Show Job Controls
Bid Cobra

LIBERTY FM 770 (1096-02-051)

Items: 74

County: LIBERTY
Length: N/A
Highway: FM 770
District: BEAUMONT
Control Number: 1096-02-051
DBE Goal: N/A
Project: BR 2022(174)
Guaranty: N/A
Time: 225 WORKING DAYS
Engineer's Estimate: $5,140,281.35
Date: 12/01/2021 (4 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (2)
E
Engineer's Estimate
$5,140,281.35
$5,883,531.46
Over/Under Est: 14.46% $743,250.11
Over/Under Est: 37.14% $1,909,072.13
Amt Left: 19.82% $1,165,822.02
Subcontractor Percentage Amount
HB FARMER FOUNDATION, LLC 13.66% $961,024.49
AMERICAN REMEDIATION OPTIONS, INC. 4.76% $334,881.15
BARRICADES UNLIMITED 2.56% $180,104.15
TRP CONSTRUCTION GROUP, LLC 1.50% $105,529.78
DUSTROL, INC. 1.35% $94,976.80
J & M CONSTRUCTION COMPANY 1.12% $78,795.57
J & M CONTRACTING, COMPANY 1.12% $78,795.57
HOUSTON SAWING & DRILLING 0.20% $14,070.64
Total: 26.27% $1,848,178.15

Bid Items & Bid Tabulations

74 Total 0 of 74
LIBERTY  |  FM 770  |  BEAUMONT  |  1096-02-051  |  12/01/2021  |  $5,140,281.35  |  BR 2022(174)  |  BRIDGE REPL  |  225 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS MATERIALS GROUP, INC.
RAGLE CONSTRUCTION, INC.
PREPARING ROW
STA 28.000 $2,250.000 $800.000 $22,000.000
REMOVING CONC (PAV)
SY 6,973.000 $5.530 $9.000 $11.000
REMOVING CONCRETE(MOW STRIP)
LF 2,176.000 $8.000 $5.500 $4.000
REMOVING STAB BASE AND ASPH PAV (0-4")
SY 7,864.000 $12.000 $4.000 $4.000
EXCAVATION (ROADWAY)
CY 811.000 $20.000 $24.000 $80.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 7,579.000 $7.000 $25.000 $30.000
FURNISHING AND PLACING TOPSOIL (4")
SY 3,671.000 $1.170 $7.500 $2.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 3,671.000 $0.280 $0.280 $1.880
VEGETATIVE WATERING
MG 62.800 $17.850 $33.000 $22.000
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 1,871.000 $0.930 $1.280 $3.000
PROOF ROLLING
HR 40.000 $100.000 $92.000 $87.000
LIME (HYD, COM, OR QK(SLURRY))
TON 138.000 $178.220 $220.000 $202.000
LIME TRT (SUBGRADE)(6")
SY 9,231.000 $3.820 $4.500 $7.000
D-GR HMA(SQ) TY-B PG64-22
TON 4,062.000 $83.420 $102.000 $100.000
D-GR HMA(SQ) TY-D SAC-A PG70-22
TON 1,016.000 $110.000 $130.000 $120.000
D-GR HMA (SQ) TY-D PG64_22(LEVEL-UP)
TON 301.000 $119.810 $144.000 $110.000
TACK COAT
GAL 2,770.000 $5.800 $4.600 $2.500
PLAN & TEXT ASPH CONC PAV(0" TO 2")
SY 1,814.000 $1.450 $15.100 $8.000
CEM STABIL BKFL
CY 260.000 $97.000 $160.000 $169.000
DRILL SHAFT (24 IN)
LF 3,378.000 $200.000 $240.000 $240.000
CL C CONC (ABUT)
CY 84.200 $950.000 $2,450.000 $1,500.000
CL C CONC (CAP)
CY 44.000 $1,000.000 $3,275.000 $2,100.000
CL C CONC (COLUMN)
CY 20.000 $1,000.000 $1,975.000 $2,500.000
REINF CONC SLAB (SLAB BEAM)
SF 11,848.000 $22.000 $28.450 $28.000
APPROACH SLAB
CY 216.000 $590.000 $650.000 $475.000
PRESTR CONC SLAB BEAM (4SB12)
LF 323.940 $150.000 $203.000 $300.000
PRESTR CONC SLAB BEAM (5SB12)
LF 647.880 $150.000 $170.000 $250.000
PRESTR CONC SLAB BEAM (4SB15)
LF 492.000 $165.000 $179.000 $250.000
PRESTR CONC SLAB BEAM (5SB15)
LF 984.000 $180.000 $169.000 $182.000
RIPRAP (CONC)(5 IN)
CY 366.000 $546.910 $533.000 $537.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 459.000 $110.000 $156.000 $184.000
RIPRAP (MOW STRIP)(4 IN)
CY 224.000 $450.000 $594.000 $500.000
STR STEEL (MISC NON - BRIDGE)
LB 658.000 $5.500 $11.500 $16.000
RAIL (TY T223)
LF 623.000 $100.000 $188.000 $111.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 2.000 $37,000.000 $20,800.000 $100,000.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $50,000.000 $120,640.000 $138,000.000
MOBILIZATION
LS 1.000 $430,300.000 $581,900.000 $700,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 15.000 $5,557.950 $4,000.000 $40,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 520.000 $20.690 $32.800 $33.800
ROCK FILTER DAMS (REMOVE)
LF 520.000 $7.430 $9.100 $8.810
TEMP SEDMT CONT FENCE (INSTALL)
LF 4,920.000 $2.830 $2.900 $2.900
TEMP SEDMT CONT FENCE (REMOVE)
LF 4,920.000 $0.920 $0.760 $0.640
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 1,000.000 $5.730 $5.100 $5.800
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,000.000 $0.850 $1.040 $1.350
CONSTRUCTING DETOURS
SY 7,774.000 $108.940 $46.000 $51.000
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 16.000 $3,000.000 $4,250.000 $2,000.000
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
LF 4,170.000 $31.020 $72.000 $20.000
PORT CTB (MOVE)(F-SHAPE)(TY 1)
LF 10,770.000 $4.000 $4.100 $12.000
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
LF 4,170.000 $6.000 $15.000 $8.000
MTL W-BEAM GD FEN (TIM POST)
LF 3,450.000 $27.330 $26.500 $25.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 12.000 $2,451.290 $1,875.000 $1,800.000
REMOVE METAL BEAM GUARD FENCE
LF 1,350.000 $3.500 $2.600 $2.000
GUARDRAIL END TREATMENT (INSTALL)
EA 12.000 $3,237.670 $2,900.000 $2,950.000
GUARDRAIL END TREATMENT (REMOVE)
EA 12.000 $195.000 $310.000 $200.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 24.000 $1,296.810 $1,210.000 $480.000
CRASH CUSH ATTEN (REMOVE)
EA 10.000 $806.770 $855.000 $480.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 10.000 $8,000.000 $9,100.000 $7,100.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 5.000 $493.510 $520.000 $600.000
REMOVE SM RD SN SUP&AM
EA 7.000 $104.960 $76.000 $20.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 82.000 $115.250 $27.800 $23.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 20,480.000 $1.050 $1.250 $0.540
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 288.000 $7.710 $6.100 $3.000
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 34,560.000 $1.000 $1.200 $0.300
PAVEMENT SEALER 4"
LF 1,422.000 $0.270 $0.210 $0.060
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 5,270.000 $0.350 $0.660 $0.750
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
LF 200.000 $0.280 $1.120 $1.250
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 3,670.000 $0.290 $0.670 $0.750
REFL PAV MRKR TY II-A-A
EA 103.000 $3.920 $6.100 $5.000
ELIM EXT PAV MRK & MRKS (4")
LF 55,080.000 $1.000 $0.520 $0.250
ELIM EXT PAV MRK & MRKS (24")
LF 288.000 $2.600 $5.100 $2.000
PAV SURF PREP FOR MRK (4")
LF 1,422.000 $0.070 $0.130 $0.040
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $13,290.910 $17,500.000 $40,000.000
TMA (STATIONARY)
DAY 37.000 $192.190 $375.000 $178.000
TMA (MOBILE OPERATION)
DAY 15.000 $207.000 $365.000 $134.000
Totals: $5,140,281.350 $5,883,531.460 $7,049,353.480