LIVE OAK CR (0916-29-014)

Items: 55

County: LIVE OAK
Length: N/A
Highway: CR
District: CORPUS CHRISTI
Control Number: 0916-29-014
DBE Goal: N/A
Project: BR 2017(097)
Guaranty: N/A
Time: 177 WORKING DAYS
Engineer's Estimate: $1,603,810.50
Date: 02/02/2023 (3 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To: N/A
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (2)
E
Engineer's Estimate
$1,603,810.50
Over/Under Est: -0.91% -$14,543.60
Over/Under Est: 49.6% $795,457.45
Amt Left: 50.97% $810,001.05

Bid Items & Bid Tabulations

55 Total 0 of 55
LIVE OAK  |  CR  |  CORPUS CHRISTI  |  0916-29-014  |  02/02/2023  |  $1,603,810.50  |  BR 2017(097)  |  REPLACE BRIDGE AND APPROACHES  |  177 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
LISKA CONSTRUCTION COMPANY, INC.
PREPARING ROW
STA 5.100 $5,000.000 $15,614.760 $14,500.000
REMOVING STAB BASE AND ASPH PAV (6")
SY 514.000 $10.000 $16.180 $10.000
EXCAVATION (ROADWAY)
CY 241.000 $50.000 $44.330 $20.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 1,621.000 $50.000 $28.910 $45.000
COMPOST MANUF TOPSOIL (4")
SY 1,713.000 $8.000 $8.030 $15.000
STRAW/HAY MLCH SEED(PERM)(RURAL)(CLAY)
SY 1,713.000 $6.500 $4.260 $5.000
STRAW/HAY MLCH SEED(TEMP)(WARM)
SY 857.000 $1.500 $1.160 $5.000
STRAW/HAY MLCH SEED(TEMP)(COOL)
SY 857.000 $2.000 $1.160 $5.000
VEGETATIVE WATERING
MG 74.000 $50.000 $67.550 $200.000
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 187.000 $145.000 $177.040 $175.000
PRIME COAT (MULTI OPTION)
GAL 187.000 $15.000 $12.490 $33.000
ASPH (MULTI OPTION)
GAL 310.000 $15.000 $7.920 $23.000
ASPH(AC-15P, HFRS-2P OR CRS-2P)
GAL 255.000 $10.000 $8.520 $25.000
AGGR(TY-PB GR-4S OR TY-PB GR-4)(SAC-B)
CY 8.000 $500.000 $679.910 $2,730.000
AGGR(TY-PB GR-3 OR TY-PB GR-3S)(SAC-B)
CY 10.000 $500.000 $543.920 $2,268.000
CEM STABIL BKFL
CY 78.000 $200.000 $211.180 $210.000
TEMPORARY SPL SHORING
SF 841.000 $50.000 $61.610 $46.000
FOUNDATON LOADTEST(D4945)(DRILLD SHAFT)
EA 2.000 $75,000.000 $9,001.820 $21,000.000
DRILL SHAFT (36 IN)
LF 411.000 $750.000 $821.860 $1,150.000
CL C CONC (ABUT)
CY 38.000 $1,200.000 $1,154.800 $1,500.000
CL C CONC (CAP)
CY 22.200 $1,300.000 $2,406.960 $1,800.000
CL C CONC (COLUMN)
CY 19.000 $1,500.000 $1,630.380 $1,200.000
REINF CONC SLAB
SF 5,070.000 $25.000 $28.390 $35.000
PRESTR CONC GIRDER (TX28)
LF 774.000 $150.000 $193.070 $215.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 253.000 $185.000 $195.110 $175.000
RIPRAP (MOW STRIP)(4 IN)
CY 13.600 $550.000 $970.870 $1,300.000
RAIL (TY T223)
LF 438.000 $102.000 $170.560 $200.000
SEALED EXPANSION JOINT (4 IN) (SEJ - A)
LF 50.000 $180.000 $138.640 $275.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $78,000.000 $48,373.660 $90,000.000
MOBILIZATION
LS 1.000 $150,000.000 $193,525.680 $208,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 11.000 $5,000.000 $508.960 $1,500.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 90.000 $65.000 $37.830 $75.000
ROCK FILTER DAMS (REMOVE)
LF 90.000 $25.000 $11.580 $25.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 111.000 $25.000 $27.130 $75.000
CONSTRUCTION EXITS (REMOVE)
SY 111.000 $10.000 $8.750 $25.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,060.000 $4.000 $3.770 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,060.000 $1.500 $1.140 $1.000
CONSTRUCTING DETOURS
SY 45.000 $50.000 $173.080 $50.000
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 40.000 $40.000 $68.260 $90.000
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 80.000 $50.000 $50.380 $45.000
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 40.000 $15.000 $39.790 $90.000
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 80.000 $20.000 $37.040 $45.000
MTL BEAM GD FEN TRANS (TL2)
EA 4.000 $1,807.500 $1,798.820 $2,420.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,800.000 $3,893.570 $4,290.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 6.000 $750.000 $844.480 $1,000.000
REMOVE SM RD SN SUP&AM
EA 2.000 $65.000 $167.230 $250.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 4.000 $50.000 $103.070 $60.000
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)
EA 4.000 $50.000 $103.070 $60.000
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 1,020.000 $3.300 $4.300 $3.500
REFL PAV MRKR TY II-A-A
EA 13.000 $5.500 $20.080 $5.750
PAV SURF PREP FOR MRK (4")
LF 390.000 $1.100 $1.300 $0.580
TIP TESTING(DRILL SHAFT)
EA 3.000 $5,000.000 $3,862.470 $5,775.000
TEMP CONSTRUCTION ACCESS
LS 1.000 $75,000.000 $44,929.790 $475,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 14.000 $300.000 $184.190 $220.000
TMA (STATIONARY)
DAY 1.000 $350.000 $1,353.030 $515.000
Totals: $1,603,810.500 $1,589,266.910 $2,399,267.950