LAVACA CR (0913-29-052)

Items: 39

County: LAVACA
Length: N/A
Highway: CR
District: YOAKUM
Control Number: 0913-29-052
DBE Goal: N/A
Project: BR 2020(726)
Guaranty: N/A
Time: 117 WORKING DAYS
Engineer's Estimate: $927,694.50
Date: 12/02/2021 (4 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (4)
E
Engineer's Estimate
$927,694.50
$965,493.88
Over/Under Est: 4.07% $37,799.38
Over/Under Est: 18.35% $170,254.53
Amt Left: 13.72% $132,455.15
Over/Under Est: 24.44% $226,764.00
Amt Left: 19.57% $188,964.62
Delta: -5.15% -$56,509.47
$1,156,874.65
Over/Under Est: 24.7% $229,180.15
Amt Left: 19.82% $191,380.77
Delta: -0.21% -$2,416.15
Subcontractor Percentage Amount
KELLER NORTH AMERICA, INC. 7.94% $76,660.22
BATTEN DRILLING, INC. 7.43% $71,736.20
DEPENDABLE FENCE 6.23% $60,150.27
A K FUQUAY CONSTRUCTION 1.68% $16,220.30
FLASHER EQUIPMENT COMPANY 0.91% $8,785.99
A-CORE CONCRETE CUTTING, INC. 0.66% $6,372.26
Total: 24.85% $239,925.24

Bid Items & Bid Tabulations

39 Total 0 of 39
LAVACA  |  CR  |  YOAKUM  |  0913-29-052  |  12/02/2021  |  $927,694.50  |  BR 2020(726)  |  BRIDGE REPL  |  117 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SB CONTRACTORS LLC
ACME BRIDGE COMPANY, INC.
HILL COUNTRY BRIDGE, INC.
TREVWAY, INC.
PREPARING ROW
STA 9.000 $3,000.000 $1,500.000 $4,100.000 $6,760.000 $1,200.000
EXCAVATION (ROADWAY)
CY 640.000 $10.000 $14.210 $22.300 $13.300 $21.000
EXCAVATION (CHANNEL)
CY 390.000 $15.000 $26.680 $30.000 $15.500 $30.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 347.000 $20.000 $15.260 $26.600 $22.150 $32.000
BLADING
HR 40.000 $100.000 $83.840 $112.000 $33.200 $50.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 2,319.000 $2.000 $0.930 $0.530 $0.550 $2.000
BROADCAST SEED (TEMP) (WARM)
SY 580.000 $2.000 $3.240 $1.750 $1.800 $2.000
BROADCAST SEED (TEMP) (COOL)
SY 580.000 $2.000 $3.240 $1.750 $1.800 $2.000
VEGETATIVE WATERING
MG 26.100 $50.000 $45.000 $81.500 $155.000 $150.000
FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS)
CY 409.000 $100.000 $86.810 $107.000 $108.500 $131.000
CEM STABIL BKFL
CY 118.000 $100.000 $116.350 $208.000 $217.000 $162.000
DRILL SHAFT (30 IN)
LF 162.000 $220.000 $188.970 $198.000 $225.000 $444.000
DRILL SHAFT (36 IN)
LF 291.000 $260.000 $228.710 $242.000 $263.000 $578.530
CL C CONC (ABUT)
CY 68.400 $1,100.000 $821.720 $1,040.000 $940.000 $603.000
CL C CONC (CAP)
CY 13.500 $1,100.000 $1,362.950 $1,320.000 $925.000 $1,045.000
CL C CONC (COLUMN)
CY 11.000 $1,100.000 $1,232.700 $1,070.000 $1,195.000 $1,420.000
REINF CONC SLAB
SF 2,990.000 $20.000 $25.190 $28.900 $27.750 $23.000
REINF CONC SLAB (BOX BEAM)
SF 1,810.000 $20.000 $20.080 $20.800 $21.350 $23.000
SHEAR KEY
CY 8.000 $400.000 $729.720 $818.000 $865.000 $1,515.260
PRESTR CONC BOX BEAM (5B20)
LF 357.000 $175.000 $189.340 $266.000 $237.000 $234.000
PRESTR CONC GIRDER (TX28)
LF 455.700 $140.000 $165.780 $268.000 $205.000 $178.000
RIPRAP (STONE PROTECTION)(15 IN)
CY 626.000 $180.000 $237.400 $184.000 $180.000 $209.000
RAIL (TY T223)
LF 270.000 $100.000 $92.600 $110.000 $125.000 $157.120
RAIL (TY T631)
LF 152.000 $100.000 $120.210 $117.000 $100.000 $97.190
ARMOR JOINT (SEALED)
LF 104.000 $85.000 $87.490 $142.000 $88.000 $68.150
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 2.000 $25,000.000 $15,005.690 $11,000.000 $38,125.000 $30,000.000
REMOV STR (SMALL FENCE)
LF 382.000 $3.000 $6.590 $1.850 $11.000 $6.000
MOBILIZATION
LS 1.000 $81,000.000 $96,000.000 $105,000.000 $115,400.000 $100,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $4,000.000 $2,500.000 $1,950.000 $3,980.000 $1,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,581.000 $3.000 $5.200 $4.800 $5.000 $3.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,581.000 $1.000 $0.910 $0.960 $1.000 $0.500
MTL W-BEAM GD FEN (TIM POST)
LF 137.500 $25.000 $42.650 $50.500 $42.000 $49.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $280.000 $2,797.850 $2,810.000 $3,525.000 $2,207.000
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $2,800.000 $3,790.460 $3,480.000 $3,875.000 $3,244.660
WIRE FENCE (TY A)
LF 863.000 $15.000 $13.090 $16.000 $20.000 $7.000
WIRE FENCE (WATER GAP)
LF 48.000 $65.000 $65.440 $133.000 $127.000 $148.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 4.000 $11.000 $27.260 $26.600 $55.000 $6.320
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)
EA 2.000 $11.000 $27.270 $37.200 $55.000 $8.840
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 12.000 $25.000 $32.720 $42.600 $55.000 $15.160
Totals: $927,694.500 $965,493.904 $1,097,949.030 $1,154,458.500 $1,156,874.650