Bid Cobra

LEON SH0007 (6390-98-001)

Items: 11

County: LEON
Length: N/A
Highway: SH0007
District: BRYAN
Control Number: 6390-98-001
DBE Goal: N/A
Project: BPM - 639098001
Guaranty: N/A
Time: 38 W
Engineer's Estimate: $152,780.00
Date: 12/07/2021 (4 years ago)
Contract Number: N/A
Type: BRIDGE REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (8)
E
Engineer's Estimate
$152,780.00
$167,760.00
Over/Under Est: 9.8% $14,980.00
Over/Under Est: 15.75% $24,060.00
Amt Left: 5.41% $9,080.00
Over/Under Est: 17.08% $26,100.00
Amt Left: 6.63% $11,120.00
Delta: -1.15% -$2,040.00
Over/Under Est: 62.1% $94,884.00
Amt Left: 47.63% $79,904.00
Delta: -38.45% -$68,784.00
Over/Under Est: 64.21% $98,095.50
Amt Left: 49.54% $83,115.50
Delta: -1.30% -$3,211.50
Over/Under Est: 70.26% $107,346.00
Amt Left: 55.06% $92,366.00
Delta: -3.69% -$9,250.50
Over/Under Est: 76.34% $116,630.00
Amt Left: 60.59% $101,650.00
Delta: -3.57% -$9,284.00
Over/Under Est: 137.11% $209,470.00
Amt Left: 115.93% $194,490.00
Delta: -34.46% -$92,840.00

Bid Items & Bid Tabulations

11 Total 0 of 11
LEON  |  SH0007  |  BRYAN  |  6390-98-001  |  12/07/2021  |  $152,780.00  |  BPM - 639098001  |  BRIDGE REPAIR  |  38 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
B & MS CONSTRUCTION, INC.
TALBRAN ENTERPRISES LLC
STRUCTURAL INTEGRITY GROUP LLC
FUQUA CONSTRUCTION CO., INC.
BOEN LANDSCAPING & IRRIGATION, LLC
DIGG COMMERCIAL, LLC
FORDE CONSTRUCTION COMPANY, INC.
A. L. HELMCAMP, INC.
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 1,000.000 $2.500 $2.300 $1.000 $1.000 $1.000 $1.000 $0.900 $2.000 $1.000
BROADCAST SEED (TEMP) (WARM)
SY 500.000 $0.750 $2.760 $1.000 $1.000 $1.000 $1.000 $1.800 $1.000 $1.000
BROADCAST SEED (TEMP) (COOL)
SY 500.000 $0.650 $2.760 $1.000 $1.000 $1.000 $1.000 $1.800 $1.000 $1.000
TEMPORARY SPL SHORING (COFFERDAM)
SF 402.000 $40.000 $23.000 $70.000 $10.000 $1.000 $12.750 $13.000 $5.000 $25.000
CL C CONC(PILE ENCASEMENT)
LF 306.000 $275.000 $285.000 $350.000 $465.000 $700.000 $600.000 $600.000 $600.000 $800.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 62.000 $175.000 $250.000 $200.000 $325.000 $300.000 $375.000 $300.000 $375.000 $200.000
MOBILIZATION
LS 1.000 $25,000.000 $34,500.000 $15,000.000 $5,500.000 $4,043.200 $20,000.000 $20,000.000 $26,000.000 $30,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $2,500.000 $3,450.000 $2,000.000 $1,500.000 $1,000.000 $2,000.000 $3,000.000 $8,700.000 $18,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 200.000 $4.000 $3.740 $4.000 $1.000 $3.000 $3.000 $4.000 $1.000 $10.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 200.000 $1.000 $1.730 $2.000 $1.000 $1.000 $1.500 $1.000 $0.250 $5.000
TMA (STATIONARY)
DAY 20.000 $250.000 $240.000 $250.000 $1.000 $230.940 $500.000 $1,000.000 $260.000 $300.000
Totals: $152,780.000 $167,760.000 $176,840.000 $178,880.000 $247,664.000 $250,875.500 $260,126.000 $269,410.000 $362,250.000