Show Job Controls
Bid Cobra

LUBBOCK 13TH ST (0905-06-121)

Items: 51

County: LUBBOCK
Length: 0.0010 MILES (0.0015 MILES)
Highway: 13TH ST
District: LUBBOCK
Control Number: 0905-06-121
DBE Goal: 0.0%
Project: STP 2025(788)VRUG
Guaranty: $8,000.00
Time: 37 WORKING DAYS
Engineer's Estimate: $376,554.75
Date: 07/01/2026 1:00 PM CDT (17 days ago)
Contract Number: 7263032
Type: TRAFFIC SIGNAL IMPROVEMENTS
Project ID: A00184345
Contract Type: FEDERAL
Project Description: IMPROVE TRAFFIC SIGNALS, INSTALL FLASHING YELLOW ARROW
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
MIKE STROOPE
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$376,554.75
Over/Under Est: -12.81% -$48,254.85
Over/Under Est: -4.62% -$17,408.81
Amt Left: 9.4% $30,846.04
$369,037.86
Over/Under Est: -2% -$7,516.89
Amt Left: 12.41% $40,737.96
Delta: -2.75% -$9,891.92

Bid Items & Bid Tabulations

51 Total 0 of 51
LUBBOCK  |  13TH ST  |  LUBBOCK  |  0905-06-121  |  07/01/2026 1:00 PM CDT  |  $376,554.75  |  STP 2025(788)VRUG  |  TRAF SIGNAL IMPRVS  |  37 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
VACA UNDERGROUND UTILITIES INC
APOLLO CONSTRUCTORS, INC.
JASCO
REMOV CONC (SIDEWALK, RAMP OR SUP)
SY 161.000 $25.000 $18.000 $17.390 $32.000
DRILL SHAFT (24 IN)
LF 24.000 $370.000 $250.000 $55.000 $230.150
DRILL SHAFT (TRF SIG POLE) (36 IN)
LF 56.000 $550.000 $300.000 $435.000 $415.000
MOBILIZATION
LS 1.000 $34,000.000 $30,000.000 $36,000.000 $55,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $5,000.000 $3,500.000 $3,898.000 $1,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 74.000 $60.000 $65.000 $135.000 $110.110
TMA (STATIONARY)
DAY 74.000 $300.000 $150.000 $100.000 $228.150
SANDBAGS FOR EROSION CONTROL
EA 8.000 $50.000 $25.000 $27.000 $10.290
CONC SIDEWALKS (5")
SY 62.000 $100.000 $65.000 $65.690 $200.000
CURB RAMPS (TY 5)
SY 99.000 $300.000 $325.000 $241.380 $480.000
CONDT (PVC) (SCH 80) (2")
LF 100.000 $20.000 $15.000 $21.000 $18.500
CONDT (PVC) (SCH 80) (4")
LF 90.000 $37.000 $20.000 $35.350 $28.500
CONDT (PVC) (SCH 80) (4") (BORE)
LF 225.000 $49.000 $25.000 $47.890 $38.000
ELEC CONDR (NO.6) BARE
LF 350.000 $4.000 $2.550 $2.680 $2.500
ELEC CONDR (NO.2) INSULATED
LF 120.000 $5.500 $5.000 $3.750 $3.450
GROUND BOX TY D (162922)
EA 6.000 $1,725.000 $1,000.000 $1,500.000 $1,314.890
GROUND BOX TY D (162922)W/APRON
EA 1.000 $2,750.000 $1,450.000 $1,985.000 $1,600.600
REMOVE GROUND BOX
EA 4.000 $400.000 $500.000 $750.000 $422.660
REMOVE ELECTRICAL SERVICES
EA 1.000 $1,100.000 $500.000 $875.000 $816.120
ELC SRV TY D 120/240 060(NS)SS(N)SP(O)
EA 1.000 $8,500.000 $10,000.000 $9,350.000 $5,500.000
ALUMINUM SIGNS (TY A)
SF 30.000 $42.000 $40.000 $35.000 $42.400
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 1.000 $900.000 $1,000.000 $500.000 $642.260
PREFAB PM TY B (W)(24")(SLD)
LF 24.000 $40.000 $32.000 $50.000 $32.230
PREFAB PM TY C (W)(8")(SLD)
LF 600.000 $6.500 $10.500 $8.000 $5.500
PREFAB PM TY C (W)(24")(SLD)
LF 296.000 $18.000 $15.000 $20.000 $16.090
PREFAB PM TY C (W)(ARROW)
EA 8.000 $250.000 $325.000 $325.000 $228.950
ELIM EXT PM & MRKS (8")
LF 600.000 $2.850 $0.900 $3.000 $2.450
ELIM EXT PM & MRKS (24")
LF 296.000 $3.000 $0.900 $6.000 $4.650
ELIM EXT PM & MRKS (ARROW)
EA 6.000 $95.000 $25.000 $125.000 $80.240
INSTALL HWY TRF SIG (ISOLATED)
EA 1.000 $30,000.000 $40,000.000 $38,892.000 $34,119.000
REMOVING TRAFFIC SIGNALS
EA 1.000 $8,750.000 $5,000.000 $9,856.000 $6,845.900
VEH SIG SEC (12")LED(GRN)
EA 11.000 $375.000 $350.000 $385.250 $346.150
VEH SIG SEC (12")LED(GRN ARW)
EA 4.000 $375.000 $350.000 $385.250 $356.950
VEH SIG SEC (12")LED(YEL)
EA 11.000 $375.000 $350.000 $385.250 $336.850
VEH SIG SEC (12")LED(YEL ARW)
EA 8.000 $375.000 $350.000 $385.250 $345.250
VEH SIG SEC (12")LED(RED)
EA 11.000 $375.000 $350.000 $385.250 $332.800
VEH SIG SEC (12")LED(RED ARW)
EA 4.000 $375.000 $350.000 $385.250 $339.150
PED SIG SEC (LED)(COUNTDOWN)
EA 8.000 $1,000.000 $600.000 $921.000 $712.990
BACKPLATE W/REF BRDR(3 SEC)(VENT)ALUM
EA 11.000 $250.000 $225.000 $225.000 $201.950
BACKPLATE W/REF BRDR(4 SEC)(VENT)ALUM
EA 4.000 $275.000 $275.000 $245.000 $245.660
TRF SIG CBL (TY A)(12 AWG)(2 CONDR)
LF 925.000 $2.850 $3.000 $2.250 $2.450
TRF SIG CBL (TY A)(12 AWG)(4 CONDR)
LF 40.000 $5.300 $3.500 $3.650 $2.800
TRF SIG CBL (TY A)(12 AWG)(5 CONDR)
LF 325.000 $4.100 $5.000 $3.980 $3.250
TRF SIG CBL (TY A)(12 AWG)(7 CONDR)
LF 330.000 $4.500 $6.000 $4.170 $4.250
TRF SIG CBL (TY A)(12 AWG)(20 CONDR)
LF 460.000 $9.250 $15.000 $7.690 $9.100
INS TRF SIG PL AM (S)1 ARM(28')
EA 1.000 $10,000.000 $12,600.000 $12,183.000 $11,245.780
INS TRF SIG PL AM(S)1 ARM(32')
EA 1.000 $13,000.000 $13,500.000 $13,465.000 $11,789.870
INS TRF SIG PL AM(S)1 ARM(40')
EA 2.000 $15,250.000 $17,000.000 $17,964.000 $13,546.760
PED POLE ASSEMBLY
EA 4.000 $4,000.000 $2,000.000 $4,958.000 $2,612.340
INSTALL OF CABLES
LF 870.000 $2.900 $3.000 $2.250 $5.050
INSTALL OF PEDESTRIAN PUSH BUTTONS
EA 8.000 $595.000 $500.000 $150.000 $355.000
Totals: $376,554.750 $328,299.900 $359,145.940 $369,037.860
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
PUBLIC UTILITY FORCE ACCT WORK (PART) $3,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $1.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $2,000.00
MATERIALS FURNISHED BY CITY (PART) $77,000.00
Total: $82,001.00