Job Info for 0073-07-068

County: LIVE OAK Highway: IH 37 Date: 06/29/2022 (2 years ago) Engineer's Estimate: $893,116 Control Number: 0073-07-068
Project: STP 2022(831)TP District: CORPUS CHRISTI Time: 85 WORKING DAYS Type: TRANSPORTATION NON-ROADWAY
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $893,115.82
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.   $1,030,452.14 1
15.38% | $137,336.32
CK NEWBERRY, LLC   $1,448,533.31 2
62.19% | $555,417.49
40.57% | $418,081.17
LCR TOTAL TRANSPORT LLC   $1,548,461.65 3
73.38% | $655,345.83
50.27% | $518,009.51
6.90% | $99,928.34
ACME BRIDGE COMPANY, INC.   $1,590,474.20 4
78.08% | $697,358.38
54.35% | $560,022.06
2.71% | $42,012.55
TEXAS MATERIALS GROUP, INC.   $1,614,867.35 5
80.81% | $721,751.53
56.71% | $584,415.21
1.53% | $24,393.15
Subcontractor Percentage Amount
THOMAS EXCAVATIONS AND UTILITIES LLC 4.36% $44,927.71
TEX OP CONSTRUCTION, LP 2.01% $20,712.09
HIGHWAY BARRICADES AND SERVICES, LLC 1.66% $17,105.51
Total: 8.03% $82,745.31

Bid Items

Items: 28, 0 filtered
LIVE OAK IH 37  |  CORPUS CHRISTI  |  0073-07-068  |  06/29/2022  |  $893,116  |  STP 2022(831)TP  |  TRANSPORT NON-ROADWAY  |  85 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate SALINAS CONSTRUCTION TECHNOLOGIES, LTD. CK NEWBERRY, LLC LCR TOTAL TRANSPORT LLC ACME BRIDGE COMPANY, INC. TEXAS MATERIALS GROUP, INC.
104 6015 REMOVING CONC (SIDEWALKS) SY 1,984.000 $12.000 $10.300 $15.000 $28.000 $17.300 $21.000
104 6022 REMOVING CONC (CURB AND GUTTER) LF 981.000 $7.930 $6.860 $15.000 $28.000 $9.000 $12.000
112 6003 SUBGRADE WIDENING (DENS CONT) SY 1,947.000 $2.500 $9.540 $15.000 $6.500 $28.000 $24.000
192 6021 PLANT MATERIAL (5 GAL) (TREE) EA 6.000 $150.000 $1,388.440 $1,000.000 $700.000 $234.000 $700.000
247 6041 FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS) CY 325.000 $69.260 $129.070 $295.000 $134.000 $230.000 $230.000
260 6012 LIME(HYD,COM OR QK)(SLRY)OR QK(DRY) TON 181.000 $200.000 $297.580 $200.000 $349.000 $220.000 $330.000
260 6027 LIME TRT (EXST MATL)(8") SY 1,947.000 $15.000 $13.180 $20.000 $15.000 $11.600 $13.500
310 6009 PRIME COAT (MC-30) GAL 584.000 $4.330 $9.880 $11.000 $8.500 $5.900 $13.250
316 6001 ASPH (MULTI OPTION) GAL 623.000 $3.170 $7.900 $10.000 $7.300 $29.200 $8.000
316 6427 AGGR(TY-PB GR-4S OR TY-PB GR-4)(SAC-B) CY 18.000 $146.360 $470.360 $1,000.000 $425.000 $1,400.000 $475.000
354 6021 PLANE ASPH CONC PAV(0" TO 2") SY 19,793.000 $2.500 $2.170 $4.000 $5.600 $2.350 $4.500
500 6001 MOBILIZATION LS 1.000 $50,553.730 $99,150.510 $125,000.000 $101,000.000 $145,000.000 $162,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 5.000 $4,334.600 $1,065.150 $5,000.000 $2,600.000 $4,000.000 $19,250.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 1,925.000 $3.000 $3.350 $5.000 $6.000 $5.100 $5.250
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 1,925.000 $1.000 $0.880 $2.000 $1.250 $1.750 $0.750
529 6007 CONC CURB & GUTTER (TY I) LF 981.000 $23.590 $19.650 $40.010 $48.000 $52.900 $45.000
531 6002 CONC SIDEWALKS (5") SY 2,005.000 $75.000 $61.070 $95.000 $117.000 $97.600 $92.000
531 6018 CURB RAMPS (TY 1) SY 428.000 $125.000 $112.310 $150.000 $117.000 $70.000 $150.000
666 6302 RE PM W/RET REQ TY I (W)4"(SLD)(090MIL) LF 3,873.000 $0.320 $2.170 $2.500 $2.400 $2.300 $1.950
668 6111 PRE PM TY C (ACC PRK)(BLU)(SYMBL ONLY) EA 4.000 $250.000 $267.210 $300.000 $260.000 $257.000 $220.000
752 6005 TREE REMOVAL (4" - 12" DIA) EA 1.000 $454.000 $857.030 $2,000.000 $1,830.000 $2,920.000 $325.000
752 6006 TREE REMOVAL (12" - 18" DIA) EA 2.000 $1,302.000 $1,254.300 $2,500.000 $2,125.000 $4,440.000 $850.000
752 6008 TREE REMOVAL (24" - 30" DIA) EA 3.000 $1,820.000 $2,048.830 $3,000.000 $3,000.000 $6,430.000 $1,600.000
772 6003 POST AND CABLE FENCE (NEW INSTALLATION) LF 2,173.000 $15.000 $19.270 $20.000 $24.000 $23.000 $22.000
3076 6042 D-GR HMA TY-D SAC-B PG70-22 TON 2,713.000 $110.000 $135.000 $165.000 $199.000 $199.000 $185.000
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 170.000 $75.000 $76.570 $100.000 $225.000 $338.000 $85.000
6185 6002 TMA (STATIONARY) DAY 85.000 $250.000 $204.420 $125.000 $250.000 $139.000 $175.000
7296 6001 WATER AND WASTEWATER UTILITY RELOCATION LS 1.000 $28,500.000 $32,885.790 $85,000.000 $48,000.000 $105,000.000 $82,500.000