Job Info for 0917-31-034

County: MADISON Highway: CR Date: 06/02/2023 (1 year ago) Engineer's Estimate: $657,162 Control Number: 0917-31-034
Project: BR 2021(239) District: BRYAN Time: 153 WORKING DAYS Type: BRIDGE REPLACEMENT
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $657,161.96
R CONSTRUCTION CIVIL, LLC   $669,117.60 1
1.82% | $11,955.64
SEFBO PIPELINE BRIDGE, INCORPORATED   $707,228.67 2
7.62% | $50,066.71
5.7% | $38,111.07
TEXAS MATERIALS GROUP, INC.   $839,727.60 3
27.78% | $182,565.64
25.5% | $170,610.00
18.73% | $132,498.93
Subcontractor Percentage Amount
MORRIS COUNTY CONTRACTORS, L.L.C. 3.08% $20,608.82
BUYERS BARRICADES HOUSTON, LLC 1.53% $10,237.50
PENHALL COMPANY 1.09% $7,293.38
HERMANOS STEEL, LLC 0.88% $5,888.23
HIGHWAY 1 LLC 0.68% $4,550.00
SEMARCK LANDSCAPE SERVICES, INC. 0.63% $4,215.44
Total: 7.89% $52,793.37

Bid Items

Items: 40, 0 filtered
MADISON CR  |  BRYAN  |  0917-31-034  |  06/02/2023  |  $657,162  |  BR 2021(239)  |  BRIDGE REPL  |  153 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate R CONSTRUCTION CIVIL, LLC SEFBO PIPELINE BRIDGE, INCORPORATED TEXAS MATERIALS GROUP, INC.
100 6002 PREPARING ROW STA 3.650 $6,000.000 $10,000.000 $10,542.610 $20,000.000
110 6001 EXCAVATION (ROADWAY) CY 149.000 $30.000 $25.000 $20.130 $100.000
110 6002 EXCAVATION (CHANNEL) CY 37.040 $55.000 $25.000 $71.270 $130.000
132 6005 EMBANKMENT (FINAL)(ORD COMP)(TY C) CY 166.000 $45.000 $25.000 $85.080 $90.000
160 6003 FURNISHING AND PLACING TOPSOIL (4") SY 732.000 $5.500 $4.000 $10.330 $6.000
164 6001 BROADCAST SEED (PERM) (RURAL) (SANDY) SY 732.000 $1.100 $1.000 $0.700 $1.500
164 6009 BROADCAST SEED (TEMP) (WARM) SY 366.000 $1.200 $0.800 $1.210 $1.500
164 6011 BROADCAST SEED (TEMP) (COOL) SY 366.000 $1.100 $0.800 $1.210 $1.500
168 6001 VEGETATIVE WATERING MG 15.000 $350.000 $41.000 $104.000 $50.000
169 6003 SOIL RETENTION BLANKETS (CL 1) (TY C) SY 131.000 $4.200 $4.000 $77.310 $2.000
247 6064 FL BS (CMP IN PLC)(TY A GR 4) (6") SY 916.000 $25.000 $35.000 $22.860 $29.000
400 6005 CEM STABIL BKFL CY 34.000 $240.000 $250.000 $229.380 $350.000
416 6002 DRILL SHAFT (24 IN) LF 393.000 $240.000 $365.000 $317.990 $418.000
420 6013 CL C CONC (ABUT) CY 21.000 $1,600.000 $2,500.000 $2,401.820 $2,200.000
420 6029 CL C CONC (CAP) CY 6.900 $1,900.000 $2,500.000 $2,638.860 $3,500.000
420 6037 CL C CONC (COLUMN) CY 2.100 $2,000.000 $2,800.000 $5,929.070 $5,000.000
422 6007 REINF CONC SLAB (SLAB BEAM) SF 2,080.000 $30.000 $30.000 $26.290 $39.000
425 6012 PRESTR CONC SLAB BEAM (5SB15) LF 394.920 $285.000 $250.000 $272.310 $260.000
432 6033 RIPRAP (STONE PROTECTION)(18 IN) CY 163.000 $240.000 $210.000 $145.630 $234.000
450 6006 RAIL (TY T223) LF 184.000 $175.000 $130.000 $173.280 $195.000
454 6004 ARMOR JOINT (SEALED) LF 46.000 $175.000 $100.000 $200.730 $160.000
496 6009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) EA 1.000 $30,000.000 $25,000.000 $63,600.000 $19,000.000
500 6001 MOBILIZATION LS 1.000 $55,110.160 $65,000.000 $60,000.000 $80,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 8.000 $6,000.000 $1,800.000 $225.000 $5,000.000
506 6002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 85.000 $45.000 $39.000 $41.290 $42.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 85.000 $17.000 $2.000 $8.470 $12.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 888.000 $5.250 $4.000 $4.250 $3.900
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 888.000 $1.900 $1.000 $0.410 $1.250
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 75.000 $30.000 $22.000 $156.260 $32.000
540 6007 MTL BEAM GD FEN TRANS (TL2) EA 4.000 $1,500.000 $1,200.000 $720.000 $1,500.000
540 6014 SHORT RADIUS LF 45.000 $140.000 $55.000 $25.200 $56.000
540 6015 DRIVEWAY TERMINAL ANCHOR SECTION EA 1.000 $1,200.000 $1,200.000 $480.000 $1,000.000
540 6039 MTL BM GD FEN TRANS (31"-28")(25') EA 1.000 $700.000 $600.000 $480.000 $750.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 3.000 $3,400.000 $3,241.000 $2,544.000 $3,000.000
550 6022 GATE (INSTALL)(DOUBLE)(6' X 16') EA 1.000 $3,500.000 $756.000 $5,040.000 $2,500.000
644 6056 IN SM RD SN SUP&AM TYTWT(1)UA(P) EA 4.000 $710.000 $66.000 $360.000 $550.000
644 6076 REMOVE SM RD SN SUP&AM EA 2.000 $150.000 $110.000 $120.000 $150.000
658 6014 INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) EA 8.000 $35.000 $25.000 $61.050 $25.000
658 6046 INSTL OM ASSM (OM-2X)(WC)GND EA 6.000 $90.000 $80.000 $112.000 $65.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 8.000 $45.000 $28.000 $60.000 $35.000
Totals: $657,161.96 $669,117.60 $707,228.69 $839,727.60