LAMB SL 430 (0052-13-005)

Items: 40

County: LAMB
Length: N/A
Highway: SL 430
District: LUBBOCK
Control Number: 0052-13-005
DBE Goal: N/A
Project: STP 2018(603)
Guaranty: N/A
Time: 50 WORKING DAYS
Engineer's Estimate: $628,878.90
Date: 03/07/2018 (8 years ago)
Contract Number: N/A
Type: INTERSECTION IMPROVEMENTS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$628,878.90
$746,928.46
Over/Under Est: 18.77% $118,049.56
$765,282.51
Over/Under Est: 21.69% $136,403.61
Amt Left: 2.46% $18,354.05
Over/Under Est: 22.49% $141,410.76
Amt Left: 3.13% $23,361.20
Delta: -0.65% -$5,007.15

Bid Items & Bid Tabulations

40 Total 0 of 40
LAMB  |  SL 430  |  LUBBOCK  |  0052-13-005  |  03/07/2018  |  $628,878.90  |  STP 2018(603)  |  INTERS IMPRVS  |  50 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ALLEN BUTLER CONSTRUCTION, INC.
DUININCK, INC.
GILVIN-TERRILL, LTD.
REMOVING CONC (MISC)
SY 123.850 $30.000 $48.570 $40.000 $35.000
EXCAVATION (ROADWAY)
CY 70.000 $10.000 $68.550 $38.500 $35.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 406.000 $20.000 $46.690 $54.500 $50.000
BACKFILL (TY B)
STA 7.520 $1,000.000 $725.790 $610.000 $1,000.000
BLADING
STA 7.520 $1,000.000 $472.530 $305.000 $1,000.000
REWORK BS MTL (TY C)(7"- 9.5")(DC)
SY 3,520.000 $5.000 $9.400 $4.950 $10.000
PRIME COAT (MC-30)
GAL 710.000 $6.000 $9.270 $7.700 $5.000
EMULS ASPH (EROSN CONT)(CSS-1H)
GAL 330.000 $6.000 $8.780 $7.150 $9.000
ASPH (AC-20-5TR)
GAL 1,500.000 $6.000 $4.770 $5.400 $7.500
AGGR(TY-PB GR-4 SAC-B)
CY 35.000 $200.000 $873.500 $355.000 $175.000
D-GR HMA(SQ) TY-B PG70-28
TON 1,176.000 $175.000 $129.050 $160.000 $160.000
STONE-MTRX-ASPH SMA-D SAC-A PG70-28
TON 417.000 $220.000 $243.420 $290.000 $180.000
PLANE ASPH CONC PAV (4" TO 7")
SY 3,520.000 $5.000 $4.560 $5.600 $7.000
CONC PVMT (CONT REINF - CRCP) (10")
SY 690.450 $120.000 $159.040 $185.000 $200.000
CURB (TYPE II)
LF 357.200 $10.000 $49.200 $26.000 $25.000
CEM STABIL BKFL
CY 49.300 $300.000 $216.400 $230.000 $400.000
RIPRAP (CONC)(4 IN)
CY 0.700 $1,000.000 $16,662.540 $3,900.000 $3,000.000
RC PIPE (CL III)(24 IN)
LF 264.000 $80.000 $167.890 $110.000 $150.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 4.000 $1,500.000 $5,201.750 $3,300.000 $10,000.000
MOBILIZATION
LS 1.000 $60,000.000 $75,800.000 $76,365.190 $64,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $8,000.000 $2,763.070 $8,700.000 $9,000.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 100.000 $25.000 $70.300 $65.500 $50.000
CONSTRUCTION EXITS (REMOVE)
SY 100.000 $10.000 $36.290 $26.000 $40.000
SANDBAGS FOR EROSION CONTROL
EA 60.000 $10.000 $51.830 $15.500 $5.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $600.000 $1,146.770 $1,300.000 $500.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 8.000 $500.000 $1,109.770 $1,200.000 $375.000
INSTL DEL ASSM (D-SW)SZ 1(FLX)GND(BI)
EA 4.000 $60.000 $184.960 $175.000 $60.000
INSTL OM ASSM (OM-2Z)(FLX)GND(BI)
EA 4.000 $60.000 $184.960 $175.000 $60.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 6.000 $20.000 $147.970 $19.500 $15.000
REFL PAV MRK TY I (Y)24"(SLD)(100MIL)
LF 45.000 $2.000 $26.630 $23.500 $18.000
PAVEMENT SEALER 4"
LF 302.000 $2.000 $0.190 $0.170 $0.130
PAVEMENT SEALER 24"
LF 45.000 $2.000 $1.110 $0.980 $0.750
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 1,904.000 $1.000 $2.220 $1.950 $1.500
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 2,550.000 $1.000 $2.220 $1.950 $1.500
PREFAB PAV MRK TY B (W)(24")(SLD)
LF 89.000 $20.000 $59.930 $53.000 $40.500
PAV SURF PREP FOR MRK (4")
LF 302.000 $0.400 $1.110 $0.980 $0.750
PAV SURF PREP FOR MRK (24")
LF 134.000 $0.400 $4.590 $4.050 $3.100
FULL - WIDTH MOWING
AC 2.090 $1,000.000 $1,350.540 $195.000 $250.000
LITTER REMOVAL
AC 1.050 $100.000 $2,445.120 $52.500 $540.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 60.000 $100.000 $110.980 $165.000 $100.000
Totals: $628,878.900 $746,928.502 $765,282.515 $770,289.660