LLANO SH 29 (0150-04-049)

Items: 109

County: LLANO
Length: N/A
Highway: SH 29
District: AUSTIN
Control Number: 0150-04-049
DBE Goal: N/A
Project: C 150-4-49
Guaranty: N/A
Time: 173 WORKING DAYS
Engineer's Estimate: $5,031,369.71
Date: 05/07/2020 (6 years ago)
Contract Number: N/A
Type: CONSTRUCT SUPER 2 PASSING LANES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (10)
E
Engineer's Estimate
$5,031,369.71
$4,653,514.57
Over/Under Est: -7.51% -$377,855.14
Over/Under Est: -7.07% -$355,837.02
Amt Left: 0.47% $22,018.12
Over/Under Est: -4.41% -$222,102.22
Amt Left: 3.35% $155,752.92
Delta: -2.86% -$133,734.80
Over/Under Est: 8.93% $449,052.30
Amt Left: 17.77% $826,907.44
Delta: -13.96% -$671,154.52
Over/Under Est: 13.85% $696,924.48
Amt Left: 23.1% $1,074,779.62
Delta: -4.52% -$247,872.18
Over/Under Est: 16.37% $823,528.01
Amt Left: 25.82% $1,201,383.15
Delta: -2.21% -$126,603.53
Over/Under Est: 16.82% $846,521.28
Amt Left: 26.31% $1,224,376.42
Delta: -0.39% -$22,993.27
$5,985,407.63
Over/Under Est: 18.96% $954,037.92
Amt Left: 28.62% $1,331,893.06
Delta: -1.83% -$107,516.64
$6,237,818.99
Over/Under Est: 23.98% $1,206,449.28
Amt Left: 34.05% $1,584,304.42
Delta: -4.22% -$252,411.36
Over/Under Est: 38.5% $1,936,972.69
Amt Left: 49.74% $2,314,827.83
Delta: -11.71% -$730,523.41

Bid Items & Bid Tabulations

109 Total 0 of 109
LLANO  |  SH 29  |  AUSTIN  |  0150-04-049  |  05/07/2020  |  $5,031,369.71  |  C 150-4-49  |  CONSTRUCT SUPER 2 PASSING LANES  |  173 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ACME BRIDGE COMPANY, INC.
JOE BLAND CONSTRUCTION, L.P.
BIG CREEK CONSTRUCTION, LTD.
KNIFE RIVER CORPORATION - SOUTH
ANGEL BROTHERS HOLDINGS CORP.
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
TIERRA LEASE SERVICE, LLC
ALLEN KELLER COMPANY
DAN WILLIAMS COMPANY
AARON CONCRETE CONTRACTORS, L.P.
PREPARING ROW
STA 143.000 $800.000 $445.000 $770.000 $500.000 $1,370.000 $1,051.000 $284.870 $400.000 $760.000 $1,000.000 $1,000.000
EXCAVATION (ROADWAY)
CY 40,389.000 $10.500 $7.700 $11.000 $8.000 $13.250 $13.250 $15.700 $12.250 $12.400 $13.000 $27.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 48,961.000 $10.000 $3.450 $5.000 $8.000 $9.400 $14.700 $8.720 $10.000 $12.000 $16.000 $12.000
FURNISHING AND PLACING TOPSOIL (4")
SY 37,587.000 $1.100 $1.750 $2.000 $2.000 $1.700 $1.300 $2.700 $4.000 $1.800 $2.000 $1.300
DRILL SEEDING (PERM) (RURAL) (SANDY)
SY 37,587.000 $0.150 $0.150 $0.250 $0.150 $0.150 $0.150 $0.200 $0.150 $0.180 $0.250 $0.300
DRILL SEEDING (TEMP) (WARM)
SY 18,793.500 $0.130 $0.130 $0.150 $0.120 $0.130 $0.130 $0.140 $0.150 $0.190 $0.150 $0.300
DRILL SEEDING (TEMP) (COOL)
SY 18,793.500 $0.130 $0.110 $0.150 $0.120 $0.120 $0.120 $0.140 $0.150 $0.190 $0.150 $0.300
VEGETATIVE WATERING
MG 633.000 $40.000 $25.700 $22.000 $12.000 $32.650 $19.000 $53.720 $40.000 $6.000 $20.000 $34.000
SOIL RETENTION BLANKETS (CL 1) (TY C)
SY 37,587.000 $1.250 $0.970 $1.200 $1.000 $1.000 $1.000 $1.000 $1.750 $1.000 $1.500 $2.000
FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS)
CY 13,050.000 $50.000 $52.500 $48.000 $42.000 $38.750 $48.400 $55.340 $63.000 $55.500 $55.000 $71.000
PRIME COAT (MULTI OPTION)
GAL 9,141.000 $4.000 $4.100 $4.000 $4.000 $3.500 $3.950 $4.480 $4.250 $4.150 $3.850 $4.500
ASPH (TIER I)
GAL 35,460.000 $3.250 $3.200 $3.800 $3.000 $4.400 $3.450 $3.900 $3.250 $3.100 $3.000 $4.200
AGGR(TY-PD GR-4 SAC-B)
CY 779.000 $92.000 $107.000 $106.000 $100.000 $94.300 $98.000 $131.520 $100.000 $120.000 $105.000 $120.000
D-GR HMA (SQ) TYC PG70-22 (LEVEL-UP)
TON 1,031.000 $100.000 $102.000 $96.000 $90.000 $83.450 $83.000 $97.820 $110.000 $94.000 $120.000 $110.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 2,350.000 $40.000 $35.000 $41.000 $35.000 $31.500 $38.000 $90.100 $47.000 $44.830 $50.000 $45.000
PLAN & TEXT ASPH CONC PAV(0" TO 1")
SY 2,043.000 $2.250 $4.250 $5.000 $4.000 $5.350 $3.750 $6.690 $5.500 $15.200 $5.000 $5.600
FLOWABLE BACKFILL
CY 2.000 $600.000 $523.000 $1,500.000 $450.000 $537.650 $544.000 $530.840 $575.000 $610.000 $500.000 $556.000
TRENCH EXCAVATION PROTECTION
LF 94.000 $20.000 $23.000 $50.000 $25.000 $21.500 $23.000 $19.920 $5.750 $27.000 $5.000 $25.000
TEMPORARY SPL SHORING
SF 1,919.000 $45.000 $53.700 $31.000 $40.000 $86.000 $65.000 $56.460 $25.000 $79.000 $16.000 $72.000
CL A CONC (MISC)
CY 1.000 $2,500.000 $1,050.000 $2,000.000 $1,000.000 $2,688.000 $1,075.000 $997.720 $1,725.000 $1,220.000 $1,500.000 $1,110.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 15.000 $250.000 $214.000 $725.000 $750.000 $360.000 $222.000 $192.420 $58.000 $250.000 $425.000 $230.000
RIPRAP (CONC)(4 IN)
CY 498.000 $450.000 $444.000 $465.000 $400.000 $591.000 $460.000 $430.160 $575.000 $520.000 $420.000 $475.000
RIPRAP (CONC)(CL B)(5 IN)
CY 61.000 $485.000 $449.000 $465.000 $475.000 $645.000 $465.000 $536.390 $520.000 $523.000 $450.000 $480.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 298.000 $150.000 $193.000 $110.000 $150.000 $242.000 $200.000 $291.570 $175.000 $225.000 $230.000 $250.000
RIPRAP (MOW STRIP)(4 IN)
CY 180.000 $485.000 $517.000 $540.000 $450.000 $645.000 $525.000 $529.840 $500.000 $600.000 $580.000 $640.000
CLEANING AND SEALING EXIST JOINTS(CL3)
LF 50.000 $50.000 $125.000 $165.000 $150.000 $97.000 $125.000 $153.510 $135.000 $140.000 $30.000 $130.000
RETROFIT RAIL (TY T631)
LF 252.000 $120.000 $91.900 $91.000 $125.000 $118.000 $86.000 $110.890 $110.000 $102.000 $125.000 $90.000
CONC BOX CULV (7 FT X 3 FT)(EXTEND)
LF 16.000 $750.000 $669.000 $1,300.000 $850.000 $806.000 $695.000 $785.260 $875.000 $780.000 $1,000.000 $710.000
CONC BOX CULV (7 FT X 4 FT)(EXTEND)
LF 200.000 $850.000 $813.000 $850.000 $900.000 $914.000 $845.000 $574.500 $975.000 $950.000 $600.000 $865.000
CONC BOX CULV (7 FT X 7 FT)(EXTEND)
LF 60.000 $950.000 $392.000 $1,220.000 $1,000.000 $1,021.000 $407.000 $917.510 $1,150.000 $455.000 $800.000 $420.000
RC PIPE (CL III)(18 IN)
LF 224.000 $65.000 $47.000 $88.000 $60.000 $62.400 $49.000 $60.260 $83.000 $55.000 $85.000 $50.000
RC PIPE (CL III)(24 IN)
LF 69.000 $70.000 $60.600 $116.000 $80.000 $134.400 $63.000 $88.170 $100.000 $70.000 $125.000 $65.000
RC PIPE (CL III)(36 IN)
LF 28.000 $120.000 $141.000 $188.000 $180.000 $177.400 $146.000 $221.180 $200.000 $164.000 $350.000 $150.000
RC PIPE (CL IV)(36 IN)
LF 10.000 $175.000 $193.000 $257.000 $200.000 $215.000 $200.000 $319.410 $300.000 $225.000 $500.000 $205.000
RC PIPE (CL V)(24 IN)
LF 26.000 $145.000 $73.200 $134.000 $100.000 $150.550 $76.000 $121.170 $190.000 $85.000 $300.000 $78.000
RC PIPE (CL V)(30 IN)
LF 167.000 $175.000 $136.000 $184.000 $150.000 $177.450 $140.000 $131.650 $225.000 $158.000 $150.000 $145.000
HEADWALL (CH - FW - 0) (DIA= 24 IN)
EA 1.000 $3,500.000 $6,290.000 $5,900.000 $3,500.000 $4,300.000 $6,500.000 $7,372.160 $4,600.000 $7,325.000 $9,000.000 $6,700.000
HEADWALL (CH - PW - 0) (DIA= 24 IN)
EA 3.000 $5,000.000 $6,010.000 $9,200.000 $5,000.000 $5,377.000 $6,200.000 $9,337.450 $5,000.000 $7,000.000 $9,000.000 $6,400.000
HEADWALL (CH - PW - 0) (DIA= 30 IN)
EA 4.000 $6,000.000 $6,690.000 $13,000.000 $7,000.000 $8,065.000 $6,900.000 $10,288.440 $5,750.000 $7,800.000 $10,000.000 $7,200.000
HEADWALL (CH - PW - 0) (DIA= 36 IN)
EA 2.000 $6,500.000 $8,100.000 $10,500.000 $9,000.000 $9,140.000 $8,400.000 $11,344.060 $8,400.000 $9,440.000 $10,500.000 $8,600.000
WINGWALL (FW - S) (HW=6 FT)
EA 1.000 $10,000.000 $23,700.000 $16,800.000 $25,000.000 $18,280.000 $24,000.000 $23,432.860 $10,000.000 $27,640.000 $15,500.000 $25,000.000
WINGWALL (FW - S) (HW=9 FT)
EA 1.000 $16,000.000 $25,900.000 $36,200.000 $45,000.000 $27,960.000 $26,000.000 $28,283.870 $19,750.000 $30,170.000 $30,000.000 $27,000.000
WINGWALL (PW - 1) (HW=5 FT)
EA 1.000 $14,000.000 $19,200.000 $14,300.000 $24,000.000 $17,205.000 $20,000.000 $20,416.520 $30,800.000 $22,315.000 $17,500.000 $20,000.000
WINGWALL (PW - 1) (HW=6 FT)
EA 2.000 $20,000.000 $35,300.000 $34,100.000 $27,500.000 $24,735.000 $36,000.000 $17,611.140 $38,500.000 $41,100.000 $21,000.000 $37,500.000
WINGWALL (PW - 1) (HW=9 FT)
EA 1.000 $25,000.000 $40,600.000 $59,200.000 $75,000.000 $69,895.000 $42,000.000 $47,333.560 $55,000.000 $47,350.000 $40,000.000 $43,200.000
HEADWALL (CH - PW - 0)(DIA= 24 IN)(MOD)
EA 1.000 $8,250.000 $9,180.000 $13,200.000 $9,500.000 $4,840.000 $9,500.000 $12,884.810 $7,000.000 $10,700.000 $11,000.000 $9,800.000
HEADWALL (CH - PW - 0)(DIA=36 IN)(MOD)
EA 3.000 $6,000.000 $9,400.000 $16,000.000 $15,000.000 $11,290.000 $9,700.000 $12,208.880 $8,000.000 $10,950.000 $15,000.000 $10,000.000
SET (TY II) (18 IN) (RCP) (4: 1) (P)
EA 14.000 $1,100.000 $1,210.000 $1,800.000 $800.000 $1,075.000 $1,200.000 $992.880 $2,000.000 $1,400.000 $1,150.000 $1,300.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 3.000 $1,500.000 $1,590.000 $2,600.000 $1,000.000 $1,290.000 $1,600.000 $1,180.380 $2,500.000 $1,850.000 $1,200.000 $1,700.000
SET (TY II) (24 IN) (RCP) (5: 1) (C)
EA 1.000 $1,600.000 $1,700.000 $2,600.000 $1,100.000 $1,615.000 $1,700.000 $1,180.380 $2,500.000 $1,980.000 $1,050.000 $1,800.000
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 2.000 $1,500.000 $1,880.000 $2,900.000 $1,500.000 $2,690.000 $1,900.000 $1,117.880 $3,300.000 $2,190.000 $1,100.000 $2,000.000
SET (TY II) (36 IN) (RCP) (3: 1) (C)
EA 1.000 $2,500.000 $2,830.000 $4,300.000 $2,500.000 $3,225.000 $2,900.000 $2,029.510 $4,800.000 $3,300.000 $1,200.000 $3,010.000
SET (TY II) (36 IN) (RCP) (4: 1) (C)
EA 1.000 $2,950.000 $2,930.000 $4,300.000 $2,750.000 $3,765.000 $3,000.000 $2,248.260 $4,800.000 $3,400.000 $1,300.000 $3,110.000
SET (TY II) (36 IN) (RCP) (4: 1) (P)
EA 1.000 $3,200.000 $4,660.000 $5,200.000 $2,750.000 $3,765.000 $4,800.000 $3,479.510 $4,800.000 $5,425.000 $2,500.000 $4,950.000
CLEAN EXIST CULVERTS
EA 22.000 $3,000.000 $3,140.000 $1,000.000 $2,500.000 $1,615.000 $5,000.000 $2,896.110 $2,000.000 $6,100.000 $1,500.000 $5,550.000
REMOV STR (SET)
EA 31.000 $500.000 $157.000 $330.000 $400.000 $806.000 $160.000 $446.290 $825.000 $180.000 $450.000 $170.000
REMOV STR (WINGWALL)
EA 7.000 $1,150.000 $1,570.000 $1,400.000 $1,500.000 $1,290.000 $1,600.000 $2,157.230 $2,000.000 $1,825.000 $1,500.000 $1,700.000
REMOV STR (HEADWALL)
EA 7.000 $1,650.000 $314.000 $1,400.000 $1,500.000 $1,290.000 $325.000 $1,403.070 $1,500.000 $365.000 $1,600.000 $335.000
REMOV STR (PIPE)
LF 332.000 $15.000 $4.700 $10.000 $17.000 $32.250 $4.800 $11.590 $22.000 $5.500 $45.000 $5.000
MOBILIZATION
LS 1.000 $365,000.000 $353,000.000 $100,000.000 $410,000.000 $460,240.000 $578,000.000 $512,496.500 $550,000.000 $420,000.000 $615,000.000 $400,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 14.000 $8,000.000 $5,910.000 $1,800.000 $2,500.000 $2,710.000 $2,900.000 $2,536.330 $2,000.000 $10,400.000 $15,500.000 $1,500.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 660.000 $28.000 $34.400 $23.000 $25.000 $35.300 $36.000 $29.980 $28.000 $33.000 $28.000 $39.000
ROCK FILTER DAMS (REMOVE)
LF 660.000 $8.000 $11.300 $7.500 $5.000 $11.600 $10.800 $8.940 $17.000 $18.000 $15.000 $28.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 112.000 $28.000 $48.200 $13.000 $25.000 $49.600 $50.000 $17.330 $22.000 $19.000 $16.000 $33.000
CONSTRUCTION EXITS (REMOVE)
SY 112.000 $8.000 $11.600 $8.000 $5.000 $12.000 $11.000 $3.030 $16.000 $16.000 $13.500 $22.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 26,235.000 $2.500 $2.150 $2.000 $2.750 $2.200 $2.250 $2.920 $2.250 $2.400 $2.000 $5.600
TEMP SEDMT CONT FENCE (REMOVE)
LF 26,235.000 $0.500 $0.590 $0.500 $0.650 $0.600 $0.560 $0.900 $0.750 $0.450 $0.350 $2.200
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 2.000 $5,000.000 $1,000.000 $3,000.000 $7,500.000 $5,510.000 $6,220.000 $5,038.090 $4,700.000 $10,980.000 $12,000.000 $50,000.000
DRIVEWAYS (ACP)
SY 410.000 $50.000 $62.800 $48.000 $25.000 $34.400 $53.600 $33.200 $27.500 $51.000 $80.000 $52.000
DRIVEWAYS (SURF TREAT)
SY 680.000 $22.000 $18.100 $50.000 $20.000 $17.500 $24.500 $14.660 $17.000 $14.600 $35.000 $47.000
MTL W-BEAM GD FEN (TIM POST)
LF 2,880.000 $20.000 $23.000 $22.000 $27.000 $23.650 $27.150 $25.430 $25.000 $26.800 $25.000 $28.000
DRIVEWAY TERMINAL ANCHOR SECTION
EA 1.000 $630.000 $891.000 $852.000 $900.000 $916.200 $876.000 $973.090 $950.000 $1,040.000 $900.000 $900.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 5.000 $860.000 $1,140.000 $1,100.000 $1,100.000 $1,174.000 $1,000.000 $1,357.240 $1,200.000 $1,330.000 $1,350.000 $1,000.000
MTL BM GD FEN (LONG SPAN SYSTEM)
LF 300.000 $22.500 $21.000 $20.000 $21.000 $21.550 $27.000 $31.110 $22.000 $24.400 $35.000 $28.000
REMOVE METAL BEAM GUARD FENCE
LF 3,179.000 $1.000 $2.100 $2.000 $3.000 $2.150 $5.400 $2.320 $2.250 $2.450 $2.500 $5.600
GUARDRAIL END TREATMENT (REMOVE)
EA 14.000 $200.000 $209.000 $200.000 $250.000 $215.000 $270.000 $343.300 $225.000 $243.000 $325.000 $278.000
GDRAIL END TRT(INST)(WOOD POST)(TY I)
EA 14.000 $2,425.000 $2,910.000 $2,800.000 $2,800.000 $2,989.000 $3,250.000 $3,203.300 $3,075.000 $3,385.000 $3,500.000 $3,300.000
WIRE FENCE (TY A)
LF 500.000 $12.000 $9.800 $3.000 $15.000 $27.000 $38.000 $16.690 $16.500 $80.000 $25.000 $73.000
MAILBOX INSTALL-S (WC-POST) TY 3
EA 2.000 $225.000 $171.000 $200.000 $170.000 $175.950 $198.000 $210.610 $200.000 $200.000 $300.000 $295.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 10.000 $525.000 $517.000 $580.000 $500.000 $531.600 $625.000 $642.910 $550.000 $600.000 $650.000 $660.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 10.000 $550.000 $585.000 $600.000 $560.000 $602.000 $654.000 $671.510 $600.000 $680.000 $850.000 $880.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 2.000 $870.000 $802.000 $850.000 $780.000 $825.450 $920.000 $943.210 $850.000 $935.000 $1,400.000 $1,400.000
REMOVE SM RD SN SUP&AM
EA 22.000 $100.000 $89.800 $100.000 $100.000 $92.400 $105.000 $119.390 $95.000 $215.000 $200.000 $140.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 20.000 $15.000 $13.600 $30.000 $15.000 $14.000 $30.000 $40.110 $14.000 $16.000 $21.000 $23.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 15.000 $45.000 $0.520 $65.000 $50.000 $53.000 $68.000 $81.710 $55.000 $60.000 $51.000 $56.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 198.000 $24.000 $15.700 $28.000 $15.000 $16.000 $30.000 $35.500 $16.500 $18.000 $28.000 $30.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 1,509.000 $1.000 $1.500 $1.000 $1.000 $0.910 $1.000 $1.060 $0.550 $2.000 $1.850 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 1,420.000 $1.000 $1.500 $1.000 $1.000 $0.910 $1.000 $1.090 $0.550 $2.000 $1.850 $1.000
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
LF 609.000 $1.100 $1.050 $1.000 $1.000 $0.750 $0.760 $1.250 $0.550 $0.900 $0.750 $0.400
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 170.000 $2.200 $1.250 $2.000 $1.500 $0.750 $0.760 $1.870 $1.000 $0.900 $0.750 $1.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 50.000 $10.000 $7.300 $7.000 $7.000 $4.300 $4.350 $9.560 $17.000 $4.800 $4.500 $7.800
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 6.000 $115.000 $125.000 $120.000 $120.000 $430.000 $434.000 $147.510 $450.000 $490.000 $405.000 $140.000
REFL PAV MRK TY I(W)(LNDP ARW)(100MIL)
EA 4.000 $375.000 $301.000 $288.000 $300.000 $430.000 $434.000 $340.070 $450.000 $490.000 $405.000 $278.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 2.000 $175.000 $143.000 $137.000 $150.000 $430.000 $434.000 $197.240 $450.000 $490.000 $405.000 $278.000
REFL PAV MRK TY I (Y)24"(SLD)(100MIL)
LF 200.000 $8.000 $5.200 $5.000 $5.000 $4.300 $4.350 $5.970 $11.000 $4.900 $4.100 $7.800
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 3,060.000 $0.450 $0.540 $0.550 $0.600 $0.430 $0.430 $0.600 $0.750 $0.500 $0.450 $0.450
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 180.000 $0.450 $0.630 $0.550 $0.600 $0.430 $0.430 $1.180 $0.750 $0.500 $0.450 $0.450
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 28,600.000 $0.600 $0.630 $0.600 $0.600 $0.620 $0.630 $1.190 $0.850 $0.700 $0.600 $0.800
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 29,660.000 $0.600 $0.630 $0.600 $0.600 $0.620 $0.630 $0.670 $0.850 $0.700 $0.600 $0.800
REFL PAV MRKR TY I-C
EA 9.000 $10.000 $4.200 $4.000 $5.000 $13.700 $13.850 $14.740 $11.000 $15.500 $13.000 $4.200
REFL PAV MRKR TY II-A-A
EA 736.000 $4.150 $3.450 $4.000 $4.000 $2.950 $3.000 $3.760 $4.500 $3.300 $3.000 $4.200
REFL PAV MRKR TY II-C-R
EA 149.000 $4.150 $4.200 $4.000 $4.000 $2.950 $3.000 $5.020 $6.500 $3.300 $3.000 $4.200
PAV SURF PREP FOR MRK (ARROW)
EA 10.000 $22.000 $52.300 $50.000 $50.000 $1.000 $1.090 $64.310 $350.000 $1.300 $1.100 $28.000
PAV SURF PREP FOR MRK (WORD)
EA 2.000 $50.000 $52.300 $50.000 $50.000 $1.000 $1.090 $101.540 $350.000 $1.300 $1.100 $28.000
D-GR HMA TY-C PG70-22
TON 10,314.000 $75.000 $81.000 $76.000 $77.000 $75.700 $72.550 $82.630 $85.000 $84.000 $90.000 $84.000
TACK COAT
GAL 7,050.000 $3.000 $3.200 $3.980 $2.500 $3.600 $3.200 $5.120 $4.400 $4.300 $3.000 $4.500
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $6,500.000 $4,180.000 $3,500.000 $7,500.000 $2,700.000 $13,650.000 $17,395.910 $8,700.000 $12,800.000 $10,000.000 $8,900.000
TMA (STATIONARY)
DAY 126.000 $200.000 $63.300 $175.000 $200.000 $490.000 $150.000 $264.670 $325.000 $240.000 $300.000 $720.000
TMA (MOBILE OPERATION)
HR 80.000 $60.000 $33.700 $195.000 $50.000 $67.000 $45.000 $365.060 $60.000 $120.000 $65.000 $280.000
Totals: $5,031,369.710 $4,653,514.580 $4,675,532.700 $4,809,267.490 $5,480,422.015 $5,728,294.195 $5,854,897.720 $5,877,891.000 $5,985,407.640 $6,237,819.000 $6,968,342.400