LIBERTY FM2090 (6499-84-001)

Items: 37

County: LIBERTY
Length: 0.0100 MILES
Highway: FM2090
District: BEAUMONT
Control Number: 6499-84-001
DBE Goal: 0.0%
Project: RMC - A00220509
Guaranty: $13,000.00
Time: 45 WORKING DAYS
Engineer's Estimate: $693,480.79
Date: 06/10/2026 11:00 AM CDT (5 weeks ago)
Contract Number: 6262002
Type: BASE REPAIR WITH SEAL COAT AND/OR OVERLAY
Project ID: A00220509
Project Description: BASE REPAIR, LEVEL UP, AND OVERLAY
Mail/Deliver Bids To: N/A
ROBERTO M RODRIGUEZ
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$693,480.79
Over/Under Est: 4.75% $32,925.51
Over/Under Est: 25.71% $178,320.71
Amt Left: 20.02% $145,395.20
Over/Under Est: 28.22% $195,682.46
Amt Left: 22.41% $162,756.95
Delta: -1.99% -$17,361.75

Bid Items & Bid Tabulations

37 Total 0 of 37
LIBERTY  |  FM2090  |  BEAUMONT  |  6499-84-001  |  06/10/2026 11:00 AM CDT  |  $693,480.79  |  RMC - A00220509  |  BASE REPAIR WITH SEAL COAT AND/OR OV...  |  45 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
FORDE CONSTRUCTION COMPANY, INC.
TEXAS MATERIALS GROUP, INC.
BACKFILL (TY A OR B)
STA 49.000 $195.000 $320.000 $530.000 $398.750
BROADCAST SEED (TEMP_WARM)
SY 5,093.000 $0.130 $0.500 $1.000 $0.250
VEGETATIVE WATERING
TGL 14.000 $6.500 $30.000 $50.000 $114.500
SP MIXES SP-C SAC-A PG76-22
TON 2,198.000 $150.000 $142.700 $160.000 $170.500
TACK COAT
GAL 1,600.000 $5.000 $4.500 $5.250 $4.750
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 859.000 $50.000 $71.150 $92.000 $112.250
PLANE ASPH CONC PAV (2.5")
SY 1,525.000 $6.500 $10.800 $12.000 $6.500
PLANE ASPH CONC PAV (0" TO 2-1/2")
SY 1,288.000 $3.000 $3.100 $14.000 $9.750
RIPRAP (MOW STRIP)(4 IN)
CY 64.000 $535.000 $800.000 $920.000 $733.500
MOBILIZATION
LS 1.000 $61,545.000 $67,000.000 $60,000.000 $88,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $6,750.000 $2,500.000 $5,000.000 $2,200.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 45.000 $69.000 $75.000 $170.000 $91.750
TMA (STATIONARY)
DAY 43.000 $192.000 $275.000 $170.000 $403.500
TMA (MOBILE OPERATION)
DAY 2.000 $250.000 $125.000 $750.000 $947.250
DRIVEWAYS (ACP)
SY 1,262.000 $40.000 $38.600 $56.000 $34.500
DRIVEWAYS (BASE)
SY 391.000 $23.000 $43.150 $54.000 $63.500
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 2,600.000 $0.500 $0.600 $1.800 $2.000
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 4,950.000 $0.500 $0.320 $1.000 $1.250
MTL W-BEAM GD FEN (TIM POST)
LF 1,300.000 $28.000 $22.750 $24.000 $31.750
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,200.000 $2,100.000 $1,520.000 $2,072.500
REMOVE METAL BEAM GUARD FENCE
LF 1,300.000 $3.000 $3.400 $3.500 $3.250
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,100.000 $2,860.000 $3,005.000 $3,607.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $235.000 $200.000 $210.000 $305.500
MAILBOX INSTALL-M (TWG-POST) TY 1
EA 5.000 $680.000 $660.000 $690.000 $727.500
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 12.000 $310.000 $290.000 $305.000 $275.000
MAILBOX INSTALL-D (TWG-POST) TY 2
EA 1.000 $290.000 $332.000 $348.000 $275.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 7.000 $715.000 $620.000 $650.000 $593.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 10.000 $825.000 $841.000 $885.000 $825.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 1.000 $930.000 $850.000 $890.000 $1,216.500
REMOVE SM RD SN SUP&AM
EA 18.000 $110.000 $88.000 $93.000 $116.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 28.000 $7.000 $26.000 $27.000 $40.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 524.000 $1.500 $1.000 $3.000 $1.250
REFL PAV MRK TY I (W)6"(SLD)(090MIL)
LF 10,470.000 $0.460 $0.780 $2.100 $1.250
REFL PAV MRK TY I (Y)6"(BRK)(090MIL)
LF 610.000 $0.550 $1.000 $1.150 $1.250
REFL PAV MRK TY I (Y)6"(SLD)(090MIL)
LF 8,195.000 $0.500 $0.780 $0.900 $1.250
PREFAB PM TY C (W)(24")(SLD)
LF 60.000 $14.000 $22.000 $25.000 $25.000
REFL PAV MRKR TY II-C-R
EA 129.000 $4.000 $6.000 $6.500 $8.500
Totals: $693,480.790 $726,406.300 $871,801.500 $889,163.250