LIMESTONE FM 1245 (1191-03-033)

Items: 64

County: LIMESTONE
Length: N/A
Highway: FM 1245
District: WACO
Control Number: 1191-03-033
DBE Goal: N/A
Project: BR 2020(319)
Guaranty: N/A
Time: 210 WORKING DAYS
Engineer's Estimate: $2,910,759.50
Date: 08/04/2021 (4 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (3)
E
Engineer's Estimate
$2,910,759.50
$2,816,412.46
Over/Under Est: -3.24% -$94,347.04
Over/Under Est: 14.63% $425,768.00
Amt Left: 18.47% $520,115.04
$3,407,720.65
Over/Under Est: 17.07% $496,961.15
Amt Left: 21% $591,308.19
Delta: -2.13% -$71,193.15

Bid Items & Bid Tabulations

64 Total 0 of 64
LIMESTONE  |  FM 1245  |  WACO  |  1191-03-033  |  08/04/2021  |  $2,910,759.50  |  BR 2020(319)  |  REPLACE BRIDGE AND APPROACHES  |  210 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
STATELINE CONSTRUCTION, LLC
HODGES AND SON CONSTRUCTION COMPANY, INC.
A. L. HELMCAMP, INC.
PREPARING ROW
STA 15.800 $2,500.000 $950.000 $2,600.000 $2,300.000
REMOVING CONC (RIPRAP)
SY 559.000 $10.000 $12.000 $30.000 $23.000
REMOVING CONC (DRIVEWAYS)
SY 83.000 $15.000 $25.000 $30.000 $37.000
REMOVING CONCRETE(MOW STRIP)
LF 1,865.000 $10.000 $12.000 $12.000 $10.000
REMOVING STAB BASE & ASPH PAV (7"-12")
SY 3,510.000 $5.000 $6.000 $8.000 $6.000
EXCAVATION (ROADWAY)
CY 707.000 $13.000 $16.000 $20.000 $22.000
EXCAVATION (CHANNEL)
CY 160.000 $13.000 $40.000 $20.000 $48.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 1,413.000 $16.000 $17.500 $20.000 $42.000
FURNISHING AND PLACING TOPSOIL (4")
SY 10,065.000 $2.000 $5.000 $4.000 $2.600
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 10,065.000 $0.700 $0.750 $0.500 $0.450
BROADCAST SEED (TEMP)(WARM OR COOL)
SY 10,065.000 $0.700 $0.750 $0.500 $0.350
VEGETATIVE WATERING
MG 165.000 $25.000 $20.000 $1.000 $22.000
SOIL RETENTION BLANKETS (CL 1) (TY C)
SY 1,532.000 $2.000 $5.000 $3.000 $2.100
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
CY 1,203.000 $55.000 $77.000 $60.000 $68.000
PRIME COAT(MC-30 OR AE-P)
GAL 753.000 $5.000 $14.000 $5.000 $10.000
ASPH (CRS-2)
GAL 1,695.000 $5.000 $8.500 $3.000 $5.600
AGGR(TY-D GR-4 OR TY-L GR-4)
CY 29.000 $300.000 $675.000 $400.000 $750.000
CEM STABIL BKFL
CY 324.000 $150.000 $245.000 $250.000 $200.000
DRILL SHAFT (18 IN)
LF 140.000 $110.000 $145.000 $80.000 $180.000
DRILL SHAFT (36 IN)
LF 1,313.000 $200.000 $232.000 $145.000 $230.000
CL B CONC (FLUME)
CY 14.800 $500.000 $800.000 $550.000 $770.000
CL C CONC (ABUT)(HPC)
CY 102.100 $1,000.000 $825.000 $950.000 $1,800.000
CL C CONC (CAP)(HPC)
CY 93.500 $1,200.000 $975.000 $1,100.000 $1,800.000
CL C CONC (COLUMN)(HPC)
CY 55.900 $1,500.000 $1,200.000 $1,100.000 $1,000.000
REINF CONC SLAB
SF 17,850.000 $19.000 $15.250 $22.000 $23.000
APPROACH SLAB
CY 113.700 $500.000 $500.000 $600.000 $1,000.000
PRESTR CONC BOX BEAM (5XB20)
LF 534.000 $220.000 $195.000 $270.000 $210.000
PRESTR CONC GIRDER (TX54)
LF 1,550.000 $150.000 $175.000 $270.000 $190.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 1,111.000 $110.000 $105.000 $125.000 $90.000
RIPRAP (STONE PROTECTION)(24 IN)
CY 2,221.000 $115.000 $105.000 $125.000 $90.000
RIPRAP (MOW STRIP)(4 IN)
CY 82.000 $425.000 $400.000 $550.000 $600.000
RAIL (TY T1W)
LF 856.000 $190.000 $180.000 $170.000 $220.000
RAIL (TY T223)
LF 310.000 $110.000 $150.000 $140.000 $220.000
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 168.000 $110.000 $94.000 $80.000 $100.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $30,000.000 $35,000.000 $60,000.000 $34,000.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $100,000.000 $75,000.000 $120,000.000 $55,000.000
MOBILIZATION
LS 1.000 $265,000.000 $90,000.000 $310,000.000 $300,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 14.000 $5,000.000 $7,500.000 $2,500.000 $4,500.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 132.000 $30.000 $35.000 $5.000 $37.000
ROCK FILTER DAMS (REMOVE)
LF 132.000 $10.000 $14.000 $5.000 $15.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 3,245.000 $3.000 $3.250 $1.000 $2.200
TEMP SEDMT CONT FENCE (REMOVE)
LF 3,245.000 $1.000 $1.350 $1.000 $0.750
DRIVEWAYS (CONC)
SY 69.000 $75.000 $70.000 $60.000 $165.000
RUMBLE STRIPS (SHOULDER)
LF 1,623.000 $0.250 $2.250 $2.000 $3.200
RUMBLE STRIPS (CENTERLINE)
LF 811.000 $0.250 $2.250 $2.000 $5.500
MTL W-BEAM GD FEN (STEEL POST)
LF 650.000 $25.000 $36.380 $30.000 $27.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 8.000 $1,750.000 $2,361.210 $1,900.000 $2,000.000
REMOVE METAL BEAM GUARD FENCE
LF 875.000 $3.000 $3.250 $2.500 $2.200
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 8.000 $235.000 $200.000 $200.000 $220.000
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $2,500.000 $4,750.000 $2,800.000 $2,700.000
GUARDRAIL END TREATMENT (REMOVE)
EA 8.000 $325.000 $180.990 $250.000 $220.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 4.000 $600.000 $575.000 $800.000 $530.000
REMOVE SM RD SN SUP&AM
EA 4.000 $100.000 $379.300 $100.000 $160.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 28.000 $25.000 $19.150 $30.000 $16.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 35.000 $35.000 $44.670 $30.000 $40.000
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 1,900.000 $2.000 $2.470 $2.000 $2.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 1,260.000 $2.000 $2.470 $2.000 $2.000
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 158.000 $2.000 $2.960 $2.000 $2.000
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 1,900.000 $2.000 $2.470 $2.000 $2.000
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 630.000 $2.000 $2.470 $2.000 $2.000
REFL PAV MRKR TY II-A-A
EA 40.000 $20.000 $19.760 $10.000 $11.000
TACK COAT
GAL 942.000 $3.000 $5.390 $2.000 $7.800
D-GR HMA TY-C SAC-B PG64-22 (EXEMPT)
TON 412.000 $130.000 $140.000 $118.000 $225.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $10,000.000 $6,000.000 $30,000.000 $10,000.000
Totals: $2,910,759.500 $2,816,412.460 $3,336,527.500 $3,407,720.650