Show Job Controls
Bid Cobra

LA SALLE IH 35 (0017-08-118)

Items: 47

County: LA SALLE
Length: N/A
Highway: IH 35
District: LAREDO
Control Number: 0017-08-118
DBE Goal: N/A
Project: F 2023(478)
Guaranty: N/A
Time: 49 WORKING DAYS
Engineer's Estimate: $1,510,367.43
Date: 04/04/2023 (3 years ago)
Contract Number: N/A
Type: REPAIR ROADWAY
Mail/Deliver Bids To: N/A
LUIS VILLARREAL
ANGEL MARTINEZ
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$1,510,367.43
$1,863,389.00
Over/Under Est: 23.37% $353,021.57
Over/Under Est: 32.98% $498,144.08
Amt Left: 7.79% $145,122.51
$2,096,706.00
Over/Under Est: 38.82% $586,338.57
Amt Left: 12.52% $233,317.00
Delta: -4.39% -$88,194.49
Over/Under Est: 51.2% $773,303.97
Amt Left: 22.55% $420,282.40
Delta: -8.92% -$186,965.40
Subcontractor Percentage Amount
TEXAS ICON CONSTRUCTION, LLC 27.96% $521,003.56
PERFORMANCE EQUIPMENT SERVICE 3.62% $67,454.68
HIGHWAY BARRICADES AND SERVICES, LLC 1.15% $21,428.97
PRIMATE CONSTRUCTION, LP 0.64% $11,925.69
PROFESSIONAL TRAFFIC CONTROL LLC 0.53% $9,875.96
Total: 33.90% $631,688.86

Bid Items & Bid Tabulations

47 Total 0 of 47
LA SALLE  |  IH 35  |  LAREDO  |  0017-08-118  |  04/04/2023  |  $1,510,367.43  |  F 2023(478)  |  REPAIR ROADWAY  |  49 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ANDERSON COLUMBIA CO., INC.
TEXAS MATERIALS GROUP, INC.
CK NEWBERRY, LLC
ACME BRIDGE COMPANY, INC.
REMOVING CONC (RIPRAP)
SY 88.000 $10.000 $50.000 $36.000 $100.000 $27.100
REMOVING CONC (FLUME)
SY 72.000 $15.000 $70.000 $36.000 $100.000 $33.100
REMOVE TRT BASE & ASPH PAV (20"-30")
SY 608.000 $5.000 $50.000 $38.000 $30.000 $33.900
EXCAVATION (ROADWAY)
CY 610.000 $15.000 $45.000 $50.000 $40.000 $35.100
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 1,438.000 $30.000 $48.000 $70.000 $40.000 $47.300
BLADING
HR 10.000 $150.000 $250.000 $180.000 $130.000 $204.000
SOIL RETENTION BLANKETS (CL 1) (TY C)
SY 3,184.000 $8.000 $4.000 $3.450 $2.500 $1.450
PROOF ROLLING
HR 8.000 $280.000 $120.000 $150.000 $100.000 $137.000
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 282.000 $115.000 $140.000 $195.000 $150.000 $195.000
FL BS (CMP IN PLC)(TY E GR 4)(FNAL POS)
CY 209.000 $45.000 $160.000 $123.000 $125.000 $167.000
PRIME COAT (MC-30)
GAL 114.000 $4.700 $14.000 $37.000 $25.000 $5.700
FLEXIBLE PAVEMENT STRUCTURE REPAIR(5")
SY 1,337.000 $30.000 $64.000 $55.000 $100.000 $109.000
PLANE ASPH CONC PAV (3")
SY 9,320.000 $5.000 $5.000 $3.500 $5.000 $5.500
FLOWABLE BACKFILL
CY 180.000 $200.000 $240.000 $210.000 $300.000 $390.000
RIPRAP (CONC)(CL B)
CY 779.000 $650.000 $600.000 $700.000 $625.000 $616.000
RIPRAP (MOW STRIP)(4 IN)
CY 91.000 $650.000 $630.000 $685.000 $650.000 $621.000
CLEANING AND SEALING EXISTING JOINTS
LF 240.000 $35.000 $50.000 $47.000 $100.000 $56.400
MOBILIZATION
LS 1.000 $134,510.680 $180,000.000 $200,000.000 $200,000.000 $210,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $3,500.000 $4,000.000 $34,500.000 $25,000.000 $19,600.000
ONE-WAY TRAF CONT (FLAGGER CONT)
HR 150.000 $150.000 $150.000 $85.000 $125.000 $180.000
PTB (FRN&INSTL)(SGL SLP)(TY 1) OR (STL)
LF 1,200.000 $60.000 $87.000 $50.000 $100.000 $160.000
PTB (MOVE)(SGL SLP)(TY 1) OR (STL)
LF 1,200.000 $4.500 $18.000 $20.000 $15.000 $7.400
PTB (REMOVE)(SGL SLP)(TY 1) OR (STL)
LF 1,200.000 $14.000 $20.000 $20.000 $40.000 $40.100
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 4,367.000 $0.250 $2.000 $1.900 $1.500 $1.250
MTL W-BEAM GD FEN (TIM POST)
LF 1,125.000 $28.050 $30.000 $23.000 $28.000 $23.300
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 1.000 $1,700.000 $3,500.000 $3,100.000 $3,000.000 $4,340.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 1.000 $1,250.000 $2,400.000 $1,800.000 $2,000.000 $1,830.000
REMOVE METAL BEAM GUARD FENCE
LF 1,125.000 $2.400 $10.000 $1.350 $2.000 $1.400
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 1.000 $250.000 $880.000 $275.000 $300.000 $279.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $2,900.000 $4,300.000 $3,100.000 $4,000.000 $3,190.000
GUARDRAIL END TREATMENT (REMOVE)
EA 2.000 $300.000 $400.000 $270.000 $400.000 $280.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 1.000 $1,250.000 $1,800.000 $1,300.000 $2,000.000 $1,400.000
CRASH CUSH ATTEN (REMOVE)
EA 1.000 $800.000 $2,200.000 $550.000 $2,000.000 $335.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 1.000 $8,140.000 $10,000.000 $11,000.000 $12,000.000 $9,500.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 26.000 $30.000 $115.000 $28.000 $30.000 $28.000
PAVEMENT SEALER 6"
LF 580.000 $0.200 $2.000 $1.580 $2.000 $1.600
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 145.000 $0.700 $2.300 $2.180 $2.500 $2.250
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 2,184.000 $0.400 $2.500 $1.800 $2.000 $1.850
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 2,184.000 $0.400 $2.000 $1.690 $2.000 $1.750
REFL PAV MRKR TY II-C-R
EA 28.000 $4.250 $18.000 $17.000 $20.000 $16.800
ELIM EXT PAV MRK & MRKS (4")
LF 2,465.000 $0.450 $1.300 $1.200 $5.000 $1.100
D-GR HMA TY-B SAC-B PG70-22
TON 377.000 $100.000 $174.000 $170.000 $180.000 $216.000
STONE-MTRX-ASPH SMA-C SAC-A PG76-22
TON 1,611.000 $140.000 $186.000 $200.000 $215.000 $256.000
BONDING COURSE
GAL 941.000 $3.000 $7.000 $5.000 $7.000 $3.400
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $11,000.000 $7,000.000 $11,000.000 $10,000.000 $17,000.000
TMSP RADAR SPEED CONTROL MONITOR
EA 2.000 $13,500.000 $11,000.000 $6,000.000 $6,000.000 $20,700.000
TMA (STATIONARY)
DAY 120.000 $225.000 $300.000 $350.000 $400.000 $261.000
Totals: $1,510,367.430 $1,863,389.000 $2,008,511.510 $2,096,706.000 $2,283,671.400