 REF PROF PAV MRK TY I(W)4"(SLD)(060MIL) LF 774,582.000 $0.500 $0.335 $0.350 $0.380 $0.400 $0.450 $0.420 $0.480 $0.620
666 6287 REF PROF PAV MRK TY I(Y)4"(SLD)(090MIL) LF 33,280.000 $0.550 $0.450 $0.400 $0.500 $0.420 $0.450 $0.480 $0.620 $0.700
666 6291 REF PROF PAV MRK TY I(Y)4"(BRK)(090MIL) LF 4,480.000 $0.600 $1.000 $0.450 $0.500 $0.420 $0.450 $0.550 $1.100 $0.700
6056 6002 PREFORMED CENTERLINE RUMBLE STRIP LF 655.000 $4.000 $10.000 $6.000 $6.000 $5.000 $10.000 $5.000 $12.000 $18.500
Totals: $445,666.21 $285,999.99 $295,661.70 $323,151.16 $328,972.00 $372,108.90 $378,037.84 $422,820.96 $549,790.34