Job Info for 0913-29-037

County: LAVACA Highway: CR Date: 06/06/2018 (6 years ago) Engineer's Estimate: $1,438,658 Control Number: 0913-29-037
Project: BR 2007(662) District: YOAKUM Time: 235 WORKING DAYS Type: REPLACE BRIDGE AND APPROACHES

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $1,438,657.50
HILL COUNTRY BRIDGE, INC.   $1,395,463.51 1
-3% | -$43,193.99
CAPITAL EXCAVATION COMPANY   $1,494,021.41 2
3.85% | $55,363.91
7.06% | $98,557.90
SB CONTRACTORS LLC   $1,509,026.26 3
4.89% | $70,368.76
8.14% | $113,562.75
1.00% | $15,004.85
CONSTAR CONSTRUCTION   $1,515,134.00 4
5.32% | $76,476.50
8.58% | $119,670.49
0.40% | $6,107.74
A GREATER AUSTIN DEVELOPMENT COMPANY, LTD.   $1,660,805.00 5
15.44% | $222,147.50
19.01% | $265,341.49
9.61% | $145,671.00

Bid Items

Items: 45, 0 filtered
LAVACA CR  |  YOAKUM  |  0913-29-037  |  06/06/2018  |  $1,438,658  |  BR 2007(662)  |  REPLACE BRIDGE AND APPROACHES  |  235 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate HILL COUNTRY BRIDGE, INC. CAPITAL EXCAVATION COMPANY SB CONTRACTORS LLC CONSTAR CONSTRUCTION A GREATER AUSTIN DEVELOPMENT COMPANY, LTD.
100 6002 PREPARING ROW STA 3.800 $3,000.000 $6,260.000 $10,000.000 $5,500.000 $1,200.000 $8,000.000
110 6001 EXCAVATION (ROADWAY) CY 421.000 $20.000 $21.250 $28.000 $12.000 $17.000 $48.000
132 6005 EMBANKMENT (FINAL)(ORD COMP)(TY C) CY 1,534.000 $35.000 $28.160 $20.000 $30.000 $22.000 $68.000
150 6002 BLADING HR 60.000 $80.000 $80.880 $100.000 $55.000 $100.000 $125.000
164 6021 CELL FBR MLCH SEED(PERM)(RURAL)(SANDY) SY 1,255.000 $2.000 $1.300 $1.650 $1.250 $3.000 $1.300
164 6023 CELL FBR MLCH SEED(PERM)(RURAL)(CLAY) SY 305.000 $2.000 $4.550 $3.000 $4.500 $3.000 $4.800
164 6029 CELL FBR MLCH SEED(TEMP)(WARM) SY 391.000 $1.000 $4.550 $3.000 $4.500 $3.000 $4.800
164 6031 CELL FBR MLCH SEED(TEMP)(COOL) SY 391.000 $1.000 $4.550 $3.000 $4.500 $3.000 $4.800
168 6001 VEGETATIVE WATERING MG 13.200 $100.000 $240.000 $50.000 $50.000 $110.000 $80.000
247 6366 FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS) CY 728.000 $120.000 $101.000 $85.000 $100.000 $110.000 $131.000
310 6009 PRIME COAT (MC-30) GAL 612.000 $10.000 $13.000 $20.000 $14.000 $17.000 $14.000
316 6246 AGGR(TY-PE GR-3 SAC-B) CY 37.000 $300.000 $430.000 $660.000 $430.000 $650.000 $475.000
316 6249 AGGR(TY-PE GR-4 SAC-B) CY 24.000 $300.000 $430.000 $660.000 $430.000 $650.000 $475.000
316 6400 ASPH (AC-15P OR AC-10-2TR OR CRS-2P) GAL 2,266.000 $6.000 $18.250 $14.000 $18.500 $19.000 $13.650
400 6005 CEM STABIL BKFL CY 102.000 $150.000 $177.500 $180.000 $175.000 $120.000 $250.000
416 6002 DRILL SHAFT (24 IN) LF 789.000 $180.000 $126.400 $174.000 $155.000 $185.000 $140.000
416 6003 DRILL SHAFT (30 IN) LF 477.000 $185.000 $194.250 $210.000 $200.000 $240.000 $210.000
420 6013 CL C CONC (ABUT) CY 71.800 $850.000 $770.000 $800.000 $950.000 $950.000 $1,000.000
420 6029 CL C CONC (CAP) CY 35.400 $1,200.000 $765.000 $865.000 $1,100.000 $1,300.000 $1,300.000
420 6037 CL C CONC (COLUMN) CY 14.400 $1,200.000 $1,135.000 $915.000 $1,400.000 $1,000.000 $1,500.000
422 6005 REINF CONC SLAB (BOX BEAM) SF 4,042.000 $16.000 $13.750 $13.000 $13.000 $14.000 $15.000
422 6007 REINF CONC SLAB (SLAB BEAM) SF 4,290.000 $18.000 $17.350 $15.000 $18.000 $16.000 $18.000
422 6023 SHEAR KEY CY 20.000 $300.000 $500.000 $700.000 $250.000 $400.000 $550.000
425 6001 PRESTR CONC BOX BEAM (4B20) LF 370.500 $175.000 $154.500 $165.000 $185.000 $195.000 $180.000
425 6002 PRESTR CONC BOX BEAM (5B20) LF 494.000 $160.000 $154.500 $165.000 $185.000 $195.000 $180.000
425 6010 PRESTR CONC SLAB BEAM (5SB12) LF 592.500 $175.000 $159.500 $165.000 $195.000 $155.000 $190.000
425 6012 PRESTR CONC SLAB BEAM (5SB15) LF 222.500 $165.000 $175.250 $165.000 $195.000 $210.000 $190.000
432 6033 RIPRAP (STONE PROTECTION)(18 IN) CY 378.800 $150.000 $158.000 $330.000 $155.000 $150.000 $150.000
450 6006 RAIL (TY T223) LF 660.000 $115.000 $106.000 $90.000 $115.000 $130.000 $180.000
454 6004 ARMOR JOINT (SEALED) LF 147.000 $75.000 $63.000 $85.000 $65.000 $80.000 $140.000
496 6009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) EA 2.000 $15,000.000 $14,000.000 $12,800.000 $19,000.000 $14,000.000 $3,700.000
496 6010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) EA 1.000 $20,000.000 $27,000.000 $25,000.000 $15,000.000 $20,000.000 $8,000.000
500 6001 MOBILIZATION LS 1.000 $130,000.000 $133,900.000 $150,000.000 $149,969.510 $120,000.000 $165,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 16.000 $2,500.000 $2,100.000 $1,000.000 $2,500.000 $900.000 $2,500.000
506 6001 ROCK FILTER DAMS (INSTALL) (TY 1) LF 120.000 $30.000 $27.350 $50.000 $35.000 $50.000 $29.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 120.000 $10.000 $8.090 $40.000 $8.000 $17.000 $8.500
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 1,540.000 $3.000 $2.270 $2.500 $3.000 $5.000 $2.400
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 1,540.000 $1.000 $1.000 $0.750 $1.000 $2.000 $1.100
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 12.000 $1,800.000 $1,985.000 $1,960.000 $2,000.000 $2,300.000 $2,400.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 12.000 $2,200.000 $2,865.000 $2,623.000 $2,623.000 $3,900.000 $2,400.000
552 6001 WIRE FENCE (TY A) LF 156.000 $20.000 $28.350 $20.000 $22.000 $25.000 $13.000
552 6008 WIRE FENCE (WATER GAP) LF 64.000 $25.000 $30.400 $20.000 $30.000 $45.000 $59.000
658 6014 INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) EA 16.000 $20.000 $15.200 $15.000 $15.000 $30.000 $10.500
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 24.000 $20.000 $15.200 $15.000 $15.000 $40.000 $21.500
6185 6002 TMA (STATIONARY) DAY 3.000 $1,000.000 $1,185.000 $363.720 $250.000 $700.000 $400.000
Totals: $1,438,657.50 $1,395,463.52 $1,494,021.41 $1,509,026.26 $1,515,134.00 $1,660,805.00