Bid Cobra

MAVERICK US 277 (0300-01-105)

Items: 86

County: MAVERICK
Length: N/A
Highway: US 277
District: LAREDO
Control Number: 0300-01-105
DBE Goal: N/A
Project: F 2022(104)
Guaranty: N/A
Time: 274 WORKING DAYS
Engineer's Estimate: $7,033,199.85
Date: 11/04/2021 (4 years ago)
Contract Number: N/A
Type: GRADE,BASE,ACP,SURF,STR,PAV MRK
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (3)
E
Engineer's Estimate
$7,033,199.85
$5,512,871.65
Over/Under Est: -21.62% -$1,520,328.20
Over/Under Est: -13.34% -$937,883.19
Amt Left: 10.57% $582,445.01
$6,491,105.71
Over/Under Est: -7.71% -$542,094.14
Amt Left: 17.74% $978,234.06
Delta: -6.49% -$395,789.05

Bid Items & Bid Tabulations

86 Total 0 of 86
MAVERICK  |  US 277  |  LAREDO  |  0300-01-105  |  11/04/2021  |  $7,033,199.85  |  F 2022(104)  |  GRADE,BASE,ACP,SURF,STR,PAV MRK  |  274 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ANDERSON COLUMBIA CO., INC.
HUNTER INDUSTRIES, LTD.
FARIS INDUSTRIES, INC.
PREPARING ROW
STA 242.000 $5,000.000 $500.000 $1,449.160 $642.620
EXCAVATION (ROADWAY)
CY 15,523.000 $9.000 $15.000 $20.160 $13.850
EMBANKMENT (FINAL)(ORD COMP)(TY A)
CY 12,226.000 $17.000 $12.000 $16.830 $13.150
DRILL SEEDING (PERM) (RURAL) (CLAY)
AC 16.900 $615.000 $1,500.000 $1,353.000 $1,425.000
DRILL SEEDING (TEMP) (WARM)
AC 16.900 $550.000 $1,100.000 $990.000 $1,100.000
PROOF ROLLING
HR 18.000 $150.000 $85.000 $102.600 $63.900
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 12,203.000 $90.000 $63.000 $70.240 $63.240
REWORK BS MTL (TY C) (6") (DENS CONT)
SY 45,697.000 $2.500 $2.000 $2.850 $1.700
PRIME COAT (MC-30)
GAL 8,677.000 $4.500 $4.500 $5.230 $4.980
PLANE ASPH CONC PAV (2")
SY 50,922.000 $1.250 $2.000 $1.510 $1.270
CUT & RESTORING PAV
SY 81.000 $125.000 $230.000 $202.680 $200.000
FLOWABLE BACKFILL
CY 90.000 $200.000 $180.000 $178.500 $170.000
TEMPORARY SPL SHORING
SF 6,157.000 $30.000 $10.000 $8.920 $8.500
CONC BOX CULV (3 FT X 2 FT)(EXTEND)
LF 38.000 $500.000 $500.000 $498.740 $475.000
CONC BOX CULV (4 FT X 3 FT)(EXTEND)
LF 8.000 $850.000 $610.000 $603.740 $575.000
CONC BOX CULV (5 FT X 5 FT)(EXTEND)
LF 17.000 $900.000 $650.000 $656.240 $625.000
CONC BOX CULV (6 FT X 5 FT)(EXTEND)
LF 10.000 $550.000 $700.000 $682.490 $650.000
RC PIPE (CL III)(24 IN)
LF 271.000 $65.000 $80.000 $78.750 $75.000
RC PIPE (CL III)(30 IN)
LF 68.000 $90.000 $100.000 $99.750 $95.000
WINGWALL (PW - 1) (HW=4 FT)
EA 2.000 $12,610.000 $9,000.000 $8,924.910 $8,500.000
WINGWALL (PW - 1) (HW=5 FT)
EA 1.000 $19,000.000 $14,000.000 $13,124.860 $12,250.000
WINGWALL (PW - 1) (HW=7 FT)
EA 2.000 $21,500.000 $19,000.000 $18,374.810 $17,500.000
SET (TY I)(S=3 FT)(HW=3FT)(4:1)(C)
EA 4.000 $7,800.000 $5,000.000 $4,777.450 $4,550.000
SET (TY I)(S= 4 FT)(HW= 6 FT)(4:1) (C)
EA 1.000 $7,000.000 $6,000.000 $5,722.440 $5,450.000
SET (TY I)(S= 5 FT)(HW= 7 FT)(4:1) (C)
EA 4.000 $7,665.000 $7,000.000 $6,982.430 $6,650.000
SET (TY I)(S= 6 FT)(HW= 7 FT)(4:1) (C)
EA 2.000 $8,480.000 $8,000.000 $7,874.920 $7,500.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 4.000 $1,500.000 $1,500.000 $1,417.490 $1,350.000
SET (TY II) (24 IN) (RCP) (6: 1) (C)
EA 4.000 $1,500.000 $2,000.000 $1,942.480 $1,850.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 2.000 $1,330.000 $2,000.000 $1,942.480 $1,850.000
SET (TY II) (30 IN) (RCP) (6: 1) (C)
EA 2.000 $2,800.000 $3,500.000 $3,517.460 $3,350.000
REMOV STR (SET)
EA 4.000 $840.000 $500.000 $472.500 $450.000
REMOV STR (WINGWALL)
EA 14.000 $1,325.000 $2,000.000 $2,099.980 $2,000.000
REMOV STR (HEADWALL)
EA 2.000 $1,300.000 $2,000.000 $2,099.980 $2,000.000
REMOV STR (PIPE)
LF 297.000 $16.000 $15.000 $15.750 $15.000
MOBILIZATION
LS 1.000 $611,832.150 $534,000.000 $604,384.800 $714,021.660
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 14.000 $3,500.000 $4,500.000 $1,733.290 $2,550.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 308.000 $60.000 $57.000 $97.000 $56.750
ROCK FILTER DAMS (REMOVE)
LF 308.000 $12.000 $36.000 $25.580 $36.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 468.000 $20.000 $33.000 $25.850 $32.950
CONSTRUCTION EXITS (REMOVE)
SY 468.000 $8.000 $19.000 $9.540 $18.950
BACKHOE WORK (EROSION & SEDMT CONT)
HR 75.000 $70.000 $94.000 $91.200 $70.290
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,935.000 $3.000 $4.000 $4.220 $3.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,935.000 $1.000 $1.500 $0.750 $1.250
ONE-WAY TRAF CONT (PILOT CAR)
HR 168.000 $95.000 $150.000 $102.600 $84.010
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 2.000 $3,550.000 $9,000.000 $9,478.290 $5,200.000
PTB (FRN&INSTL)(SGL SLP)(TY 1) OR (STL)
LF 120.000 $60.000 $68.000 $74.150 $30.000
PTB (MOVE)(SGL SLP)(TY 1) OR (STL)
LF 1,200.000 $4.600 $54.000 $49.790 $18.000
PTB (REMOVE)(SGL SLP)(TY 1) OR (STL)
LF 120.000 $8.150 $54.000 $55.280 $10.000
DRIVEWAYS (CONC)
SY 168.000 $100.000 $110.000 $105.000 $106.390
DRIVEWAYS (ACP)
SY 447.000 $45.000 $68.000 $52.560 $54.640
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 40,180.000 $0.500 $0.140 $0.060 $0.140
RUMBLE STRIPS (CENTERLINE) ASPHALT
LF 10,580.000 $0.500 $0.460 $0.240 $0.160
CRASH CUSH ATTEN (MOVE & RESET)
EA 20.000 $1,575.000 $1,600.000 $1,500.000 $1,000.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $5,000.000 $800.000 $700.000 $710.500
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $400.000 $10,000.000 $9,800.000 $6,850.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 9.000 $550.000 $600.000 $715.000 $550.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 7.000 $550.000 $650.000 $920.000 $635.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 6.000 $550.000 $1,200.000 $1,020.000 $1,000.000
REMOVE SM RD SN SUP&AM
EA 9.000 $90.000 $250.000 $120.000 $150.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 20.000 $20.000 $30.000 $10.000 $25.000
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
EA 20.000 $75.000 $95.000 $88.000 $85.000
WK ZN PAV MRK REMOV (REFL) TY I-C
EA 8,836.000 $4.500 $2.500 $2.500 $4.000
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 7,733.000 $4.500 $2.500 $2.500 $4.000
WK ZN PAV MRK REMOV (TRAF BTN) TY W
EA 35,346.000 $5.000 $2.500 $2.500 $3.000
WK ZN PAV MRK REMOV (TRAF BTN) TY Y
EA 35,253.000 $5.000 $2.500 $2.500 $3.000
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 96.000 $8.500 $10.000 $10.000 $8.000
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 21,600.000 $0.750 $1.500 $1.500 $1.830
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 1,584.000 $1.000 $2.000 $1.410 $1.590
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 2,112.000 $1.000 $2.000 $1.410 $1.590
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
LF 1,147.000 $0.600 $2.500 $2.500 $1.000
REFL PAV MRK TY I(W)(LNDP ARW)(100MIL)
EA 6.000 $300.000 $0.500 $350.000 $477.000
PAVEMENT SEALER 4"
LF 62,086.000 $0.250 $0.200 $0.200 $0.150
PAVEMENT SEALER (LNDP ARROW)
EA 6.000 $60.000 $100.000 $100.000 $244.000
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 6,961.000 $0.500 $0.450 $0.450 $0.500
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 40,940.000 $0.500 $0.450 $0.450 $0.450
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 55,730.000 $0.500 $0.450 $0.450 $0.450
REFL PAV MRKR TY I-C
EA 333.000 $5.000 $5.000 $5.000 $4.300
REFL PAV MRKR TY II-A-A
EA 699.000 $5.000 $5.000 $5.000 $4.300
ELIM EXT PAV MRK & MRKS (4")
LF 171,960.000 $0.700 $0.250 $0.250 $0.630
D-GR HMA TY-B SAC-B PG70-22
TON 12,703.000 $80.000 $80.000 $86.670 $104.370
SP MIXES SP-C SAC-A PG76-22
TON 10,799.000 $90.000 $102.000 $103.470 $156.110
BONDING COURSE
GAL 9,453.000 $3.000 $4.000 $4.060 $3.640
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $15,000.000 $7,500.000 $8,600.000
PREFORMED IN-LANE(TRANS) RUMBLE STRIP
LF 1,920.000 $14.750 $25.000 $25.000 $14.000
TMA (STATIONARY)
DAY 244.000 $150.000 $200.000 $300.000 $170.000
TMA (MOBILE OPERATION)
HR 196.000 $90.000 $67.000 $100.000 $54.000
Totals: $7,033,199.850 $5,512,871.650 $6,095,316.660 $6,491,105.710