Bid Cobra

LAVACA US 90A (0446-01-048)

Items: 70

County: LAVACA
Length: N/A
Highway: US 90A
District: YOAKUM
Control Number: 0446-01-048
DBE Goal: N/A
Project: STP 2017(701)HES
Guaranty: N/A
Time: 90 WORKING DAYS
Engineer's Estimate: $805,958.60
Date: 02/02/2017 (9 years ago)
Contract Number: N/A
Type: SAFETY TREAT FIXED OBJECTS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$805,958.60
$793,103.50
Over/Under Est: -1.6% -$12,855.10
Over/Under Est: 1.97% $15,879.00
Amt Left: 3.62% $28,734.10
Over/Under Est: 2.18% $17,588.40
Amt Left: 3.84% $30,443.50
Delta: -0.21% -$1,709.40
$1,146,094.84
Over/Under Est: 42.2% $340,136.24
Amt Left: 44.51% $352,991.34
Delta: -39.17% -$322,547.84
Over/Under Est: 42.83% $345,166.40
Amt Left: 45.14% $358,021.50
Delta: -0.44% -$5,030.16
Over/Under Est: 43.85% $353,386.40
Amt Left: 46.18% $366,241.50
Delta: -0.71% -$8,220.00
$1,278,370.50
Over/Under Est: 58.61% $472,411.90
Amt Left: 61.19% $485,267.00
Delta: -10.27% -$119,025.50

Bid Items & Bid Tabulations

70 Total 0 of 70
LAVACA  |  US 90A  |  YOAKUM  |  0446-01-048  |  02/02/2017  |  $805,958.60  |  STP 2017(701)HES  |  SAFETY TREAT FIXED OBJECTS  |  90 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
K-BAR SERVICES, INC.
HILL COUNTRY BRIDGE, INC.
CONSTAR CONSTRUCTION
RELMCO, INC.
LESTER CONTRACTING, INC.
CHAMPION INFRASTRUCTURE, LLC
FNH CONSTRUCTION, LLC
PREPARING ROW
STA 1.000 $2,000.000 $2,000.000 $3,505.000 $2,000.000 $25,000.000 $2,280.000 $4,500.000 $10,000.000
PREPARING ROW(TREE)(5" TO 12" DIA)
EA 8.000 $800.000 $2,000.000 $685.000 $500.000 $2,200.000 $285.000 $600.000 $2,500.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY C)
CY 295.000 $15.000 $60.000 $30.150 $18.000 $50.000 $46.000 $70.000 $35.000
BLADING
HR 30.000 $100.000 $60.000 $179.250 $80.000 $105.000 $220.000 $250.000 $150.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
AC 2.500 $1,500.000 $200.000 $551.000 $1,500.000 $2,200.000 $1,313.000 $1,400.000 $2,500.000
VEGETATIVE WATERING
MG 101.900 $20.000 $30.000 $27.500 $80.000 $50.000 $83.000 $100.000 $55.000
FL BS (CIP)(TY A GR 1-2 OR 5) FINAL POS
CY 268.000 $100.000 $60.000 $130.400 $110.000 $115.000 $115.000 $120.000 $250.000
PRIME COAT (MC-30)
GAL 315.000 $5.000 $8.000 $15.000 $13.000 $8.000 $11.000 $40.000 $10.000
AGGR(TY-PE GR-4 SAC-B)
CY 10.000 $120.000 $300.000 $500.000 $540.000 $300.000 $945.750 $120.000 $300.000
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
GAL 427.000 $2.800 $10.000 $20.000 $13.000 $8.000 $9.000 $40.000 $8.000
CEM STABIL BKFL
CY 126.000 $150.000 $100.000 $166.750 $70.000 $135.000 $90.000 $80.000 $140.000
CUT & RESTORING PAV
SY 164.000 $150.000 $100.000 $61.400 $50.000 $135.000 $173.000 $60.000 $150.000
TEMPORARY SPL SHORING
SF 780.000 $25.000 $5.000 $26.800 $15.000 $45.000 $15.000 $60.000 $45.000
CL C CONC (HEADWALL)
CY 1.500 $750.000 $700.000 $775.000 $1,000.000 $4,500.000 $2,750.000 $2,500.000 $1,500.000
RIPRAP (CONC)(5 IN)
CY 87.100 $400.000 $475.000 $766.000 $350.000 $533.000 $650.000 $700.000 $650.000
CMP (GAL STL 18 IN)
LF 20.000 $55.000 $50.000 $34.700 $47.000 $107.430 $77.750 $120.000 $65.000
CMP AR (GAL STL DES 2)
LF 16.000 $65.000 $70.000 $36.400 $50.000 $90.940 $76.000 $150.000 $85.000
CMP AR (GAL STL DES 3)
LF 48.000 $80.000 $80.000 $39.700 $55.000 $77.550 $50.700 $160.000 $95.000
CONC BOX CULV (3 FT X 2 FT)
LF 7.000 $260.000 $300.000 $243.500 $470.000 $981.500 $1,081.000 $525.000 $600.000
CONC BOX CULV (4 FT X 3 FT)
LF 7.000 $350.000 $600.000 $299.000 $480.000 $994.500 $1,112.000 $600.000 $700.000
CONC BOX CULV (5 FT X 2 FT)
LF 15.000 $350.000 $1,200.000 $310.000 $490.000 $994.500 $1,035.000 $750.000 $700.000
CONC BOX CULV (5 FT X 4 FT)
LF 8.000 $450.000 $1,000.000 $377.750 $510.000 $1,007.500 $1,135.000 $820.000 $750.000
CONC BOX CULV (6 FT X 3 FT)
LF 8.000 $450.000 $800.000 $387.500 $520.000 $825.500 $1,203.000 $1,050.000 $850.000
CONC BOX CULV (6 FT X 4 FT)
LF 24.000 $550.000 $1,000.000 $364.750 $530.000 $955.500 $1,154.000 $1,200.000 $850.000
CONC BOX CULV (7 FT X 6 FT)
LF 16.000 $650.000 $1,500.000 $460.000 $800.000 $1,092.000 $1,309.000 $2,100.000 $900.000
CONC BOX CULV (8 FT X 8 FT)
LF 24.000 $900.000 $1,700.000 $607.000 $850.000 $1,042.600 $1,545.000 $2,900.000 $1,500.000
CONC BOX CULV (9 FT X 8 FT)
LF 16.000 $1,050.000 $1,800.000 $794.000 $900.000 $1,076.400 $1,850.000 $3,600.000 $1,500.000
RC PIPE (CL III)(18 IN)
LF 16.000 $60.000 $70.000 $70.350 $50.000 $87.100 $79.000 $120.000 $85.000
RC PIPE (CL III)(24 IN)
LF 136.000 $75.000 $100.000 $45.550 $54.000 $75.400 $77.500 $150.000 $125.000
RC PIPE (ARCH)(CL III)(DES 2)
LF 78.000 $175.000 $80.000 $70.450 $80.000 $201.500 $222.000 $275.000 $300.000
RC PIPE (ARCH)(CL III)(DES 3)
LF 168.000 $185.000 $90.000 $70.450 $90.000 $215.800 $182.000 $280.000 $300.000
RC PIPE (ARCH)(CL III)(DES 4)
LF 80.000 $200.000 $100.000 $94.700 $200.000 $266.500 $217.500 $320.000 $300.000
WINGWALL (FW - S) (HW=10 FT)
EA 1.000 $11,000.000 $10,000.000 $11,390.000 $16,000.000 $21,000.000 $19,895.000 $12,000.000 $30,000.000
WINGWALL (FW - S) (HW=11 FT)
EA 2.000 $12,000.000 $12,000.000 $13,520.000 $18,000.000 $32,500.000 $21,787.500 $15,000.000 $50,000.000
WINGWALL (FW - S) (HW=9 FT)
EA 1.000 $10,000.000 $8,000.000 $10,150.000 $15,000.000 $21,000.000 $18,645.000 $12,000.000 $28,500.000
SET (TY I)(S=3 FT)(HW=3FT)(4:1)(C)
EA 2.000 $5,000.000 $3,100.000 $4,820.000 $5,300.000 $5,846.100 $6,670.000 $2,200.000 $5,000.000
SET (TY I)(S= 4 FT)(HW= 4 FT)(4:1) (C)
EA 2.000 $5,000.000 $3,200.000 $6,640.000 $7,000.000 $7,337.200 $8,442.500 $3,200.000 $5,000.000
SET (TY I)(S= 5 FT)(HW= 3 FT)(4:1) (C)
EA 4.000 $4,500.000 $3,200.000 $4,827.000 $6,000.000 $6,074.250 $6,965.000 $2,600.000 $5,500.000
SET (TY I)(S= 5 FT)(HW= 6 FT)(4:1) (C)
EA 2.000 $6,000.000 $5,600.000 $13,100.000 $9,000.000 $11,952.200 $7,635.000 $7,600.000 $7,000.000
SET (TY I)(S= 6 FT)(HW= 4 FT)(4:1) (C)
EA 2.000 $6,000.000 $3,200.000 $7,620.000 $6,200.000 $8,412.300 $7,760.000 $4,500.000 $7,000.000
SET (TY I)(S= 6 FT)(HW= 5 FT)(4:1) (C)
EA 10.000 $8,000.000 $5,000.000 $4,657.000 $6,600.000 $7,014.800 $8,465.000 $3,400.000 $8,000.000
SET (TY I)(S= 7 FT)(HW= 7 FT)(3:1) (C)
EA 2.000 $7,000.000 $8,000.000 $6,380.000 $7,300.000 $7,874.100 $7,855.000 $4,600.000 $8,000.000
SET (TY I)(S= 7 FT)(HW= 7 FT)(4:1) (C)
EA 2.000 $7,500.000 $5,000.000 $8,490.000 $8,200.000 $9,366.500 $10,402.500 $4,800.000 $8,000.000
SET (TY II) (12 IN) (RCP) (6: 1) (P)
EA 2.000 $800.000 $1,200.000 $1,005.000 $1,400.000 $1,300.000 $1,532.000 $1,500.000 $1,250.000
SET (TY II) (18 IN) (CMP) (6: 1) (P)
EA 12.000 $900.000 $1,200.000 $1,011.000 $1,500.000 $1,300.000 $1,827.500 $1,800.000 $1,250.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 18.000 $1,000.000 $1,200.000 $1,201.000 $1,600.000 $1,300.000 $2,223.000 $1,800.000 $1,250.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 13.000 $1,200.000 $1,200.000 $1,404.000 $1,800.000 $1,332.500 $2,873.000 $2,600.000 $1,500.000
SET (TY II) (36 IN) (RCP) (4: 1) (C)
EA 2.000 $3,000.000 $1,400.000 $2,500.000 $3,900.000 $2,028.000 $5,668.500 $4,200.000 $3,000.000
SET (TY II) (DES 2) (CMP) (6: 1) (P)
EA 4.000 $1,600.000 $1,000.000 $729.000 $1,500.000 $1,300.000 $2,116.000 $2,400.000 $1,250.000
SET (TY II) (DES 2) (RCP) (6: 1) (P)
EA 2.000 $2,000.000 $1,000.000 $1,692.000 $2,800.000 $2,548.000 $3,449.000 $2,400.000 $1,250.000
SET (TY II) (DES 3) (CMP) (6: 1) (P)
EA 10.000 $1,800.000 $1,100.000 $1,056.000 $1,600.000 $1,300.000 $2,465.000 $2,400.000 $1,250.000
SET (TY II) (DES 3) (RCP) (6: 1) (P)
EA 8.000 $2,500.000 $1,200.000 $2,214.000 $2,300.000 $3,315.000 $3,602.000 $2,400.000 $1,250.000
SET (TY II) (DES 4) (RCP) (6: 1) (P)
EA 4.000 $3,000.000 $1,300.000 $3,930.000 $4,000.000 $5,707.000 $5,524.000 $5,200.000 $1,250.000
REMOV STR (SMALL)
EA 7.000 $1,000.000 $1,000.000 $388.500 $600.000 $1,000.000 $2,150.000 $1,200.000 $1,500.000
MOBILIZATION
LS 1.000 $58,500.000 $75,000.000 $82,000.000 $43,000.000 $110,000.000 $68,000.000 $75,000.000 $125,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $3,000.000 $4,000.000 $7,750.000 $3,400.000 $6,500.000 $2,412.000 $4,500.000 $8,500.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 90.000 $30.000 $30.000 $26.250 $50.000 $37.400 $77.500 $40.000 $30.000
ROCK FILTER DAMS (REMOVE)
LF 90.000 $8.000 $5.000 $5.250 $15.000 $9.900 $53.750 $10.000 $15.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,690.000 $2.500 $4.000 $2.860 $3.000 $2.200 $3.000 $5.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,690.000 $0.500 $1.000 $0.780 $1.000 $2.200 $1.400 $2.000 $2.000
MTL W-BEAM GD FEN (TIM POST)
LF 1,550.000 $20.000 $22.000 $15.500 $25.000 $21.450 $24.650 $25.000 $25.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,500.000 $1,200.000 $2,401.000 $2,000.000 $1,870.000 $437.500 $800.000 $1,850.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 150.000 $50.000 $40.000 $39.400 $60.000 $61.600 $76.250 $75.000 $50.000
REMOVE METAL BEAM GUARD FENCE
LF 500.000 $1.000 $3.000 $3.820 $3.000 $1.100 $2.750 $6.000 $30.000
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $150.000 $100.000 $62.050 $300.000 $165.000 $343.750 $800.000 $500.000
GUARDRAIL END TREATMENT (INSTALL)
EA 12.000 $2,400.000 $2,400.000 $1,864.000 $2,400.000 $2,387.000 $3,000.000 $2,750.000 $2,850.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 38.000 $10.000 $3.000 $12.950 $70.000 $13.200 $22.400 $20.000 $100.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 40.000 $25.000 $20.000 $28.900 $50.000 $20.900 $30.000 $150.000 $100.000
INSTL DEL ASSM (D-SY)SZ (BRF)CTB (BI)
EA 6.000 $25.000 $20.000 $13.450 $50.000 $20.900 $32.000 $60.000 $100.000
INSTL OM ASSM (OM-2Y)(WC)GND(BI)
EA 34.000 $50.000 $20.000 $120.500 $60.000 $55.000 $52.500 $150.000 $100.000
Totals: $805,958.600 $793,103.500 $821,837.600 $823,547.000 $1,146,094.840 $1,151,125.000 $1,159,345.000 $1,278,370.500