PREPARING ROW
|
STA
|
28.000
|
$2,250.000
|
$800.000
|
$22,000.000
|
|
|
REMOVING CONC (PAV)
|
SY
|
6,973.000
|
$5.530
|
$9.000
|
$11.000
|
|
|
REMOVING CONCRETE(MOW STRIP)
|
LF
|
2,176.000
|
$8.000
|
$5.500
|
$4.000
|
|
|
REMOVING STAB BASE AND ASPH PAV (0-4")
|
SY
|
7,864.000
|
$12.000
|
$4.000
|
$4.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
811.000
|
$20.000
|
$24.000
|
$80.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
7,579.000
|
$7.000
|
$25.000
|
$30.000
|
|
|
FURNISHING AND PLACING TOPSOIL (4")
|
SY
|
3,671.000
|
$1.170
|
$7.500
|
$2.000
|
|
|
BROADCAST SEED (PERM) (RURAL) (CLAY)
|
SY
|
3,671.000
|
$0.280
|
$0.280
|
$1.880
|
|
|
VEGETATIVE WATERING
|
MG
|
62.800
|
$17.850
|
$33.000
|
$22.000
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY A)
|
SY
|
1,871.000
|
$0.930
|
$1.280
|
$3.000
|
|
|
PROOF ROLLING
|
HR
|
40.000
|
$100.000
|
$92.000
|
$87.000
|
|
|
LIME (HYD, COM, OR QK(SLURRY))
|
TON
|
138.000
|
$178.220
|
$220.000
|
$202.000
|
|
|
LIME TRT (SUBGRADE)(6")
|
SY
|
9,231.000
|
$3.820
|
$4.500
|
$7.000
|
|
|
D-GR HMA(SQ) TY-B PG64-22
|
TON
|
4,062.000
|
$83.420
|
$102.000
|
$100.000
|
|
|
D-GR HMA(SQ) TY-D SAC-A PG70-22
|
TON
|
1,016.000
|
$110.000
|
$130.000
|
$120.000
|
|
|
D-GR HMA (SQ) TY-D PG64_22(LEVEL-UP)
|
TON
|
301.000
|
$119.810
|
$144.000
|
$110.000
|
|
|
TACK COAT
|
GAL
|
2,770.000
|
$5.800
|
$4.600
|
$2.500
|
|
|
PLAN & TEXT ASPH CONC PAV(0" TO 2")
|
SY
|
1,814.000
|
$1.450
|
$15.100
|
$8.000
|
|
|
CEM STABIL BKFL
|
CY
|
260.000
|
$97.000
|
$160.000
|
$169.000
|
|
|
DRILL SHAFT (24 IN)
|
LF
|
3,378.000
|
$200.000
|
$240.000
|
$240.000
|
|
|
CL C CONC (ABUT)
|
CY
|
84.200
|
$950.000
|
$2,450.000
|
$1,500.000
|
|
|
CL C CONC (CAP)
|
CY
|
44.000
|
$1,000.000
|
$3,275.000
|
$2,100.000
|
|
|
CL C CONC (COLUMN)
|
CY
|
20.000
|
$1,000.000
|
$1,975.000
|
$2,500.000
|
|
|
REINF CONC SLAB (SLAB BEAM)
|
SF
|
11,848.000
|
$22.000
|
$28.450
|
$28.000
|
|
|
APPROACH SLAB
|
CY
|
216.000
|
$590.000
|
$650.000
|
$475.000
|
|
|
PRESTR CONC SLAB BEAM (4SB12)
|
LF
|
323.940
|
$150.000
|
$203.000
|
$300.000
|
|
|
PRESTR CONC SLAB BEAM (5SB12)
|
LF
|
647.880
|
$150.000
|
$170.000
|
$250.000
|
|
|
PRESTR CONC SLAB BEAM (4SB15)
|
LF
|
492.000
|
$165.000
|
$179.000
|
$250.000
|
|
|
PRESTR CONC SLAB BEAM (5SB15)
|
LF
|
984.000
|
$180.000
|
$169.000
|
$182.000
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
366.000
|
$546.910
|
$533.000
|
$537.000
|
|
|
RIPRAP (STONE PROTECTION)(12 IN)
|
CY
|
459.000
|
$110.000
|
$156.000
|
$184.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
224.000
|
$450.000
|
$594.000
|
$500.000
|
|
|
STR STEEL (MISC NON - BRIDGE)
|
LB
|
658.000
|
$5.500
|
$11.500
|
$16.000
|
|
|
RAIL (TY T223)
|
LF
|
623.000
|
$100.000
|
$188.000
|
$111.000
|
|
|
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
|
EA
|
2.000
|
$37,000.000
|
$20,800.000
|
$100,000.000
|
|
|
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
|
EA
|
1.000
|
$50,000.000
|
$120,640.000
|
$138,000.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$430,300.000
|
$581,900.000
|
$700,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
15.000
|
$5,557.950
|
$4,000.000
|
$40,000.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 1)
|
LF
|
520.000
|
$20.690
|
$32.800
|
$33.800
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
520.000
|
$7.430
|
$9.100
|
$8.810
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
4,920.000
|
$2.830
|
$2.900
|
$2.900
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
4,920.000
|
$0.920
|
$0.760
|
$0.640
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (18")
|
LF
|
1,000.000
|
$5.730
|
$5.100
|
$5.800
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
1,000.000
|
$0.850
|
$1.040
|
$1.350
|
|
|
CONSTRUCTING DETOURS
|
SY
|
7,774.000
|
$108.940
|
$46.000
|
$51.000
|
|
|
ONE-WAY TRAF CONT (PORT TRAF SIG)
|
MO
|
16.000
|
$3,000.000
|
$4,250.000
|
$2,000.000
|
|
|
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
|
LF
|
4,170.000
|
$31.020
|
$72.000
|
$20.000
|
|
|
PORT CTB (MOVE)(F-SHAPE)(TY 1)
|
LF
|
10,770.000
|
$4.000
|
$4.100
|
$12.000
|
|
|
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
|
LF
|
4,170.000
|
$6.000
|
$15.000
|
$8.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
3,450.000
|
$27.330
|
$26.500
|
$25.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
12.000
|
$2,451.290
|
$1,875.000
|
$1,800.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
1,350.000
|
$3.500
|
$2.600
|
$2.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
12.000
|
$3,237.670
|
$2,900.000
|
$2,950.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
12.000
|
$195.000
|
$310.000
|
$200.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
24.000
|
$1,296.810
|
$1,210.000
|
$480.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
10.000
|
$806.770
|
$855.000
|
$480.000
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
10.000
|
$8,000.000
|
$9,100.000
|
$7,100.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
5.000
|
$493.510
|
$520.000
|
$600.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
7.000
|
$104.960
|
$76.000
|
$20.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
82.000
|
$115.250
|
$27.800
|
$23.000
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
20,480.000
|
$1.050
|
$1.250
|
$0.540
|
|
|
WK ZN PAV MRK REMOV (W)24"(SLD)
|
LF
|
288.000
|
$7.710
|
$6.100
|
$3.000
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
34,560.000
|
$1.000
|
$1.200
|
$0.300
|
|
|
PAVEMENT SEALER 4"
|
LF
|
1,422.000
|
$0.270
|
$0.210
|
$0.060
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
|
LF
|
5,270.000
|
$0.350
|
$0.660
|
$0.750
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
|
LF
|
200.000
|
$0.280
|
$1.120
|
$1.250
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
|
LF
|
3,670.000
|
$0.290
|
$0.670
|
$0.750
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
103.000
|
$3.920
|
$6.100
|
$5.000
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
55,080.000
|
$1.000
|
$0.520
|
$0.250
|
|
|
ELIM EXT PAV MRK & MRKS (24")
|
LF
|
288.000
|
$2.600
|
$5.100
|
$2.000
|
|
|
PAV SURF PREP FOR MRK (4")
|
LF
|
1,422.000
|
$0.070
|
$0.130
|
$0.040
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$13,290.910
|
$17,500.000
|
$40,000.000
|
|
|
TMA (STATIONARY)
|
DAY
|
37.000
|
$192.190
|
$375.000
|
$178.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
15.000
|
$207.000
|
$365.000
|
$134.000
|
|
Totals: |
$5,140,281.350
|
$5,883,531.460
|
$7,049,353.480
|