LIBERTY FM 1009 (0601-04-013)
Items: 52
County: LIBERTY
Length: N/A
Highway: FM 1009
District: BEAUMONT
Control Number: 0601-04-013
DBE Goal: 0.0%
Project: C 601-4-13
Guaranty: N/A
Time: 90 WORKING DAYS
Engineer's Estimate: $3,734,209.20
Date: 08/01/2024 (1 year ago)
Contract Number: N/A
Type: SURFACING/ROADWAY RESTORATION
Mail/Deliver Bids To: N/A
ROBERTO M RODRIGUEZ
NYEMB NYEMB
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$3,734,209.20 | |||
| $3,702,741.54 |
-0.84%
-$31,467.66
|
|||
| $3,736,503.25 |
0.06%
$2,294.05
|
0.91%
$33,761.71
|
||
| $4,089,091.56 |
9.5%
$354,882.36
|
10.43%
$386,350.02
|
-9.44%
-$352,588.31
|
|
| $5,299,999.97 |
41.93%
$1,565,790.77
|
43.14%
$1,597,258.43
|
-29.61%
-$1,210,908.41
|
|
| $5,578,508.50 |
49.39%
$1,844,299.30
|
50.66%
$1,875,766.96
|
-5.25%
-$278,508.53
|
E
Engineer's Estimate
$3,734,209.20
$3,702,741.54
Over/Under Est:
-0.84%
-$31,467.66
$3,736,503.25
Over/Under Est:
0.06%
$2,294.05
Amt Left:
0.91%
$33,761.71
$4,089,091.56
Over/Under Est:
9.5%
$354,882.36
Amt Left:
10.43%
$386,350.02
Delta:
-9.44%
-$352,588.31
$5,299,999.97
Over/Under Est:
41.93%
$1,565,790.77
Amt Left:
43.14%
$1,597,258.43
Delta:
-29.61%
-$1,210,908.41
$5,578,508.50
Over/Under Est:
49.39%
$1,844,299.30
Amt Left:
50.66%
$1,875,766.96
Delta:
-5.25%
-$278,508.53
| Subcontractor | Percentage | Amount |
|---|---|---|
| J & M CONTRACTING, COMPANY | 15.69% | $582,432.65 |
| TRP CONSTRUCTION GROUP, LLC | 1.51% | $56,053.11 |
| MURRAY CONSTRUCTION | 0.90% | $33,409.14 |
| SOUTHWEST ENVIRONMENT SERVICES LLC | 0.50% | $18,560.63 |
| PROFESSIONAL TRAFFIC CONTROL LLC | 0.20% | $7,424.25 |
| SUPERIOR TRAFFIC CONTROL, LLC | 0.18% | $6,681.83 |
| Total: | 18.98% | $704,561.61 |
Bid Items & Bid Tabulations
52
Total
0 of 52