Job Info for 0952-01-060

County: LIBERTY Highway: FM 1008 Date: 02/05/2019 (5 years ago) Engineer's Estimate: $2,879,633 Control Number: 0952-01-060
Project: C 952-1-60 District: BEAUMONT Time: 204 WORKING DAYS Type: WIDEN/TWO-COURSE SURFACE TREATMENT

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $2,879,632.93
ANGEL BROTHERS HOLDINGS CORP.   $2,730,449.36 1
-5.18% | -$149,183.57
TRIPLE B SERVICES LLP   $2,779,395.36 2
-3.48% | -$100,237.57
1.79% | $48,946.00
TEXAS MATERIALS GROUP, INC.   $3,204,364.81 3
11.28% | $324,731.88
17.36% | $473,915.45
15.29% | $424,969.45
SMITH & COMPANY   $3,476,959.83 4
20.74% | $597,326.90
27.34% | $746,510.47
8.51% | $272,595.02

Bid Items

Items: 51, 0 filtered
LIBERTY FM 1008  |  BEAUMONT  |  0952-01-060  |  02/05/2019  |  $2,879,633  |  C 952-1-60  |  WIDEN/TWO-COURSE SURF TREATMENT  |  204 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate ANGEL BROTHERS HOLDINGS CORP. TRIPLE B SERVICES LLP TEXAS MATERIALS GROUP, INC. SMITH & COMPANY
100 6002 PREPARING ROW STA 264.580 $2,500.000 $475.000 $300.000 $150.000 $750.000
112 6001 SUBGRADE WIDENING (ORD COMP) STA 264.580 $322.930 $317.000 $200.000 $400.000 $425.000
134 6002 BACKFILL (TY B) STA 264.580 $234.450 $190.000 $275.000 $190.000 $150.000
164 6024 CELL FBR MLCH SEED(PERM)(RURAL)(CLAY) AC 18.700 $1,260.000 $1,870.000 $1,750.000 $1,400.000 $1,600.000
168 6001 VEGETATIVE WATERING MG 0.130 $18.970 $34.000 $500.000 $8,200.000 $1,500.000
216 6001 PROOF ROLLING HR 826.000 $75.560 $115.000 $28.000 $85.000 $19.000
247 6055 FL BS (CMP IN PLC)(TY D GR 3)(FNAL POS) CY 4,587.000 $70.000 $82.750 $88.000 $105.000 $72.000
247 6133 FL BS (RDWY DEL) (TY D GR 1-2) TON 319.100 $40.000 $81.000 $62.000 $55.000 $50.000
275 6001 CEMENT TON 1,003.000 $156.850 $154.750 $137.000 $215.000 $195.000
275 6012 CEMENT TRT (MX EXST MTL & NW BS)(10") SY 82,565.000 $2.280 $2.900 $2.700 $2.350 $7.000
316 6017 ASPH (AC-20-5TR) GAL 29,724.000 $2.600 $3.500 $3.650 $4.500 $3.100
316 6029 ASPH (RC-250) GAL 39,631.000 $3.720 $3.700 $6.700 $5.000 $3.200
316 6453 AGGR(TY D GR 3 OR TY L GR 3) CY 870.000 $67.580 $145.000 $136.000 $210.000 $105.000
316 6461 AGGR (TY-PD GR-4P)(SAC-A) CY 661.000 $80.000 $165.000 $157.000 $295.000 $95.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 26.000 $360.180 $650.000 $530.000 $720.000 $550.000
467 6237 SET (TY I)(S= 7 FT)(HW= 2 FT)(4:1) (C) EA 2.000 $8,000.000 $7,100.000 $5.000 $5,500.000 $6,000.000
467 6341 SET (TY II) (15 IN) (RCP) (6: 1) (P) EA 2.000 $1,420.000 $825.000 $1,000.000 $1,300.000 $700.000
467 6358 SET (TY II) (18 IN) (RCP) (4: 1) (C) EA 4.000 $1,200.000 $825.000 $1,100.000 $1,200.000 $700.000
467 6363 SET (TY II) (18 IN) (RCP) (6: 1) (P) EA 58.000 $736.610 $890.000 $1,100.000 $1,000.000 $750.000
467 6380 SET (TY II) (24 IN) (CMP) (6: 1) (P) EA 6.000 $1,160.010 $1,070.000 $1,550.000 $1,300.000 $900.000
467 6395 SET (TY II) (24 IN) (RCP) (6: 1) (P) EA 66.000 $1,052.330 $1,070.000 $1,600.000 $1,300.000 $900.000
467 6419 SET (TY II) (30 IN) (RCP) (4: 1) (C) EA 4.000 $1,750.000 $2,400.000 $1,700.000 $1,700.000 $2,000.000
467 6423 SET (TY II) (30 IN) (RCP) (6: 1) (P) EA 2.000 $1,632.570 $2,900.000 $2,200.000 $2,100.000 $2,500.000
500 6001 MOBILIZATION LS 1.000 $147,603.960 $175,000.000 $220,000.000 $314,000.000 $325,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 8.000 $6,575.000 $675.000 $1,000.000 $8,000.000 $15,000.000
506 6004 ROCK FILTER DAMS (INSTALL) (TY 4) LF 660.000 $28.150 $61.000 $45.000 $39.000 $55.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 660.000 $7.270 $17.250 $15.000 $8.500 $15.000
506 6042 BIODEG EROSN CONT LOGS (INSTL) (18") LF 1,500.000 $7.230 $7.500 $6.000 $5.600 $6.500
530 6004 DRIVEWAYS (CONC) SY 121.000 $118.600 $142.000 $175.000 $97.000 $125.000
530 6005 DRIVEWAYS (ACP) SY 1,125.000 $23.000 $25.000 $51.000 $54.000 $77.000
530 6009 TURNOUTS (SURF TREAT) SY 9,266.000 $13.560 $17.000 $20.000 $25.000 $45.000
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 600.000 $18.970 $28.000 $27.000 $25.000 $29.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 500.000 $3.100 $2.750 $2.800 $2.600 $2.000
542 6002 REMOVE TERMINAL ANCHOR SECTION EA 4.000 $215.940 $350.000 $340.000 $290.000 $175.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 2.000 $2,030.440 $3,200.000 $3,000.000 $2,400.000 $2,635.000
545 6001 CRASH CUSH ATTEN (INSTL) EA 2.000 $21,000.000 $18,500.000 $18,000.000 $17,000.000 $17,500.000
560 6004 MAILBOX INSTALL-S (TWG-POST) TY 2 EA 40.000 $222.110 $350.000 $340.000 $250.000 $170.000
560 6005 MAILBOX INSTALL-D (TWG-POST) TY 2 EA 1.000 $275.000 $410.000 $395.000 $250.000 $210.000
644 6068 RELOCATE SM RD SN SUP&AM TY 10BWG EA 53.000 $324.500 $530.000 $435.000 $375.000 $470.000
658 6008 INSTL DEL ASSM (D-SW)SZ 1(FLX)GF2(BI) EA 8.000 $13.850 $17.750 $34.000 $28.000 $34.000
658 6048 INSTL OM ASSM (OM-2Z)(FLX)GND EA 32.000 $47.760 $88.000 $56.000 $55.000 $50.000
662 6016 WK ZN PAV MRK NON-REMOV (W)24"(SLD) LF 50.000 $2.360 $2.250 $6.800 $6.200 $2.000
662 6032 WK ZN PAV MRK NON-REMOV (Y)4"(BRK) LF 1,906.000 $0.180 $0.200 $0.220 $0.210 $0.160
662 6034 WK ZN PAV MRK NON-REMOV (Y)4"(SLD) LF 41,133.000 $0.200 $0.200 $0.220 $0.210 $0.160
662 6111 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 EA 5,257.000 $1.290 $0.450 $1.700 $1.800 $1.500
666 6302 RE PM W/RET REQ TY I (W)4"(SLD)(090MIL) LF 51,279.000 $0.300 $0.400 $0.280 $0.260 $0.350
666 6311 RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL) LF 24,218.000 $0.330 $0.400 $0.170 $0.160 $0.350
666 6314 RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL) LF 18,821.000 $0.310 $0.400 $0.750 $0.700 $0.350
668 6076 PREFAB PAV MRK TY C (W) (24") (SLD) LF 49.000 $11.480 $12.000 $17.000 $15.500 $10.250
672 6009 REFL PAV MRKR TY II-A-A EA 79,889.980 $3.400 $3.250 $2.450 $2.500 $2.750
6185 6001 TMA (STATIONARY) EA 1.000 $1,500.000 $11,000.000 $40,000.000 $33,000.000 $55,000.000
Totals: $2,879,632.93 $2,730,449.37 $2,779,395.36 $3,204,364.81 $3,476,959.83