Job Info for 0073-07-063

County: LIVE OAK Highway: IH 37 Date: 01/04/2017 (7 years ago) Engineer's Estimate: $951,560 Control Number: 0073-07-063
Project: STP 1602(446)HES District: CORPUS CHRISTI Time: 81 WORKING DAYS Type: INSTALL MEDIAN BARRIER

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $951,560.00
GRATIOT CONSTRUCTION, LTD.   $728,162.74 1
-23.48% | -$223,397.26
MASSANA CONSTRUCTION INC.   $800,190.00 2
-15.91% | -$151,370.00
9.89% | $72,027.26
SCR CIVIL CONSTRUCTION, LLC   $819,388.50 3
-13.89% | -$132,171.50
12.53% | $91,225.76
2.40% | $19,198.50
VANN/ELLI, INC.   $922,453.00 4
-3.06% | -$29,107.00
26.68% | $194,290.26
12.58% | $103,064.50
DAN WILLIAMS COMPANY   $946,272.50 5
-0.56% | -$5,287.50
29.95% | $218,109.76
2.58% | $23,819.50
CHAMPION INFRASTRUCTURE, LLC   $1,364,240.00 6
43.37% | $412,680.00
87.35% | $636,077.26
44.17% | $417,967.50
FNH CONSTRUCTION, LLC   $1,506,760.00 7
58.35% | $555,200.00
106.93% | $778,597.26
10.45% | $142,520.00

Bid Items

Items: 8, 0 filtered
LIVE OAK IH 37  |  CORPUS CHRISTI  |  0073-07-063  |  01/04/2017  |  $951,560  |  STP 1602(446)HES  |  INSTL MEDIAN BARRIER  |  81 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate GRATIOT CONSTRUCTION, LTD. MASSANA CONSTRUCTION INC. SCR CIVIL CONSTRUCTION, LLC VANN/ELLI, INC. DAN WILLIAMS COMPANY CHAMPION INFRASTRUCTURE, LLC FNH CONSTRUCTION, LLC
432 6046 RIPRAP (MOW STRIP)(5 IN) CY 1,296.000 $500.000 $314.550 $410.000 $340.000 $428.000 $365.000 $600.000 $660.000
500 6001 MOBILIZATION LS 1.000 $61,000.000 $72,505.810 $25,000.000 $81,000.000 $80,000.000 $92,000.000 $80,000.000 $150,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 5.000 $5,000.000 $872.090 $4,000.000 $2,575.000 $4,000.000 $18,000.000 $3,500.000 $8,500.000
506 6042 BIODEG EROSN CONT LOGS (INSTL) (18") LF 600.000 $6.000 $6.980 $5.000 $6.000 $10.500 $8.000 $10.000 $15.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 600.000 $1.250 $1.450 $2.000 $1.250 $5.000 $2.000 $5.000 $8.000
543 6002 CABLE BARRIER SYSTEM (TL-4) LF 25,290.000 $7.000 $7.980 $7.000 $9.150 $8.500 $9.250 $16.000 $15.000
543 6020 CABLE BARRIER TERMINAL SECTION (TL-4) EA 16.000 $2,200.000 $2,145.350 $2,400.000 $3,000.000 $2,500.000 $2,900.000 $4,500.000 $4,000.000
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 14.000 $70.000 $174.420 $300.000 $80.000 $250.000 $350.000 $250.000 $125.000
Totals: $951,560.00 $728,162.74 $800,190.00 $819,388.50 $922,453.00 $946,272.50 $1,364,240.00 $1,506,760.00