LIBERTY US 90 (0028-03-109)

Items: 55

County: LIBERTY
Length: N/A
Highway: US 90
District: BEAUMONT
Control Number: 0028-03-109
DBE Goal: N/A
Project: STP 2022(468)HES
Guaranty: N/A
Time: 116 WORKING DAYS
Engineer's Estimate: $1,982,559.57
Date: 08/03/2022 (3 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
ROBERTO M RODRIGUEZ
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$1,982,559.57
Over/Under Est: -18.51% -$367,068.19
Over/Under Est: -0.29% -$5,771.91
Amt Left: 22.36% $361,296.28
Over/Under Est: 13.32% $264,128.52
Amt Left: 39.07% $631,196.71
Delta: -13.65% -$269,900.43
Over/Under Est: 22.26% $441,261.91
Amt Left: 50.04% $808,330.10
Delta: -7.88% -$177,133.39

Bid Items & Bid Tabulations

55 Total 0 of 55
LIBERTY  |  US 90  |  BEAUMONT  |  0028-03-109  |  08/03/2022  |  $1,982,559.57  |  STP 2022(468)HES  |  HAZARD ELIM & SAFETY  |  116 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC
TEXAS MATERIALS GROUP, INC.
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SELECT MAINTENANCE, L.L.C.
REMOVING CONC (CURB)
LF 1,900.000 $10.000 $12.200 $5.500 $45.000 $3.000
REMOVE STAB BASE & ASPH PAV (4"-5")
SY 270.000 $4.500 $18.640 $33.000 $20.000 $30.000
FURNISHING AND PLACING TOPSOIL (4")
SY 270.000 $4.000 $18.860 $45.000 $30.000 $10.000
BLOCK SODDING
SY 270.000 $6.000 $20.860 $7.000 $20.000 $15.000
PLANE ASPH CONC PAV(0" TO 2")
SY 36,890.000 $2.850 $0.850 $1.850 $2.000 $3.000
FULL - DEPTH REPAIR CPCD (9")
SY 1,845.000 $350.000 $213.580 $498.000 $375.000 $400.000
CLEANING AND SEALING EXISTING JOINTS
LF 4,370.000 $6.000 $7.320 $7.000 $7.250 $6.000
ADJUSTING INLETS
EA 5.000 $9,000.000 $1,220.430 $4,450.000 $3,500.000 $850.000
MOBILIZATION
LS 1.000 $260,577.600 $82,058.730 $105,000.000 $160,000.000 $240,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $8,000.000 $6,623.080 $950.000 $3,000.000 $42,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 50.000 $50.000 $61.020 $83.000 $30.000 $30.000
ROCK FILTER DAMS (REMOVE)
LF 50.000 $17.000 $19.520 $17.000 $10.000 $10.000
SANDBAGS FOR EROSION CONTROL
EA 44.000 $17.000 $20.740 $66.000 $100.000 $20.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 110.000 $10.000 $6.100 $4.250 $8.000 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 110.000 $3.000 $2.070 $1.750 $5.000 $1.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 200.000 $10.000 $12.200 $4.250 $10.000 $15.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 200.000 $3.000 $2.070 $1.700 $3.000 $5.000
CONC CURB (MONO) (TY II)
LF 1,900.000 $6.000 $18.300 $44.000 $75.000 $20.000
INTERSECTIONS (ACP)
SY 890.000 $42.000 $36.950 $40.000 $31.600 $43.000
DRIVEWAYS (ACP)
SY 834.000 $85.000 $38.720 $42.000 $36.900 $43.000
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 2,228.000 $0.550 $0.490 $0.350 $0.320 $0.500
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 1,382.000 $1.100 $1.220 $0.500 $0.440 $0.750
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 755.000 $7.000 $5.490 $3.350 $3.000 $4.000
WK ZN PAV MRK NON-REMOV (W)(ARROW)
EA 12.000 $80.000 $122.040 $122.000 $110.000 $100.000
WK ZN PAV MRK NON-REMOV(W)(WORD)
EA 9.000 $96.000 $122.040 $122.000 $110.000 $120.000
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 1,360.000 $0.600 $0.490 $0.350 $0.320 $0.500
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 20,468.000 $0.500 $0.490 $0.350 $0.320 $0.500
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 876.000 $1.500 $1.830 $0.550 $1.000 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 3,478.000 $1.500 $1.950 $0.550 $1.000 $1.750
REFL PAV MRK TY I (W)4"(DOT)(090MIL)
LF 93.000 $1.100 $2.440 $0.850 $0.750 $2.000
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 1,382.000 $1.200 $2.440 $1.150 $1.050 $1.250
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 1,768.000 $0.650 $0.610 $0.650 $0.600 $0.500
RE PM W/RET REQ TY I (W)6"(BRK)(090MIL)
LF 2,181.000 $1.200 $0.850 $0.750 $0.700 $1.250
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
LF 1,051.000 $0.800 $0.610 $0.650 $0.600 $0.500
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 10,373.000 $1.000 $0.610 $0.650 $0.600 $0.500
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 749.000 $24.000 $19.530 $15.500 $14.000 $17.500
PREFAB PAV MRK TY C (W) (ARROW)
EA 21.000 $250.000 $305.110 $250.000 $220.000 $250.000
PREFAB PAV MRK TY C (W) (WORD)
EA 9.000 $325.000 $390.540 $250.000 $220.000 $300.000
PREFAB PAV MRK TY C (Y) (24") (SLD)
LF 779.000 $12.000 $19.520 $15.500 $14.000 $15.000
REFL PAV MRKR TY I-C
EA 289.000 $6.000 $7.320 $6.650 $6.000 $4.250
REFL PAV MRKR TY II-A-A
EA 262.000 $8.000 $7.320 $6.650 $6.000 $4.000
PAV SURF PREP FOR MRK (4")
LF 12,234.000 $0.080 $0.120 $0.020 $0.020 $0.070
PAV SURF PREP FOR MRK (6")
LF 2,181.000 $0.050 $0.240 $0.040 $0.040 $0.050
PAV SURF PREP FOR MRK (8")
LF 1,382.000 $0.200 $0.370 $0.070 $0.060 $0.150
PAV SURF PREP FOR MRK (24")
LF 749.000 $1.200 $1.220 $0.100 $0.100 $1.250
PAV SURF PREP FOR MRK (ARROW)
EA 21.000 $20.000 $12.200 $17.000 $15.000 $20.000
PAV SURF PREP FOR MRK (WORD)
EA 9.000 $21.000 $12.200 $17.000 $15.000 $23.000
SPALLING REPAIR (POLYMERIC) (FLEXIBLE)
GAL 1,000.000 $50.000 $124.480 $61.000 $290.000 $75.000
DRAIN INLET CLEANING
EA 9.000 $2,000.000 $3,051.080 $400.000 $2,500.000 $2,200.000
STORM SEWER CLEANING (ALL SIZES)
LF 2,200.000 $30.000 $48.820 $8.500 $20.000 $25.000
SP MIXES SP-D SAC-A PG76-22
TON 3,044.000 $120.000 $130.240 $148.000 $142.000 $160.000
TACK COAT
GAL 2,213.000 $5.000 $5.410 $4.000 $4.500 $4.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 3.000 $12,000.000 $1,220.430 $850.000 $15,000.000 $25,000.000
TMA (STATIONARY)
DAY 78.000 $300.000 $314.480 $165.000 $200.000 $175.000
TMA (MOBILE OPERATION)
HR 264.000 $110.000 $317.320 $17.000 $45.000 $75.000
Totals: $1,982,559.570 $1,615,491.380 $1,976,787.660 $2,246,688.090 $2,423,821.480