LAVACA UA 77 (0269-04-039)

Items: 71

County: LAVACA
Length: N/A
Highway: UA 77
District: YOAKUM
Control Number: 0269-04-039
DBE Goal: N/A
Project: STP 2B20(112)HES
Guaranty: N/A
Time: 75 WORKING DAYS
Engineer's Estimate: $955,596.70
Date: 08/05/2020 (5 years ago)
Contract Number: N/A
Type: ADD LEFT TURN LANES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$955,596.70
$1,216,444.86
Over/Under Est: 27.3% $260,848.16
Over/Under Est: 27.42% $262,031.72
Amt Left: 0.1% $1,183.56
Over/Under Est: 31.11% $297,279.51
Amt Left: 2.99% $36,431.35
Delta: -2.89% -$35,247.79
Over/Under Est: 35.09% $335,315.80
Amt Left: 6.12% $74,467.64
Delta: -3.04% -$38,036.29
Over/Under Est: 40.78% $389,709.20
Amt Left: 10.59% $128,861.04
Delta: -4.21% -$54,393.40
Over/Under Est: 53.17% $508,109.69
Amt Left: 20.33% $247,261.53
Delta: -8.80% -$118,400.49

Bid Items & Bid Tabulations

71 Total 0 of 71
LAVACA  |  UA 77  |  YOAKUM  |  0269-04-039  |  08/05/2020  |  $955,596.70  |  STP 2B20(112)HES  |  ADD LEFT TURN LANES  |  75 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HUNTER INDUSTRIES, LTD.
BRANNAN PAVING CO., LTD.
DEAN WORD COMPANY, LTD.
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
ANGEL BROTHERS HOLDINGS CORP.
TIERRA LEASE SERVICE, LLC
PREPARING ROW
STA 4.000 $1,400.000 $1,371.960 $2,243.000 $7,107.680 $5,000.000 $2,500.000 $3,126.780
EXCAVATION (ROADWAY)
CY 2,592.000 $8.000 $12.270 $8.100 $11.394 $17.750 $9.500 $11.200
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 3,088.000 $9.600 $15.420 $9.260 $14.631 $16.200 $13.000 $10.490
BLADING
HR 50.000 $75.000 $102.600 $125.000 $95.440 $65.000 $100.000 $133.220
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 11,200.000 $0.320 $0.230 $0.180 $0.187 $0.200 $0.250 $0.190
BROADCAST SEED (TEMP) (WARM)
SY 2,800.000 $0.200 $0.400 $0.300 $0.312 $0.320 $0.440 $0.300
BROADCAST SEED (TEMP) (COOL)
SY 2,800.000 $0.200 $0.400 $0.300 $0.312 $0.320 $0.440 $0.300
VEGETATIVE WATERING
MG 93.700 $16.000 $18.930 $20.000 $32.360 $20.000 $50.000 $28.000
FL BS (CMP IN PLC)(TYE GR1-2)(FNAL POS)
CY 4,790.000 $52.000 $63.250 $62.690 $58.935 $56.000 $65.750 $67.750
LIME TRT (EXST MATL) (6")
SY 15,489.000 $2.600 $3.420 $2.420 $2.328 $3.000 $4.500 $2.750
LIME(HYD,COM OR QK)(SLRY)OR QK(DRY)
TON 111.000 $128.000 $153.300 $145.000 $145.749 $180.000 $200.000 $221.000
PRIME COAT (MC-30)
GAL 2,650.000 $3.600 $4.060 $5.210 $4.237 $3.000 $4.000 $4.000
AGGR(TY-PE GR-3 SAC-B)
CY 156.000 $64.000 $86.700 $132.570 $123.462 $225.000 $125.000 $127.000
AGGR(TY-PE GR-4 SAC-B)
CY 168.000 $64.000 $86.700 $133.640 $94.722 $143.000 $125.000 $121.000
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
GAL 12,723.000 $2.400 $3.340 $4.060 $3.126 $2.750 $3.300 $2.800
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 100.000 $40.000 $65.510 $205.330 $99.188 $126.850 $55.000 $300.000
CEM STABIL BKFL
CY 12.000 $80.000 $190.870 $87.000 $130.000 $125.000 $500.000 $210.000
TEMPORARY SPL SHORING
SF 30.000 $12.000 $20.000 $160.000 $156.000 $150.000 $165.000 $215.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 20.000 $120.000 $255.000 $281.000 $265.200 $255.000 $275.000 $450.000
RIPRAP (CONC)(4 IN)
CY 0.700 $400.000 $550.000 $1,200.000 $1,040.000 $1,000.000 $1,100.000 $1,100.000
CMP (GAL STL 18 IN)
LF 32.000 $60.000 $180.000 $74.000 $67.600 $65.000 $70.000 $75.000
CONC BOX CULV (3 FT X 3 FT)
LF 13.000 $280.000 $700.000 $590.000 $676.000 $650.000 $710.000 $550.000
CONC BOX CULV (4 FT X 4 FT)
LF 14.000 $320.000 $900.000 $625.000 $884.000 $850.000 $925.000 $600.000
WINGWALL (PW - 1) (HW=7 FT)
EA 1.000 $14,400.000 $12,000.000 $9,800.000 $14,560.000 $14,000.000 $15,250.000 $24,500.000
WINGWALL (PW - 1) (HW=8 FT)
EA 1.000 $16,000.000 $16,000.000 $12,780.000 $17,680.000 $17,000.000 $18,500.000 $28,000.000
SET (TY I)(S=3 FT)(HW= 4 FT)(3:1)(C)
EA 2.000 $4,000.000 $3,000.000 $5,800.000 $7,280.000 $7,000.000 $7,650.000 $16,250.000
SET (TY II) (18 IN) (CMP) (6: 1) (P)
EA 4.000 $1,000.000 $1,200.000 $2,100.000 $1,040.000 $1,000.000 $1,100.000 $1,200.000
MOBILIZATION
LS 1.000 $69,000.000 $120,863.950 $93,530.000 $128,327.866 $110,000.000 $134,500.000 $175,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $3,000.000 $2,348.810 $1,581.000 $6,671.198 $2,000.000 $2,450.000 $1,700.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 50.000 $40.000 $40.000 $40.000 $41.600 $40.000 $40.000 $43.000
ROCK FILTER DAMS (REMOVE)
LF 50.000 $8.000 $11.000 $10.000 $11.440 $10.000 $10.000 $11.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 300.000 $2.400 $4.000 $4.000 $4.160 $4.000 $4.250 $4.250
TEMP SEDMT CONT FENCE (REMOVE)
LF 300.000 $1.600 $1.000 $3.000 $1.040 $3.000 $3.250 $3.250
INTERSECTIONS (ACP)
SY 800.000 $28.000 $43.980 $42.690 $19.721 $61.200 $55.000 $40.000
DRIVEWAYS (CONC)
SY 202.000 $56.000 $90.000 $130.500 $130.000 $125.000 $135.000 $95.000
DRIVEWAYS (SURF TREAT)
SY 531.000 $20.000 $30.660 $21.270 $37.163 $28.000 $50.000 $31.000
RUMBLE STRIPS (CENTERLINE)
LF 5,640.000 $0.200 $1.520 $0.850 $0.520 $1.000 $0.550 $0.850
MAILBOX INSTALL-S (WC-POST) TY 3
EA 10.000 $140.000 $125.000 $125.000 $130.000 $200.000 $265.000 $215.000
RELOCATE RD IL ASM (TRANS-BASE)
EA 2.000 $2,000.000 $1,950.000 $1,200.000 $2,028.000 $2,100.000 $2,100.000 $2,850.000
CONDT (PVC) (SCH 40) (2")
LF 285.000 $6.800 $11.000 $15.000 $11.440 $12.000 $12.000 $25.000
CONDT (PVC) (SCH 80) (2") (BORE)
LF 90.000 $9.600 $20.000 $18.000 $20.800 $22.000 $22.000 $70.000
ELEC CONDR (NO.8) BARE
LF 375.000 $0.960 $2.350 $2.000 $2.444 $2.500 $2.550 $3.250
ELEC CONDR (NO.8) INSULATED
LF 750.000 $1.000 $2.500 $2.500 $2.600 $2.650 $2.750 $3.250
GROUND BOX TY A (122311)W/APRON
EA 2.000 $480.000 $1,100.000 $1,000.000 $1,144.000 $1,250.000 $1,200.000 $1,500.000
REMOVE GROUND BOX
EA 2.000 $240.000 $200.000 $300.000 $208.000 $225.000 $220.000 $275.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 2.000 $360.000 $500.000 $500.000 $520.000 $510.000 $850.000 $550.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 1.000 $440.000 $540.000 $540.000 $561.600 $650.000 $850.000 $700.000
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
EA 2.000 $600.000 $775.000 $775.000 $806.000 $1,000.000 $1,125.000 $1,050.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 9.000 $300.000 $325.000 $325.000 $338.000 $425.000 $600.000 $400.000
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 2.000 $340.000 $365.000 $365.000 $379.600 $520.000 $650.000 $550.000
REMOVE SM RD SN SUP&AM
EA 16.000 $44.000 $75.000 $75.000 $78.000 $125.000 $150.000 $75.000
INSTL OM ASSM (OM-2Y)(WC)GND(BI)
EA 6.000 $52.000 $55.000 $55.000 $57.200 $55.000 $90.000 $55.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 10,080.000 $0.180 $0.600 $0.600 $0.624 $0.650 $0.600 $0.650
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 13,440.000 $0.180 $0.600 $0.600 $0.624 $0.650 $0.600 $0.650
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 672.000 $1.050 $1.780 $1.500 $1.516 $1.100 $1.000 $0.550
REFL PAV MRK TY I (W)8"(DOT)(090MIL)
LF 147.000 $1.000 $1.000 $1.000 $1.040 $1.100 $1.000 $1.100
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 250.000 $0.900 $1.000 $1.000 $1.040 $1.100 $1.000 $1.100
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 6,720.000 $0.400 $0.500 $0.500 $0.520 $0.520 $0.500 $0.550
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
LF 680.000 $0.350 $0.500 $0.500 $0.520 $0.520 $0.500 $0.550
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 9,190.000 $0.350 $0.500 $0.500 $0.520 $0.520 $0.500 $0.550
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 50.000 $14.000 $12.000 $12.000 $12.480 $13.000 $12.000 $13.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 4.000 $400.000 $210.000 $210.000 $218.400 $220.000 $210.000 $225.000
PREFAB PAV MRK TY C (Y) (24") (SLD)
LF 635.000 $11.000 $12.000 $12.000 $12.480 $13.000 $12.000 $13.000
REFL PAV MRKR TY I-C
EA 26.000 $4.000 $5.000 $5.000 $5.200 $5.500 $5.000 $5.500
REFL PAV MRKR TY II-A-A
EA 382.000 $4.000 $5.000 $5.000 $5.200 $5.100 $5.000 $5.500
ELIM EXT PAV MRK & MRKS (4")
LF 4,495.000 $0.360 $0.700 $0.700 $0.728 $0.750 $0.750 $1.750
D-GR HMA TY-D SAC-B PG70-22
TON 3,403.000 $76.000 $80.370 $90.690 $84.684 $91.500 $88.000 $111.000
TACK COAT
GAL 896.000 $3.200 $3.060 $3.600 $2.697 $3.000 $3.000 $3.200
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $8,000.000 $7,500.000 $10,000.000 $10,400.000 $8,000.000 $10,000.000 $5,500.000
TMA (STATIONARY)
DAY 20.000 $240.000 $304.690 $500.000 $243.000 $500.000 $250.000 $270.000
TMA (MOBILE OPERATION)
DAY 20.000 $400.000 $507.820 $250.000 $491.400 $250.000 $250.000 $27.000
Totals: $955,596.700 $1,216,444.861 $1,217,628.420 $1,252,876.270 $1,290,912.500 $1,345,305.900 $1,463,706.390