Job Info for 0017-08-118

County: LASALLE Highway: IH 35 Date: 04/04/2023 (1 year ago) Engineer's Estimate: $1,510,367 Control Number: 0017-08-118
Project: F 2023(478) District: Time: 49 WORKING DAYS Type: REPAIR ROADWAY
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $1,510,367.43
ANDERSON COLUMBIA CO., INC.   $1,863,389.00 1
23.37% | $353,021.57
TEXAS MATERIALS GROUP, INC.   $2,008,511.51 2
32.98% | $498,144.08
7.79% | $145,122.51
CK NEWBERRY, LLC   $2,096,706.00 3
38.82% | $586,338.57
12.52% | $233,317.00
4.39% | $88,194.49
ACME BRIDGE COMPANY, INC.   $2,283,671.40 4
51.2% | $773,303.97
22.55% | $420,282.40
8.92% | $186,965.40
Subcontractor Percentage Amount
TEXAS ICON CONSTRUCTION, LLC 27.96% $521,003.56
PERFORMANCE EQUIPMENT SERVICE 3.62% $67,454.68
HIGHWAY BARRICADES AND SERVICES, LLC 1.15% $21,428.97
PRIMATE CONSTRUCTION, LP 0.64% $11,925.69
PROFESSIONAL TRAFFIC CONTROL LLC 0.53% $9,875.96
Total: 33.90% $631,688.86

Bid Items

Items: 47, 0 filtered
LASALLE IH 35  |   |  0017-08-118  |  04/04/2023  |  $1,510,367  |  F 2023(478)  |  REPAIR ROADWAY  |  49 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate ANDERSON COLUMBIA CO., INC. TEXAS MATERIALS GROUP, INC. CK NEWBERRY, LLC ACME BRIDGE COMPANY, INC.
104 6009 REMOVING CONC (RIPRAP) SY 88.000 $10.000 $50.000 $36.000 $100.000 $27.100
104 6044 REMOVING CONC (FLUME) SY 72.000 $15.000 $70.000 $36.000 $100.000 $33.100
105 6122 REMOVE TRT BASE & ASPH PAV (20"-30") SY 608.000 $5.000 $50.000 $38.000 $30.000 $33.900
110 6001 EXCAVATION (ROADWAY) CY 610.000 $15.000 $45.000 $50.000 $40.000 $35.100
132 6006 EMBANKMENT (FINAL)(DENS CONT)(TY C) CY 1,438.000 $30.000 $48.000 $70.000 $40.000 $47.300
150 6002 BLADING HR 10.000 $150.000 $250.000 $180.000 $130.000 $204.000
169 6003 SOIL RETENTION BLANKETS (CL 1) (TY C) SY 3,184.000 $8.000 $4.000 $3.450 $2.500 $1.450
216 6001 PROOF ROLLING HR 8.000 $280.000 $120.000 $150.000 $100.000 $137.000
247 6041 FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS) CY 282.000 $115.000 $140.000 $195.000 $150.000 $195.000
247 6060 FL BS (CMP IN PLC)(TY E GR 4)(FNAL POS) CY 209.000 $45.000 $160.000 $123.000 $125.000 $167.000
310 6009 PRIME COAT (MC-30) GAL 114.000 $4.700 $14.000 $37.000 $25.000 $5.700
351 6001 FLEXIBLE PAVEMENT STRUCTURE REPAIR(5") SY 1,337.000 $30.000 $64.000 $55.000 $100.000 $109.000
354 6048 PLANE ASPH CONC PAV (3") SY 9,320.000 $5.000 $5.000 $3.500 $5.000 $5.500
401 6001 FLOWABLE BACKFILL CY 180.000 $200.000 $240.000 $210.000 $300.000 $390.000
432 6006 RIPRAP (CONC)(CL B) CY 779.000 $650.000 $600.000 $700.000 $625.000 $616.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 91.000 $650.000 $630.000 $685.000 $650.000 $621.000
438 6001 CLEANING AND SEALING EXISTING JOINTS LF 240.000 $35.000 $50.000 $47.000 $100.000 $56.400
500 6001 MOBILIZATION LS 1.000 $134,510.680 $180,000.000 $200,000.000 $200,000.000 $210,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 $3,500.000 $4,000.000 $34,500.000 $25,000.000 $19,600.000
510 6001 ONE-WAY TRAF CONT (FLAGGER CONT) HR 150.000 $150.000 $150.000 $85.000 $125.000 $180.000
512 6072 PTB (FRN&INSTL)(SGL SLP)(TY 1) OR (STL) LF 1,200.000 $60.000 $87.000 $50.000 $100.000 $160.000
512 6074 PTB (MOVE)(SGL SLP)(TY 1) OR (STL) LF 1,200.000 $4.500 $18.000 $20.000 $15.000 $7.400
512 6076 PTB (REMOVE)(SGL SLP)(TY 1) OR (STL) LF 1,200.000 $14.000 $20.000 $20.000 $40.000 $40.100
533 6003 RUMBLE STRIPS (SHOULDER) ASPHALT LF 4,367.000 $0.250 $2.000 $1.900 $1.500 $1.250
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 1,125.000 $28.050 $30.000 $23.000 $28.000 $23.300
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 1.000 $1,700.000 $3,500.000 $3,100.000 $3,000.000 $4,340.000
540 6016 DOWNSTREAM ANCHOR TERMINAL SECTION EA 1.000 $1,250.000 $2,400.000 $1,800.000 $2,000.000 $1,830.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 1,125.000 $2.400 $10.000 $1.350 $2.000 $1.400
542 6004 RM MTL BM GD FENCE TRANS (THRIE-BEAM) EA 1.000 $250.000 $880.000 $275.000 $300.000 $279.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 2.000 $2,900.000 $4,300.000 $3,100.000 $4,000.000 $3,190.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 2.000 $300.000 $400.000 $270.000 $400.000 $280.000
545 6003 CRASH CUSH ATTEN (MOVE & RESET) EA 1.000 $1,250.000 $1,800.000 $1,300.000 $2,000.000 $1,400.000
545 6005 CRASH CUSH ATTEN (REMOVE) EA 1.000 $800.000 $2,200.000 $550.000 $2,000.000 $335.000
545 6019 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) EA 1.000 $8,140.000 $10,000.000 $11,000.000 $12,000.000 $9,500.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 26.000 $30.000 $115.000 $28.000 $30.000 $28.000
666 6225 PAVEMENT SEALER 6" LF 580.000 $0.200 $2.000 $1.580 $2.000 $1.600
666 6306 RE PM W/RET REQ TY I (W)6"(BRK)(100MIL) LF 145.000 $0.700 $2.300 $2.180 $2.500 $2.250
666 6309 RE PM W/RET REQ TY I (W)6"(SLD)(100MIL) LF 2,184.000 $0.400 $2.500 $1.800 $2.000 $1.850
666 6321 RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL) LF 2,184.000 $0.400 $2.000 $1.690 $2.000 $1.750
672 6010 REFL PAV MRKR TY II-C-R EA 28.000 $4.250 $18.000 $17.000 $20.000 $16.800
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 2,465.000 $0.450 $1.300 $1.200 $5.000 $1.100
3076 6007 D-GR HMA TY-B SAC-B PG70-22 TON 377.000 $100.000 $174.000 $170.000 $180.000 $216.000
3080 6001 STONE-MTRX-ASPH SMA-C SAC-A PG76-22 TON 1,611.000 $140.000 $186.000 $200.000 $215.000 $256.000
3084 6001 BONDING COURSE GAL 941.000 $3.000 $7.000 $5.000 $7.000 $3.400
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 4.000 $11,000.000 $7,000.000 $11,000.000 $10,000.000 $17,000.000
6158 6001 TMSP RADAR SPEED CONTROL MONITOR EA 2.000 $13,500.000 $11,000.000 $6,000.000 $6,000.000 $20,700.000
6185 6002 TMA (STATIONARY) DAY 120.000 $225.000 $300.000 $350.000 $400.000 $261.000
Totals: $1,510,367.43 $1,863,389.00 $2,008,511.51 $2,096,706.00 $2,283,671.40