Job Info for 0916-29-019

County: LIVE OAK Highway: VA Date: 08/01/2024 (3 months ago) Engineer's Estimate: $1,069,870 Control Number: 0916-29-019
Project: STP 2024(774)TAPS District: CORPUS CHRISTI Time: 99 WORKING DAYS Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Bidder's List
Informational:

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $1,069,870.00
MAKO CONTRACTING, LLC   $968,539.79 1
-9.47% | -$101,330.21
3LW CIVIL LLC   $1,064,707.94 2
-0.48% | -$5,162.06
9.93% | $96,168.15
TI-ZACK CONCRETE, LLC   $1,382,849.24 3
29.25% | $312,979.24
42.78% | $414,309.45
29.88% | $318,141.30
FNH CONSTRUCTION, LLC   $2,164,333.00 4
102.3% | $1,094,463.00
123.46% | $1,195,793.21
56.51% | $781,483.76
Subcontractor Percentage Amount
D&G ENERGY CORPORATION 11.89% $115,159.38
IPQ CONSTRUCTION LLC 6.66% $64,504.75
HIGHWAY BARRICADES AND SERVICES, LLC 4.07% $39,419.57
WOOLERY CUSTOM FENCE CO. 3.40% $32,930.35
TRP CONSTRUCTION GROUP, LLC 0.95% $9,201.13
Total: 26.97% $261,215.18

Bid Items

Items: 77, 0 filtered
LIVE OAK VA  |  CORPUS CHRISTI  |  0916-29-019  |  08/01/2024  |  $1,069,870  |  STP 2024(774)TAPS  |  CONSTRUCT PEDESTRIAN INFRASTRUCT  |  99 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate MAKO CONTRACTING, LLC 3LW CIVIL LLC TI-ZACK CONCRETE, LLC FNH CONSTRUCTION, LLC
100 6001 PREPARING ROW AC 1.000 $10,000.000 $25,000.000 $6,500.000 $13,200.000 $150,000.000
100 6004 PREPARING ROW(TREE)(12" TO 24" DIA) EA 1.000 $2,000.000 $5,000.000 $1,000.000 $2,750.000 $5,000.000
104 6009 REMOVING CONC (RIPRAP) SY 51.000 $35.000 $52.000 $40.000 $187.760 $100.000
104 6015 REMOVING CONC (SIDEWALKS) SY 46.000 $30.000 $52.000 $40.000 $20.820 $20.000
104 6017 REMOVING CONC (DRIVEWAYS) SY 41.000 $32.000 $52.000 $40.000 $23.360 $20.000
104 6029 REMOVING CONC (CURB OR CURB & GUTTER) LF 707.000 $15.000 $15.000 $15.000 $13.540 $20.000
105 6037 REMOVING STAB BASE AND ASPH PAV(0"-16") SY 362.000 $18.000 $18.000 $15.000 $23.730 $20.000
160 6003 FURNISHING AND PLACING TOPSOIL (4") SY 205.000 $5.000 $6.000 $12.500 $41.910 $10.000
162 6002 BLOCK SODDING SY 205.000 $7.000 $10.000 $9.500 $13.200 $10.000
168 6001 VEGETATIVE WATERING MG 4.000 $50.000 $100.000 $0.010 $1.100 $1,000.000
351 6006 FLEXIBLE PAVEMENT STRUCTURE REPAIR(10") SY 807.000 $85.000 $50.000 $110.000 $115.500 $135.000
402 6001 TRENCH EXCAVATION PROTECTION LF 77.000 $25.000 $25.000 $25.000 $1.100 $10.000
416 6001 DRILL SHAFT (18 IN) LF 40.000 $600.000 $500.000 $247.500 $247.500 $100.000
420 6071 CL C CONC (COLLAR) EA 2.000 $2,500.000 $500.000 $1,500.000 $1,650.000 $1,500.000
420 6074 CL C CONC (MISC) CY 9.600 $700.000 $350.000 $850.000 $814.420 $5,000.000
420 6132 CL A CONC (STEPS) CY 3.000 $1,000.000 $300.000 $2,500.000 $814.420 $5,000.000
432 6003 RIPRAP (CONC)(6 IN) CY 18.900 $800.000 $300.000 $750.000 $814.420 $750.000
450 6047 RAIL (HANDRAIL)(TY A) LF 50.000 $200.000 $235.000 $123.200 $247.500 $200.000
450 6048 RAIL (HANDRAIL)(TY B) LF 211.000 $200.000 $175.000 $104.500 $247.500 $200.000
464 6005 RC PIPE (CL III)(24 IN) LF 59.000 $250.000 $180.000 $159.790 $275.000 $300.000
464 6010 RC PIPE (CL III)(48 IN) LF 8.000 $550.000 $498.000 $571.200 $495.000 $350.000
465 6002 MANH (COMPL)(PRM)(48IN) EA 1.000 $7,000.000 $14,400.000 $7,552.000 $13,750.000 $12,500.000
465 6004 MANH (COMPL)(PRM)(72IN) EA 1.000 $15,500.000 $21,600.000 $12,325.000 $17,050.000 $15,000.000
465 6127 INLET (COMPL)(PSL)(FG)(4FTX4FT-3FTX3FT) EA 2.000 $7,750.000 $12,870.000 $7,638.600 $17,050.000 $15,000.000
465 6557 INLET (CURB)(SPL) EA 2.000 $1,000.000 $2,000.000 $1,100.000 $17,050.000 $12,500.000
471 6003 GRATE & FRAME EA 44.000 $1,800.000 $1,200.000 $2,250.000 $5,485.540 $10,000.000
479 6005 ADJUSTING MANHOLES (WATER VALVE BOX) EA 10.000 $1,600.000 $4,256.000 $500.000 $957.600 $1,100.000
500 6001 MOBILIZATION LS 1.000 $94,600.000 $65,000.000 $138,100.000 $214,688.660 $200,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 6.000 $5,000.000 $3,000.000 $8,500.000 $4,950.000 $8,500.000
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 500.000 $9.000 $8.000 $0.010 $1.100 $18.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 500.000 $3.000 $3.000 $0.010 $1.100 $9.000
528 6004 LANDSCAPE PAVERS SY 6.000 $200.000 $500.000 $660.800 $165.000 $500.000
529 6001 CONC CURB (TY I) LF 6.000 $30.000 $28.000 $27.530 $60.440 $150.000
529 6002 CONC CURB (TY II) LF 543.000 $45.000 $28.000 $28.500 $60.440 $100.000
529 6007 CONC CURB & GUTTER (TY I) LF 46.000 $35.000 $28.000 $39.070 $60.440 $150.000
529 6008 CONC CURB & GUTTER (TY II) LF 1,100.000 $50.000 $30.000 $42.000 $51.620 $150.000
530 6004 DRIVEWAYS (CONC) SY 168.000 $115.000 $75.000 $135.000 $140.900 $150.000
530 6005 DRIVEWAYS (ACP) SY 5.000 $110.000 $75.000 $135.000 $93.610 $85.000
531 6001 CONC SIDEWALKS (4") SY 518.000 $100.000 $75.000 $118.710 $110.850 $65.000
531 6018 CURB RAMPS (TY 1) SY 73.000 $165.000 $250.000 $185.000 $166.850 $325.000
531 6019 CURB RAMPS (TY 2) SY 54.000 $165.000 $250.000 $185.000 $166.850 $325.000
531 6020 CURB RAMPS (TY 3) SY 120.000 $165.000 $250.000 $185.000 $166.850 $325.000
531 6023 CURB RAMPS (TY 6) SY 17.000 $165.000 $250.000 $185.000 $141.660 $325.000
531 6024 CURB RAMPS (TY 7) SY 70.000 $165.000 $250.000 $185.000 $141.660 $325.000
531 6030 CURB RAMPS (TY 21) SY 15.000 $165.000 $250.000 $185.000 $141.660 $325.000
531 6033 CONC SIDEWALKS (SPECIAL) (TYPE B) SY 285.000 $230.000 $175.000 $255.000 $272.940 $150.000
618 6023 CONDT (PVC) (SCH 40) (2") LF 885.000 $20.000 $24.000 $16.500 $16.500 $20.000
618 6024 CONDT (PVC) (SCH 40) (2") (BORE) LF 229.000 $40.000 $42.000 $44.000 $44.000 $60.000
618 6037 CONDT (PVC) (SCH 40) (6") LF 1,431.000 $50.000 $33.750 $29.700 $29.700 $85.000
618 6038 CONDT (PVC) (SCH 40) (6") (BORE) LF 320.000 $70.000 $72.000 $66.000 $66.000 $120.000
624 6009 GROUND BOX TY D (162922) EA 19.000 $1,100.000 $1,500.000 $1,210.000 $1,210.000 $1,500.000
624 6010 GROUND BOX TY D (162922)W/APRON EA 1.000 $1,300.000 $2,340.000 $1,320.000 $1,320.000 $1,500.000
624 6028 REMOVE GROUND BOX EA 6.000 $250.000 $570.000 $698.500 $698.500 $200.000
644 6001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 10.000 $850.000 $1,500.000 $764.500 $385.000 $1,500.000
644 6068 RELOCATE SM RD SN SUP&AM TY 10BWG EA 17.000 $650.000 $250.000 $792.000 $385.000 $1,500.000
644 6076 REMOVE SM RD SN SUP&AM EA 1.000 $150.000 $100.000 $99.000 $55.000 $500.000
666 6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL) LF 95.000 $1.000 $4.800 $2.990 $4.400 $6.000
666 6048 REFL PAV MRK TY I (W)24"(SLD)(100MIL) LF 1,494.000 $15.000 $19.200 $6.220 $17.600 $20.000
666 6099 REF PAV MRK TY I(W)18"(YLD TRI)(100MIL) EA 8.000 $35.000 $42.000 $71.500 $38.500 $500.000
666 6303 RE PM W/RET REQ TY I (W)4"(SLD)(100MIL) LF 199.000 $1.000 $2.400 $2.260 $2.200 $10.000
668 6077 PREFAB PAV MRK TY C (W) (ARROW) EA 2.000 $200.000 $240.000 $302.500 $220.000 $250.000
668 6085 PREFAB PAV MRK TY C (W) (WORD) EA 2.000 $300.000 $300.000 $385.000 $275.000 $250.000
668 6112 PRE PM TY C (ACC PRK)(WHT)(SYMBL ONLY) EA 2.000 $650.000 $360.000 $495.000 $330.000 $500.000
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 271.000 $1.000 $0.420 $0.500 $0.390 $2.000
677 6003 ELIM EXT PAV MRK & MRKS (8") LF 101.000 $2.000 $0.720 $0.570 $0.660 $6.000
677 6005 ELIM EXT PAV MRK & MRKS (12") LF 650.000 $2.000 $1.020 $0.670 $0.940 $6.000
677 6007 ELIM EXT PAV MRK & MRKS (24") LF 197.000 $5.000 $4.800 $1.450 $4.400 $20.000
677 6008 ELIM EXT PAV MRK & MRKS (ARROW) EA 1.000 $90.000 $90.000 $71.500 $82.500 $250.000
677 6012 ELIM EXT PAV MRK & MRKS (WORD) EA 1.000 $120.000 $90.000 $82.500 $82.500 $250.000
677 6017 ELIM EXT PAV MRK & MRKS (SYMBOL) EA 1.000 $150.000 $180.000 $82.500 $165.000 $250.000
677 6018 ELIM EXT PAV MRK & MRKS (18")(YLD TRI) EA 10.000 $65.000 $54.000 $33.000 $49.500 $500.000
3076 6066 TACK COAT GAL 85.000 $12.000 $25.000 $11.000 $5.500 $10.000
3076 6072 D-GR HMA TY-D PG 76-22 (EXEMPT) TON 97.000 $300.000 $350.000 $350.000 $330.000 $500.000
4128 6001 PRECAST LIGHT POLE FOUNDATION EA 8.000 $2,500.000 $1,200.000 $0.010 $1,650.000 $5,000.000
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 198.000 $155.000 $80.000 $150.000 $1.100 $150.000
6185 6002 TMA (STATIONARY) DAY 99.000 $200.000 $300.000 $185.000 $1.100 $250.000
6185 6005 TMA (MOBILE OPERATION) DAY 4.000 $250.000 $350.000 $0.010 $1.100 $550.000
Totals: $1,069,870.00 $968,539.79 $1,064,707.94 $1,382,849.25 $2,164,333.00