Show Job Controls
Bid Cobra

LIVE OAK IH 37 (0074-01-062)

Items: 56

County: LIVE OAK
Length: N/A
Highway: IH 37
District: CORPUS CHRISTI
Control Number: 0074-01-062
DBE Goal: 0.0%
Project: C 74-1-62
Guaranty: N/A
Time: 353 WORKING DAYS
Engineer's Estimate: $17,609,534.40
Date: 08/02/2024 (1 year ago)
Contract Number: N/A
Type: RESURFACE ROADWAY
Mail/Deliver Bids To: N/A
ERIC MARTINEZ
LUCIA ADAME
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$17,609,534.40
$14,385,828.18
Over/Under Est: -18.31% -$3,223,706.22
Over/Under Est: -16.47% -$2,900,229.00
Amt Left: 2.25% $323,477.22
$15,636,699.06
Over/Under Est: -11.2% -$1,972,835.34
Amt Left: 8.7% $1,250,870.88
Delta: -6.30% -$927,393.66
Subcontractor Percentage Amount
RELMCO, INC. 27.97% $4,166,769.75
HIGHWAY BARRICADES AND SERVICES, LLC 3.71% $552,689.16
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. 3.15% $469,264.38
SCOTT DERR PAINTING CO, LLC 0.80% $119,178.26
4E TREE WORX LLC 0.57% $84,914.51
PROFESSIONAL TRAFFIC CONTROL LLC 0.27% $40,222.66
INTERSTATE BARRICADES & MARKINGS, INC. 0.24% $35,753.48
A K FUQUAY CONSTRUCTION 0.08% $11,917.83
Total: 36.79% $5,480,710.03

Bid Items & Bid Tabulations

56 Total 0 of 56
LIVE OAK  |  IH 37  |  CORPUS CHRISTI  |  0074-01-062  |  08/02/2024  |  $17,609,534.40  |  C 74-1-62  |  RESURF ROADWAY  |  353 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS MATERIALS GROUP, INC.
LONE STAR PAVING COMPANY
HUNTER INDUSTRIES, LTD.
REMOVING CONCRETE(MOW STRIP)
LF 12,499.000 $11.000 $11.000 $5.500 $9.400
FLEXIBLE PAVEMENT STRUCTURE REPAIR(3")
SY 17.000 $100.000 $453.000 $805.000 $253.000
PLAN & TEXT ASPH CONC PAV(0" TO 3")
SY 70,339.000 $4.000 $4.000 $3.400 $3.660
PLANE ASPH CONC PAV (0" TO 3/4")
SY 15,804.000 $4.000 $2.650 $4.850 $3.660
PENETRATING CONCRETE SURFACE TREATMENT
SY 20,796.000 $15.000 $9.500 $8.800 $32.000
RIPRAP (MOW STRIP)(4 IN)
CY 702.000 $600.000 $495.000 $495.000 $800.000
STR STEEL (NBIS)
LB 981.000 $15.000 $30.000 $31.000 $15.000
RETROFIT RAIL (TY SSTR)
LF 9,161.000 $250.000 $178.000 $192.000 $235.000
CLEAN EXIST CULVERTS
EA 22.000 $2,600.000 $1,600.000 $1,600.000 $1,750.000
MOBILIZATION
LS 1.000 $1,102,693.000 $1,300,000.000 $1,375,000.000 $1,191,713.590
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 18.000 $7,500.000 $11,500.000 $4,500.000 $7,121.140
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,585.000 $4.200 $5.500 $3.000 $6.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,585.000 $2.400 $2.850 $1.000 $1.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 22,170.000 $45.000 $35.000 $35.000 $34.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 64,530.000 $7.300 $6.000 $6.500 $11.000
PORT CTB (STKPL)(SGL SLP)(TY 1)
LF 480.000 $11.000 $20.000 $21.000 $18.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 21,690.000 $25.000 $20.000 $21.000 $15.000
RUMBLE STRIPS (SHOULDER)
LF 319,395.000 $0.200 $0.100 $0.140 $0.080
MTL W-BEAM GD FEN (TIM POST)
LF 7,811.000 $28.000 $28.100 $24.000 $26.430
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 38.000 $2,500.000 $2,400.000 $2,600.000 $2,695.780
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 12.000 $1,100.000 $1,403.000 $1,600.000 $1,196.950
REMOVE METAL BEAM GUARD FENCE
LF 10,682.000 $3.500 $4.000 $1.000 $2.120
GUARDRAIL END TREATMENT (INSTALL)
EA 36.000 $3,500.000 $370.000 $2,900.000 $3,029.440
GUARDRAIL END TREATMENT (REMOVE)
EA 48.000 $350.000 $261.000 $190.000 $317.770
CRASH CUSH ATTEN (MOVE & RESET)
EA 27.000 $2,000.000 $900.000 $880.000 $1,461.760
CRASH CUSH ATTEN (REMOVE)
EA 9.000 $1,350.000 $800.000 $880.000 $773.250
CRASH CUSH ATTEN (INSTL) (S) (TL3)
EA 9.000 $15,000.000 $7,500.000 $9,000.000 $8,156.190
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 343.000 $25.000 $50.000 $22.000 $42.000
WK ZN PAV MRK REMOV (W)6"(BRK)
LF 10,764.000 $1.000 $0.600 $0.750 $0.600
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 107,610.000 $1.400 $0.300 $0.650 $0.300
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 43,055.000 $1.400 $0.300 $0.650 $0.300
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 13,209.000 $2.500 $1.700 $1.750 $1.690
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 26.000 $3.500 $1.700 $1.600 $1.690
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
LF 1,508.000 $1.000 $0.620 $1.600 $0.620
REFL PAV MRK TY II (W) 6" (BRK)
LF 42,700.000 $0.400 $0.320 $0.250 $0.320
REFL PAV MRK TY II (W) 6" (DOT)
LF 1,508.000 $0.750 $0.320 $0.700 $0.320
REFL PAV MRK TY II (W) 6" (SLD)
LF 171,913.000 $0.400 $0.320 $0.200 $0.320
REFL PAV MRK TY II (W) 8" (SLD)
LF 6,680.000 $0.750 $0.480 $0.450 $0.480
REFL PAV MRK TY II (W) 12" (SLD)
LF 958.000 $4.000 $2.000 $1.450 $2.000
REFL PAV MRK TY II (Y) 6" (SLD)
LF 171,064.000 $0.500 $0.320 $0.200 $0.320
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 42,700.000 $1.000 $0.660 $0.650 $0.660
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 171,913.000 $0.900 $0.660 $0.600 $0.660
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 171,064.000 $1.000 $0.660 $0.650 $0.660
REFL PAV MRK TY I (W)8"(SLD)(100MIL)1X
LF 6,680.000 $0.900 $1.000 $1.000 $1.000
PREFAB PAV MRK TY C (W) (12") (SLD)
LF 958.000 $8.000 $6.000 $9.000 $6.000
PREFAB PAV MRK TY C (W) (SYMBOL)
EA 7.000 $600.000 $500.000 $2,350.000 $500.000
REFL PAV MRKR TY II-C-R
EA 2,469.000 $5.000 $5.000 $5.000 $5.000
ELIM EXT PAV MRK & MRKS (6")
LF 161,429.000 $2.000 $0.550 $0.600 $0.550
STRIP MOWING
AC 658.000 $50.000 $100.000 $140.000 $85.000
TREE AND BRUSH REMOVAL
AC 8.320 $12,000.000 $3,600.000 $5,875.000 $6,050.000
TBWC (MEMBRANE)
GAL 151,810.000 $4.500 $4.000 $3.850 $4.210
TBWC PG76-22 SAC-A TY C
TON 37,953.000 $200.000 $169.000 $175.000 $167.500
FILLING MILLED ASPHALT RUMBLE STRIPS
LF 57,150.000 $5.000 $3.250 $2.500 $3.220
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $13,000.000 $15,200.000 $13,000.000 $12,000.000
TMA (STATIONARY)
DAY 302.000 $250.000 $200.000 $220.000 $300.000
TMA (MOBILE OPERATION)
HR 64.000 $100.000 $100.000 $160.000 $100.000
Totals: $17,609,534.400 $14,385,828.180 $14,709,305.400 $15,636,699.060