Bid Cobra

LUBBOCK US 87 (0068-01-074)

Items: 141

County: LUBBOCK
Length: N/A
Highway: US 87
District: LUBBOCK
Control Number: 0068-01-074
DBE Goal: N/A
Project: C 68-1-74
Guaranty: N/A
Time: 547 WORKING DAYS
Engineer's Estimate: $22,111,420.10
Date: 08/05/2021 (4 years ago)
Contract Number: N/A
Type: CONSTRUCT BRIDGE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (5)
E
Engineer's Estimate
$22,111,420.10
$21,657,408.59
Over/Under Est: -2.05% -$454,011.51
$21,770,390.23
Over/Under Est: -1.54% -$341,029.87
Amt Left: 0.52% $112,981.64
Over/Under Est: 1.48% $328,040.90
Amt Left: 3.61% $782,052.41
Delta: -3.07% -$669,070.77
$23,461,324.25
Over/Under Est: 6.11% $1,349,904.15
Amt Left: 8.33% $1,803,915.66
Delta: -4.55% -$1,021,863.25
$23,889,089.00
Over/Under Est: 8.04% $1,777,668.90
Amt Left: 10.3% $2,231,680.41
Delta: -1.82% -$427,764.75
Subcontractor Percentage Amount
URBAN INFRACONSTRUCTION LLC 4.71% $1,047,423.26
D & E LOGISTICS, LLC 3.57% $793,906.81
INDUSTRIAL FABRICS, INC. 1.32% $293,545.37
WAYNE BRYANT TRANSPORT, LLC 1.24% $275,754.74
ARTEX ELECTRIC, INC. 1.24% $275,754.74
BARRICADES UNLIMITED 0.93% $206,816.06
TEXOP CONSTRUCTION 0.73% $162,339.49
KELLER NORTH AMERICA, INC. 0.58% $128,982.06
TORO BRAVO CONSTRUCTION, LLC 0.56% $124,534.40
K.A. FARMER TRUCKING, INC. 0.12% $26,685.94
J. H. ODEN CONTRACTING COMPANY 0.12% $26,685.94
PRIMATE CONSTRUCTION, LP 0.05% $11,119.14
SCOTT DERR PAINTING CO, LLC 0.04% $8,895.31
WESTEX COOPERATIVE GIN 0.04% $8,895.31
JRS UNLIMITED, LLC 0.04% $8,895.31
DE NOVO TRUCKING, LLC 0.04% $8,895.31
PINNACLE GRINDING AND GROOVING LLC 0.03% $6,671.49
GORMAN OUTDOOR, INC. 0.02% $4,447.66
Total: 15.38% $3,420,248.34

Bid Items & Bid Tabulations

141 Total 0 of 141
LUBBOCK  |  US 87  |  LUBBOCK  |  0068-01-074  |  08/05/2021  |  $22,111,420.10  |  C 68-1-74  |  CONSTRUCT BRIDGE  |  547 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ALLEN BUTLER CONSTRUCTION, INC.
FNF CONSTRUCTION, INC.
SACYR CONSTRUCTION USA LLC
DUININCK, INC.
WEBBER, LLC
PREPARING ROW
STA 65.000 $1,000.000 $1,865.500 $160.000 $10,000.000 $695.000 $31,000.000
REMOVING CONC (PAV)
SY 11,221.000 $10.000 $11.750 $6.000 $10.000 $9.750 $15.000
REMOVE STAB BASE & ASPH PAV (13"-18")
SY 61,924.000 $6.000 $5.250 $5.500 $8.000 $6.650 $4.600
EXCAVATION (ROADWAY)
CY 58,834.000 $8.000 $7.250 $4.800 $6.000 $8.250 $10.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 87,697.000 $15.000 $5.750 $39.000 $30.000 $32.250 $10.000
DRILL SEEDING (PERM) (RURAL) (SANDY)
SY 78,173.000 $0.200 $0.200 $0.150 $0.200 $0.090 $1.250
VEGETATIVE WATERING
MG 32.000 $50.000 $226.500 $32.000 $40.000 $26.500 $40.000
PROOF ROLLING
HR 50.000 $100.000 $136.250 $85.000 $140.000 $145.000 $162.000
FL BS (CMP IN PLC)(TY A GR 4) (6")
SY 87,228.000 $9.000 $10.000 $8.500 $14.000 $11.500 $9.750
PRIME COAT (MC-30)
GAL 17,446.000 $5.000 $4.750 $4.500 $10.000 $4.150 $4.050
EMULS ASPH (EROSN CONT)(CSS-1H)
GAL 14,071.000 $5.000 $5.250 $3.500 $10.000 $5.050 $4.000
FOG SEAL (CSS-1H)
GAL 14,420.000 $5.000 $5.250 $3.500 $10.000 $4.250 $2.750
ASPH (AC-20-5TR)
GAL 12,682.000 $5.000 $4.750 $3.500 $10.000 $4.600 $2.450
AGGR(TY-PB GR-4 SAC-B)
CY 288.000 $200.000 $371.750 $120.000 $130.000 $175.000 $85.000
STONE-MTRX-ASPH SMA-D SAC-A PG70-28
TON 10,044.000 $140.000 $154.500 $110.000 $120.000 $170.000 $129.000
TACK COAT
GAL 4,468.000 $5.000 $5.500 $5.000 $10.000 $3.350 $3.750
FLEXIBLE PAVEMENT STRUCTURE REPAIR(3")
SY 3,100.000 $30.000 $7.500 $20.000 $55.000 $37.000 $16.600
CEM STABIL BKFL
CY 1,294.600 $150.000 $114.250 $150.000 $97.000 $230.000 $88.750
TRENCH EXCAVATION PROTECTION
LF 148.000 $25.000 $25.250 $10.000 $10.000 $54.000 $5.400
DRILL SHAFT (36 IN)
LF 1,802.000 $220.000 $235.500 $260.000 $150.000 $235.000 $189.000
DRILL SHAFT (SIGN MTS) (12 IN)
LF 14.000 $150.000 $164.750 $115.000 $190.000 $120.000 $151.000
DRILL SHAFT (SIGN MTS) (24 IN)
LF 22.000 $175.000 $221.750 $160.000 $225.000 $165.000 $233.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 128.000 $200.000 $190.000 $155.000 $155.000 $160.000 $254.000
CL C CONC (ABUT)(HPC)
CY 82.000 $1,300.000 $1,499.500 $1,200.000 $1,000.000 $1,100.000 $1,010.000
CL C CONC (CAP)(HPC)
CY 78.200 $1,300.000 $2,399.500 $2,000.000 $900.000 $1,100.000 $1,100.000
CL C CONC (COLUMN)(HPC)
CY 67.000 $1,300.000 $1,630.500 $1,500.000 $1,700.000 $1,200.000 $1,190.000
CL C CONC (RAIL FOUNDATION)
CY 73.300 $600.000 $523.750 $700.000 $450.000 $920.000 $360.000
REINF CONC SLAB
SF 22,480.000 $25.000 $31.500 $20.000 $19.000 $21.500 $23.100
APPROACH SLAB
CY 240.800 $600.000 $754.000 $600.000 $450.000 $650.000 $569.000
RETAINING WALL (MSE)
SF 69,007.000 $50.000 $55.500 $31.000 $37.000 $40.000 $58.000
PRESTR CONC GIRDER (TX46)
LF 2,794.400 $150.000 $176.000 $210.000 $175.000 $195.000 $215.000
SILICONE RESIN PAINT FINISH
SF 185.000 $30.000 $34.250 $30.000 $27.000 $32.500 $10.800
RIPRAP (CONC)(4 IN)
CY 2,793.000 $600.000 $481.750 $550.000 $387.000 $565.000 $500.000
RIPRAP (CONC)(5 IN)
CY 0.600 $800.000 $1,784.880 $2,500.000 $1,900.000 $2,200.000 $2,160.000
RAIL (TY SSTR)
LF 5,060.000 $60.000 $63.750 $70.000 $60.000 $56.500 $65.000
RAIL (TY SSTR)(HPC)
LF 562.000 $80.000 $111.250 $100.000 $75.000 $92.000 $69.000
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 174.000 $200.000 $150.500 $170.000 $170.000 $160.000 $124.000
RC PIPE (CL III)(24 IN)
LF 1,176.000 $90.000 $115.000 $100.000 $120.000 $130.000 $110.000
RC PIPE (CL III)(30 IN)
LF 914.000 $150.000 $140.500 $120.000 $160.000 $180.000 $145.000
INLET (COMPL)(PSL)(RC)(3FTX3FT)
EA 1.000 $6,000.000 $4,055.000 $5,300.000 $5,500.000 $5,400.000 $9,056.650
INLET (COMPL)(PSL)(SH)(3FTX3FT-3FTX3FT)
EA 5.000 $5,000.000 $4,599.750 $7,200.000 $5,800.000 $5,900.000 $7,750.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 4.000 $1,400.000 $2,110.250 $2,000.000 $2,300.000 $1,600.000 $1,632.000
SET (TY II) (24 IN) (RCP) (6: 1) (C)
EA 28.000 $1,500.000 $2,338.250 $2,200.000 $2,600.000 $1,700.000 $2,160.000
SET (TY II) (30 IN) (CMP) (4: 1) (C)
EA 4.000 $2,700.000 $3,647.250 $3,500.000 $3,500.000 $3,200.000 $2,060.000
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 8.000 $2,700.000 $3,005.750 $2,800.000 $4,800.000 $3,800.000 $2,430.000
CLEAN EXIST CULVERTS
EA 20.000 $2,000.000 $1,958.250 $800.000 $1,500.000 $2,200.000 $1,717.000
REMOV STR (PIPE)
EA 6.000 $2,000.000 $1,273.250 $2,100.000 $1,400.000 $540.000 $2,160.000
MOBILIZATION
LS 1.000 $2,010,000.000 $2,157,521.550 $2,141,000.000 $2,214,423.880 $2,300,000.000 $2,300,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 37.000 $12,500.000 $2,912.500 $8,000.000 $1,295.000 $7,400.000 $24,500.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 666.000 $30.000 $48.500 $36.000 $50.000 $27.000 $29.200
CONSTRUCTION EXITS (REMOVE)
SY 666.000 $15.000 $10.250 $12.000 $10.000 $8.650 $10.800
SANDBAGS FOR EROSION CONTROL
EA 372.000 $10.000 $19.000 $5.000 $14.200 $11.000 $13.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 80.000 $4.000 $3.750 $5.000 $18.000 $5.400 $10.800
TEMP SEDMT CONT FENCE (REMOVE)
LF 80.000 $1.000 $1.250 $2.100 $1.180 $1.100 $1.100
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 1,520.000 $10.000 $7.500 $5.000 $8.000 $5.000 $7.050
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,520.000 $2.000 $1.250 $1.300 $1.180 $0.970 $1.100
CONSTRUCTING DETOURS
SY 4,563.000 $60.000 $58.500 $50.000 $90.000 $64.500 $92.000
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
LF 5,880.000 $40.000 $66.000 $20.000 $75.000 $65.000 $27.100
PORT CTB (MOVE)(F-SHAPE)(TY 1)
LF 2,820.000 $10.000 $7.000 $2.000 $10.500 $12.500 $10.800
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
LF 5,880.000 $10.000 $9.250 $4.000 $8.500 $6.800 $10.800
PERM CTB (SGL SLOPE) (TY 1) (42 )
LF 4,088.000 $110.000 $97.250 $95.000 $70.000 $100.000 $75.000
CONC CURB & GUTTER (TY II)
LF 5,010.000 $25.000 $28.750 $30.000 $25.000 $38.000 $21.600
DRIVEWAYS (CONC)
SY 1,144.000 $80.000 $105.000 $90.000 $60.000 $110.000 $86.500
DRIVEWAYS (ACP)
SY 1,836.000 $60.000 $43.750 $50.000 $60.000 $62.000 $48.750
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 16,345.000 $0.500 $0.800 $0.400 $0.500 $0.350 $0.300
CRASH CUSH ATTEN (MOVE & RESET)
EA 6.000 $2,000.000 $1,781.500 $800.000 $2,650.000 $385.000 $2,700.000
CRASH CUSH ATTEN (REMOVE)
EA 10.000 $1,500.000 $1,882.500 $1,400.000 $1,130.000 $200.000 $1,190.000
CRASH CUSH ATTEN (INSTL)(R)(N)(TL3)
EA 2.000 $15,000.000 $31,599.750 $25,000.000 $32,000.000 $37,500.000 $22,180.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 10.000 $10,000.000 $6,284.750 $10,000.000 $9,510.000 $10,000.000 $9,200.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 7.000 $350.000 $348.500 $350.000 $315.000 $350.000 $308.000
MAILBOX INSTALL-D (TWW-POST) TY 4
EA 1.000 $500.000 $411.750 $400.000 $250.000 $415.000 $352.000
IN RD IL (U/P) (TY 1) (150W EQ) LED
EA 8.000 $1,600.000 $1,710.750 $1,500.000 $1,400.000 $1,500.000 $1,620.000
IN RD IL (TY ST) 40T-12 (250W EQ) LED
EA 16.000 $4,000.000 $5,385.500 $5,000.000 $4,400.000 $4,600.000 $9,200.000
CONDT (PVC) (SCH 80) (2")
LF 8,632.000 $6.000 $11.750 $10.000 $10.000 $10.000 $13.500
CONDT (PVC) (SCH 80) (2") (BORE)
LF 1,058.000 $20.000 $21.750 $18.000 $18.000 $18.500 $27.100
CONDT (RM) (3/4")
LF 271.000 $20.000 $20.250 $17.000 $16.500 $17.500 $23.800
ELEC CONDR (NO.6) BARE
LF 7,056.000 $1.500 $2.000 $1.600 $1.750 $1.600 $1.600
ELEC CONDR (NO.6) INSULATED
LF 14,112.000 $1.750 $2.000 $1.600 $1.750 $1.600 $1.850
GROUND BOX TY A (122311)W/APRON
EA 17.000 $800.000 $823.750 $800.000 $650.000 $700.000 $974.000
ELC SRV TY A 240/480 060(NS)SS(E)SP(O)
EA 1.000 $6,000.000 $7,349.500 $7,500.000 $6,000.000 $6,300.000 $9,740.000
ALUMINUM SIGNS (TY G)
SF 156.000 $30.000 $38.000 $40.000 $29.000 $38.000 $34.500
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 17.000 $800.000 $1,001.000 $750.000 $575.000 $760.000 $676.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 13.000 $900.000 $1,203.750 $1,000.000 $800.000 $950.000 $838.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 2.000 $900.000 $1,362.250 $1,100.000 $900.000 $1,100.000 $1,030.000
IN SM RD SN SUP&AM TY10BWG(1)SB(P)
EA 3.000 $800.000 $1,089.750 $900.000 $450.000 $870.000 $541.000
IN SM RD SN SUP&AM TY10BWG(1)SB(T)
EA 13.000 $900.000 $1,235.500 $1,000.000 $600.000 $990.000 $595.000
IN SM RD SN SUP&AM TY10BWG(1)SB(U)
EA 2.000 $900.000 $1,394.000 $1,100.000 $450.000 $1,100.000 $541.000
IN BRIDGE MNT CLEARANCE SGN ASSM(TY S)
EA 4.000 $1,900.000 $4,688.500 $3,000.000 $2,750.000 $2,800.000 $3,030.000
IN SM RD SN SUP&AM (INST SIGN ONLY)
EA 2.000 $1,000.000 $633.500 $200.000 $400.000 $195.000 $595.000
REMOVE SM RD SN SUP&AM
EA 22.000 $100.000 $126.750 $95.000 $85.000 $135.000 $108.000
INSTALL LRSS (STRUCT STEEL)
LB 1,283.400 $7.000 $7.500 $8.000 $5.000 $7.500 $6.000
INSTL DEL ASSM (D-SY)SZ (BRF)CTB (BI)
EA 23.000 $80.000 $88.750 $22.000 $19.000 $21.500 $21.600
REMOVE DELIN & OBJECT MARKER ASSMS
EA 11.000 $30.000 $12.750 $27.000 $18.000 $38.000 $32.500
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BR)
EA 60.000 $80.000 $25.250 $27.000 $15.000 $32.500 $27.100
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 78.000 $80.000 $126.750 $100.000 $73.000 $99.500 $81.250
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 10,120.000 $0.300 $0.300 $0.220 $0.200 $0.220 $0.300
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 59,610.000 $0.300 $0.300 $0.220 $0.200 $0.220 $0.300
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 536.000 $5.000 $2.500 $4.500 $2.000 $2.150 $2.700
WK ZN PAV MRK NON-REMOV (W)(ARROW)
EA 20.000 $20.000 $95.000 $80.000 $75.000 $81.000 $70.250
WK ZN PAV MRK NON-REMOV (W)(TPL ARW)
EA 4.000 $50.000 $316.750 $150.000 $250.000 $270.000 $162.000
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 60,174.000 $0.300 $0.300 $0.220 $0.200 $0.220 $0.300
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 5,192.000 $2.000 $1.250 $0.900 $1.000 $1.100 $1.100
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 4,236.000 $2.000 $1.250 $0.900 $1.000 $1.100 $1.100
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 7,885.000 $2.000 $1.250 $1.600 $0.950 $1.050 $0.800
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 23,840.000 $0.500 $0.600 $0.750 $0.480 $0.520 $0.300
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 5,473.000 $0.500 $0.900 $1.100 $0.720 $0.780 $0.300
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 23,947.000 $0.500 $0.600 $0.800 $0.480 $0.520 $0.300
PREFAB PAV MRK TY C (W) (12") (SLD)
LF 1,518.000 $4.000 $10.750 $9.000 $8.500 $9.200 $7.550
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 202.000 $5.000 $21.500 $18.000 $17.000 $18.500 $13.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 2.000 $250.000 $380.250 $270.000 $30.000 $325.000 $270.000
PREFAB PAV MRK TY C (W) (TPL ARROW)
EA 4.000 $300.000 $1,013.750 $470.000 $800.000 $865.000 $487.000
PREFAB PAV MRK TY C (W) (UTURN ARROW)
EA 4.000 $250.000 $760.250 $270.000 $600.000 $650.000 $433.000
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
EA 34.000 $30.000 $50.750 $27.000 $40.000 $43.000 $37.750
REFL PAV MRKR TY I-C
EA 71.000 $3.000 $5.000 $7.500 $4.000 $4.300 $3.250
REFL PAV MRKR TY II-A-A
EA 75.000 $3.000 $5.000 $7.500 $4.000 $4.300 $3.250
REFL PAV MRKR TY II-C-R
EA 130.000 $3.000 $5.000 $7.500 $4.000 $4.300 $3.250
ELIM EXT PAV MRK & MRKS (4")
LF 51,967.000 $1.000 $1.000 $0.500 $0.750 $0.810 $0.300
ELIM EXT PAV MRK & MRKS (6")
LF 7,084.000 $2.000 $1.250 $0.800 $0.950 $1.050 $0.650
ELIM EXT PAV MRK & MRKS (8")
LF 3,230.000 $3.000 $2.000 $1.000 $1.500 $1.600 $0.950
ELIM EXT PAV MRK & MRKS (ARROW)
EA 8.000 $50.000 $126.750 $125.000 $100.000 $110.000 $54.000
PAV SURF PREP FOR MRK (4")
LF 1,436.000 $0.500 $1.250 $0.100 $1.000 $1.100 $0.100
PAV SURF PREP FOR MRK (6")
LF 180.000 $0.750 $1.250 $0.150 $1.000 $1.100 $0.200
PAV SURF PREP FOR MRK (12")
LF 1,518.000 $1.000 $1.250 $0.450 $1.000 $1.100 $0.550
PAV SURF PREP FOR MRK (24")
LF 202.000 $2.000 $1.250 $0.600 $1.000 $1.100 $0.800
PAV SURF PREP FOR MRK (ARROW)
EA 10.000 $10.000 $63.250 $30.000 $50.000 $54.000 $32.500
PAV SURF PREP FOR MRK (36")(YLD TRI)
EA 34.000 $10.000 $6.250 $10.000 $5.000 $5.400 $5.400
REMOVE RDSD FLASH BEACON ASSEMBLY
EA 2.000 $1,000.000 $633.500 $1,000.000 $250.000 $975.000 $1,080.000
FULL - WIDTH MOWING
CYC 4.000 $5,000.000 $3,465.500 $3,200.000 $2,500.000 $1,100.000 $10,820.000
LITTER REMOVAL
CYC 4.000 $3,000.000 $2,952.000 $2,500.000 $3,000.000 $1,100.000 $10,820.000
CLEANING / SWEEPING(ENTRANCE/EXIT RAMP)
CYC 6.000 $3,000.000 $3,168.000 $670.000 $1,750.000 $1,100.000 $2,700.000
REINFORCED FAB FOR ASPH PVMNT OVERLAYS
SY 56,846.000 $7.000 $6.750 $6.500 $6.000 $6.200 $6.500
ASPH FOR REINF FAB (AC-20-5TR)
GAL 8,527.000 $5.000 $6.500 $12.000 $10.000 $4.050 $3.250
D-GR HMA TY-B PG70-28
TON 29,488.000 $105.000 $106.750 $115.000 $100.000 $103.300 $95.000
D-GR HMA TY-D SAC-A PG70-28
TON 331.000 $200.000 $221.250 $130.000 $150.000 $195.000 $135.000
TACK COAT
GAL 24,335.000 $5.000 $5.500 $4.000 $10.000 $3.350 $3.000
INSTALL BRIDGE IDENTIFICATION NUMBERS
EA 4.000 $200.000 $837.000 $300.000 $170.000 $325.000 $216.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 2,188.000 $200.000 $28.500 $30.000 $56.000 $38.000 $86.500
TMA (STATIONARY)
DAY 1,094.000 $200.000 $143.750 $175.000 $180.000 $215.000 $189.000
TMA (MOBILE OPERATION)
DAY 108.000 $250.000 $650.500 $525.000 $950.000 $975.000 $216.000
SOLAR POWERED LED WARNING SIGN
EA 4.000 $15,000.000 $6,335.750 $2,800.000 $3,500.000 $4,300.000 $5,410.000
TEMP SPEED MONITOR SYS
EA 1.000 $12,000.000 $22,633.250 $14,000.000 $8,000.000 $11,000.000 $9,200.000
Totals: $22,111,420.100 $21,657,408.603 $21,770,390.230 $22,439,461.000 $23,461,324.250 $23,889,089.000