Show Job Controls
Bid Cobra

MAVERICK FM 375 (1229-04-015)

Items: 32

County: MAVERICK
Length: N/A
Highway: FM 375
District: LAREDO
Control Number: 1229-04-015
DBE Goal: N/A
Project: STP 2B20(132)HES
Guaranty: N/A
Time: 120 WORKING DAYS
Engineer's Estimate: $3,473,239.37
Date: 08/06/2020 (5 years ago)
Contract Number: N/A
Type: CONCRETE RAISED MEDIAN
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$3,473,239.37
$3,474,239.85
Over/Under Est: 0.03% $1,000.48
Over/Under Est: 6.26% $217,332.98
Amt Left: 6.23% $216,332.50
Over/Under Est: 14.94% $518,877.83
Amt Left: 14.91% $517,877.35
Delta: -8.17% -$301,544.85
$4,574,394.50
Over/Under Est: 31.7% $1,101,155.13
Amt Left: 31.67% $1,100,154.65
Delta: -14.59% -$582,277.30

Bid Items & Bid Tabulations

32 Total 0 of 32
MAVERICK  |  FM 375  |  LAREDO  |  1229-04-015  |  08/06/2020  |  $3,473,239.37  |  STP 2B20(132)HES  |  CONC RAISED MEDIAN  |  120 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
VECTOR UTILITIES LLC
TRP CONSTRUCTION GROUP, LLC
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
FNH CONSTRUCTION, LLC
RIPRAP (CONC)(6 IN)
CY 3,466.000 $680.000 $474.020 $450.000 $549.940 $650.000
MOBILIZATION
LS 1.000 $311,385.400 $296,400.000 $350,000.000 $496,111.250 $450,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $8,000.000 $4,600.000 $5,500.000 $7,718.340 $8,500.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 2,540.000 $6.200 $6.260 $7.500 $12.610 $18.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 2,540.000 $1.600 $1.250 $2.500 $2.730 $9.000
CONC CURB (MONO) (TY II)
LF 53,716.000 $7.900 $23.380 $11.750 $23.580 $25.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 18.000 $555.000 $657.210 $1,000.000 $584.980 $850.000
REMOVE SM RD SN SUP&AM
EA 1.000 $94.000 $118.920 $2,500.000 $239.070 $250.000
REFL PAV MRK TY I (W)8"(DOT)(060MIL)
LF 710.000 $1.230 $1.250 $5.000 $1.290 $2.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 11,979.000 $0.840 $0.880 $5.000 $0.790 $1.000
REFL PAV MRK TY I (W)24"(SLD)(060MIL)
LF 3,532.000 $8.600 $6.010 $25.000 $5.430 $6.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 64.000 $145.000 $156.480 $250.000 $145.910 $150.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 64.000 $160.000 $156.480 $250.000 $145.910 $150.000
PAVEMENT SEALER 4"
LF 54,259.000 $0.200 $0.160 $2.500 $0.150 $0.500
PAVEMENT SEALER 8"
LF 11,979.000 $1.060 $0.460 $5.000 $0.430 $0.500
PAVEMENT SEALER (ARROW)
EA 64.000 $39.000 $75.110 $250.000 $70.210 $100.000
PAVEMENT SEALER (WORD)
EA 64.000 $51.000 $75.110 $250.000 $70.210 $100.000
RE PM W/RET REQ TY I (W)4"(SLD)(060MIL)
LF 54,914.000 $0.200 $0.480 $3.000 $0.440 $0.500
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 54,259.000 $0.330 $0.480 $3.000 $0.440 $0.500
REFL PAV MRKR TY II-C-R
EA 359.000 $4.000 $6.260 $10.000 $5.870 $6.000
ELIM EXT PAV MRK & MRKS (4")
LF 66,754.000 $1.400 $0.380 $3.000 $0.350 $0.500
ELIM EXT PAV MRK & MRKS (8")
LF 2,908.000 $1.290 $1.160 $5.000 $1.210 $1.000
ELIM EXT PAV MRK & MRKS (24")
LF 422.000 $4.700 $3.760 $10.000 $3.620 $5.000
ELIM EXT PAV MRK & MRKS (ARROW)
EA 12.000 $72.000 $65.100 $200.000 $68.410 $100.000
ELIM EXT PAV MRK & MRKS (WORD)
EA 6.000 $72.000 $65.100 $200.000 $79.630 $100.000
PAV SURF PREP FOR MRK (4")
LF 54,259.000 $0.090 $0.060 $0.050 $0.070 $0.500
PAV SURF PREP FOR MRK (8")
LF 11,979.000 $0.130 $0.150 $0.100 $0.150 $0.500
PAV SURF PREP FOR MRK (ARROW)
EA 64.000 $15.000 $62.590 $25.000 $59.210 $100.000
PAV SURF PREP FOR MRK (WORD)
EA 64.000 $20.000 $62.590 $25.000 $59.210 $100.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $24,000.000 $7,040.000 $5,000.000 $13,017.420 $16,500.000
LONG CHANNEL MOUNT CURB SYS (REMOVE)
LF 934.000 $10.000 $12.150 $20.000 $11.340 $100.000
TMA (STATIONARY)
DAY 70.000 $225.000 $275.000 $1,000.000 $386.920 $350.000
Totals: $3,473,239.370 $3,474,239.850 $3,690,572.350 $3,992,117.200 $4,574,394.500