REMOVING STAB BASE & ASPH PAV (12")
|
SY
|
37,682.000
|
$7.500
|
$8.000
|
$5.600
|
$4.900
|
|
|
|
REMOVING STAB BASE AND ASPH PAV (5")
|
SY
|
121,397.000
|
$5.000
|
$4.000
|
$2.750
|
$2.500
|
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
75,165.000
|
$9.000
|
$22.000
|
$8.000
|
$11.500
|
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY B)
|
CY
|
26,532.000
|
$10.000
|
$11.500
|
$15.000
|
$11.500
|
|
|
|
BLADING
|
STA
|
398.000
|
$160.000
|
$620.000
|
$1,250.000
|
$120.000
|
|
|
|
PROOF ROLLING
|
HR
|
15.000
|
$135.000
|
$110.000
|
$150.000
|
$115.000
|
|
|
|
FL BS (CMP IN PLC)(TY A GR 4)(5")
|
SY
|
199,003.000
|
$7.780
|
$7.000
|
$7.800
|
$9.200
|
|
|
|
REWORK BS MTL (TY D)(SURF)(ORD COMP)
|
SY
|
99,997.000
|
$1.160
|
$2.000
|
$2.000
|
$1.800
|
|
|
|
PRIME COAT (MC-30)
|
GAL
|
56,964.000
|
$4.500
|
$7.000
|
$6.000
|
$6.500
|
|
|
|
FOG SEAL (CSS-1H)
|
GAL
|
59,482.000
|
$3.500
|
$4.000
|
$4.000
|
$4.800
|
|
|
|
ASPH (AC-20-5TR)
|
GAL
|
108,234.000
|
$3.250
|
$4.500
|
$5.100
|
$5.000
|
|
|
|
AGGR(TY-PB GR-4 SAC-A)
|
CY
|
2,477.000
|
$100.000
|
$150.000
|
$115.000
|
$150.000
|
|
|
|
STRUCT EXCAV
|
CY
|
839.000
|
$10.000
|
$95.000
|
$30.000
|
$25.000
|
|
|
|
CEM STABIL BKFL
|
CY
|
452.000
|
$185.000
|
$410.000
|
$200.000
|
$330.000
|
|
|
|
CUT & RESTORING PAV
|
SY
|
165.000
|
$120.000
|
$230.000
|
$140.000
|
$230.000
|
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
529.000
|
$16.000
|
$55.000
|
$30.000
|
$30.000
|
|
|
|
TEMPORARY SPL SHORING
|
SF
|
6,481.000
|
$20.000
|
$10.000
|
$17.000
|
$24.000
|
|
|
|
CONC BOX CULV (4 FT X 2 FT)
|
LF
|
240.000
|
$320.000
|
$705.000
|
$500.000
|
$500.000
|
|
|
|
CONC BOX CULV (5 FT X 2 FT)
|
LF
|
606.000
|
$400.000
|
$825.000
|
$600.000
|
$700.000
|
|
|
|
RC PIPE (CL IV)(36 IN)
|
LF
|
344.000
|
$135.000
|
$315.000
|
$250.000
|
$350.000
|
|
|
|
RC PIPE (ARCH)(CL IV)(DES 3)
|
LF
|
525.000
|
$200.000
|
$415.000
|
$300.000
|
$470.000
|
|
|
|
WINGWALL (PW - 1) (HW=4 FT)
|
EA
|
1.000
|
$11,500.000
|
$33,000.000
|
$29,500.000
|
$31,000.000
|
|
|
|
SET (TY I)(S= 4 FT)(HW= 4 FT)(4:1) (C)
|
EA
|
3.000
|
$10,000.000
|
$16,300.000
|
$13,500.000
|
$11,000.000
|
|
|
|
SET (TY I)(S= 5 FT)(HW= 3 FT)(4:1) (C)
|
EA
|
14.000
|
$6,000.000
|
$8,250.000
|
$10,000.000
|
$9,500.000
|
|
|
|
SET (TY II) (18 IN) (RCP) (4: 1) (P)
|
EA
|
14.000
|
$1,250.000
|
$1,450.000
|
$2,000.000
|
$2,600.000
|
|
|
|
SET (TY II) (24 IN) (RCP) (4: 1) (P)
|
EA
|
20.000
|
$2,000.000
|
$1,800.000
|
$2,300.000
|
$3,200.000
|
|
|
|
SET (TY II) (36 IN) (RCP) (3: 1) (C)
|
EA
|
8.000
|
$2,600.000
|
$4,720.000
|
$6,300.000
|
$5,000.000
|
|
|
|
SET (TY II) (DES 3) (RCP) (4: 1) (C)
|
EA
|
15.000
|
$1,750.000
|
$2,280.000
|
$3,800.000
|
$3,300.000
|
|
|
|
SET (TY II) (DES 3) (RCP) (6: 1) (C)
|
EA
|
3.000
|
$2,000.000
|
$3,220.000
|
$5,600.000
|
$4,600.000
|
|
|
|
REMOV STR (HEADWALL)
|
EA
|
14.000
|
$1,500.000
|
$455.000
|
$1,350.000
|
$1,100.000
|
|
|
|
REMOV STR (PIPE)
|
EA
|
11.000
|
$700.000
|
$1,500.000
|
$1,300.000
|
$1,100.000
|
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$2,382,900.000
|
$3,115,000.000
|
$3,200,000.000
|
$3,041,000.000
|
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
24.000
|
$20,000.000
|
$14,250.000
|
$30,000.000
|
$5,000.000
|
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
247.000
|
$30.000
|
$55.000
|
$80.000
|
$50.000
|
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
247.000
|
$15.000
|
$12.000
|
$20.000
|
$13.000
|
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
444.000
|
$25.000
|
$30.000
|
$65.000
|
$25.000
|
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
444.000
|
$12.000
|
$10.000
|
$11.000
|
$9.000
|
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (18")
|
LF
|
620.000
|
$7.500
|
$10.000
|
$15.000
|
$9.000
|
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
620.000
|
$2.000
|
$2.500
|
$5.000
|
$2.500
|
|
|
|
CONSTRUCTING DETOURS
|
SY
|
8,095.000
|
$45.000
|
$94.000
|
$60.000
|
$70.000
|
|
|
|
PTB (FRN&INSTL)(SGL SLP)(TY 1) OR (STL)
|
LF
|
12,650.000
|
$50.000
|
$45.000
|
$70.000
|
$48.000
|
|
|
|
PTB (MOVE)(SGL SLP)(TY 1) OR (STL)
|
LF
|
37,945.000
|
$9.000
|
$5.000
|
$10.000
|
$4.000
|
|
|
|
PTB (REMOVE)(SGL SLP)(TY 1) OR (STL)
|
LF
|
12,650.000
|
$8.000
|
$10.000
|
$7.000
|
$4.000
|
|
|
|
INTRSCT, DRVWAYS, & TURNOUT (ACP)
|
SY
|
4,064.000
|
$50.000
|
$89.000
|
$100.000
|
$75.000
|
|
|
|
RUMBLE STRIPS (SHOULDER)
|
LF
|
78,416.000
|
$0.200
|
$0.300
|
$0.140
|
$0.200
|
|
|
|
RUMBLE STRIPS (CENTERLINE)
|
LF
|
20,650.000
|
$0.200
|
$0.300
|
$0.140
|
$0.250
|
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
14.000
|
$1,200.000
|
$885.000
|
$1,500.000
|
$1,000.000
|
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
4.000
|
$850.000
|
$715.000
|
$1,500.000
|
$400.000
|
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
4.000
|
$8,500.000
|
$9,300.000
|
$9,300.000
|
$8,000.000
|
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
18.000
|
$600.000
|
$1,200.000
|
$1,000.000
|
$1,070.000
|
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
|
EA
|
3.000
|
$1,500.000
|
$1,500.000
|
$1,600.000
|
$1,530.000
|
|
|
|
IN SM RD SN SUP&AM TY10BWG(2)SA(P)
|
EA
|
1.000
|
$1,500.000
|
$1,700.000
|
$1,900.000
|
$1,850.000
|
|
|
|
RELOCATE SM RD SN SUP&AM TY 10BWG
|
EA
|
8.000
|
$500.000
|
$850.000
|
$1,000.000
|
$1,010.000
|
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
9.000
|
$100.000
|
$125.000
|
$175.000
|
$140.000
|
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
|
LF
|
245,794.000
|
$0.150
|
$0.200
|
$0.150
|
$0.150
|
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
|
LF
|
246,988.000
|
$0.200
|
$0.200
|
$0.150
|
$0.150
|
|
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
3,976.000
|
$2.000
|
$1.000
|
$3.000
|
$1.250
|
|
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
1,988.000
|
$0.950
|
$1.000
|
$3.000
|
$1.250
|
|
|
|
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
|
LF
|
2,093.000
|
$1.000
|
$1.100
|
$1.200
|
$1.100
|
|
|
|
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
|
LF
|
1,500.000
|
$1.000
|
$1.500
|
$1.750
|
$1.600
|
|
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
6,083.000
|
$1.000
|
$1.200
|
$1.200
|
$1.200
|
|
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
|
LF
|
7,083.000
|
$0.420
|
$0.600
|
$0.600
|
$0.600
|
|
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
78,416.000
|
$0.420
|
$0.600
|
$0.600
|
$0.600
|
|
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
106,384.000
|
$0.420
|
$0.600
|
$0.600
|
$0.600
|
|
|
|
PREFAB PAV MRK TY C (W) (24") (SLD)
|
LF
|
225.000
|
$14.000
|
$15.000
|
$17.000
|
$16.000
|
|
|
|
PREFAB PAV MRK TY C (W) (ARROW)
|
EA
|
30.000
|
$230.000
|
$235.000
|
$270.000
|
$250.000
|
|
|
|
PREFAB PAV MRK TY C (W) (LNDP ARROW)
|
EA
|
16.000
|
$500.000
|
$550.000
|
$600.000
|
$560.000
|
|
|
|
PREFAB PAV MRK TY C (W) (WORD)
|
EA
|
30.000
|
$300.000
|
$320.000
|
$360.000
|
$330.000
|
|
|
|
REFL PAV MRKR TY I-C
|
EA
|
662.000
|
$3.250
|
$5.000
|
$5.850
|
$5.500
|
|
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
3,948.000
|
$3.000
|
$4.000
|
$4.600
|
$4.400
|
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
82,837.000
|
$0.350
|
$0.700
|
$0.700
|
$0.700
|
|
|
|
SP MIXES SP-B SAC-B PG70-22
|
TON
|
153,026.000
|
$80.000
|
$90.000
|
$95.000
|
$105.000
|
|
|
|
TACK COAT
|
GAL
|
56,964.000
|
$3.500
|
$5.500
|
$5.000
|
$5.200
|
|
|
|
STONE-MTRX-ASPH SMAR-F SAC-A
|
TON
|
23,580.000
|
$125.000
|
$130.000
|
$165.000
|
$150.000
|
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$15,000.000
|
$15,230.000
|
$23,500.000
|
$26,000.000
|
|
|
|
TMA (STATIONARY)
|
DAY
|
308.000
|
$150.000
|
$190.000
|
$150.000
|
$250.000
|
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
80.000
|
$80.000
|
$70.000
|
$130.000
|
$900.000
|
|
1
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
847.000
|
$90.000
|
$0.000
|
$120.000
|
$110.000
|
|
1A
|
|
THERMOPLASTIC PIPE(18 IN)(PP)(TYPE III)
|
LF
|
847.000
|
$90.000
|
$100.000
|
$0.000
|
$0.000
|
|
2
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
1,160.000
|
$100.000
|
$0.000
|
$130.000
|
$140.000
|
|
2A
|
|
THERMOPLASTIC PIPE(24 IN)(PP)(TYPE III)
|
LF
|
1,160.000
|
$100.000
|
$125.000
|
$0.000
|
$0.000
|
|
Totals: |
$26,357,772.170
|
$31,270,742.800
|
$32,395,443.690
|
$32,663,783.200
|