Job Info for 0045-09-109

County: LAMAR Highway: US 82 Date: 04/05/2024 (7 months ago) Engineer's Estimate: $3,775,100 Control Number: 0045-09-109
Project: F 2024(937) District: PARIS Time: 72 WORKING DAYS Type: PREVENTIVE MAINTENANCE
Bidder's List
Informational:
Email All | Notice | Questions
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $3,775,099.95
RICHARD DRAKE CONSTRUCTION COMPANY, L.P.   $4,740,741.02 1
25.58% | $965,641.07
RK HALL, LLC   $5,821,318.47 2
54.2% | $2,046,218.52
22.79% | $1,080,577.45
FNH CONSTRUCTION, LLC   $6,053,711.00 3
60.36% | $2,278,611.05
27.7% | $1,312,969.98
3.99% | $232,392.53

Bid Items

Items: 34, 0 filtered
LAMAR US 82  |  PARIS  |  0045-09-109  |  04/05/2024  |  $3,775,100  |  F 2024(937)  |  PREVENT MAINT  |  72 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate RICHARD DRAKE CONSTRUCTION COMPANY, L.P. RK HALL, LLC FNH CONSTRUCTION, LLC
134 6001 BACKFILL (TY A) STA 298.000 $150.000 $310.000 $328.520 $650.000
164 6013 STRAW/HAY MLCH SEED(PERM)(RURAL)(SANDY) SY 9,941.000 $0.500 $0.650 $0.640 $2.000
168 6001 VEGETATIVE WATERING MG 89.000 $30.000 $72.000 $172.990 $50.000
314 6010 EMULS ASPH (EROSN CONT)(SS-1) GAL 2,486.000 $4.600 $6.750 $5.360 $10.000
351 6006 FLEXIBLE PAVEMENT STRUCTURE REPAIR(10") SY 404.000 $80.000 $168.600 $169.590 $150.000
354 6001 PLAN & TEXT ASPH CONC PAV(0" TO 1") SY 1,898.000 $2.500 $21.800 $11.890 $20.000
354 6002 PLAN & TEXT ASPH CONC PAV(0" TO 2") SY 251.000 $3.000 $23.600 $43.770 $20.000
354 6043 PLANE ASPH CONC PAV (1") SY 4,970.000 $2.500 $10.930 $4.430 $20.000
361 6044 FULL - DEPTH REPAIR CPJR (9") SY 85.000 $225.000 $170.300 $605.010 $500.000
500 6001 MOBILIZATION LS 1.000 $342,736.360 $249,545.000 $174,639.550 $550,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 5.000 $5,000.000 $29,800.000 $23,188.030 $15,000.000
506 6040 BIODEG EROSN CONT LOGS (INSTL) (8") LF 50.000 $6.000 $18.000 $18.720 $18.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 50.000 $3.000 $4.000 $4.680 $9.000
530 6002 INTERSECTIONS (ACP) SY 1,831.000 $45.000 $31.100 $30.570 $55.000
533 6003 RUMBLE STRIPS (SHOULDER) ASPHALT LF 29,822.000 $0.300 $0.300 $0.170 $1.000
662 6109 WK ZN PAV MRK SHT TERM (TAB)TY W EA 15,061.000 $2.000 $1.900 $2.730 $6.000
662 6111 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 EA 14,418.000 $2.000 $1.900 $2.730 $6.000
666 6035 REFL PAV MRK TY I (W)8"(SLD)(090MIL) LF 1,264.000 $2.370 $1.230 $1.170 $6.000
666 6053 REFL PAV MRK TY I (W)(ARROW)(090MIL) EA 51.000 $6.000 $183.000 $201.240 $250.000
666 6077 REFL PAV MRK TY I (W)(WORD)(090MIL) EA 4.000 $0.700 $257.000 $241.020 $250.000
666 6101 REF PAV MRK TY I(W)36"(YLD TRI)(090MIL) EA 37.000 $25.000 $97.000 $88.920 $250.000
666 6182 REFL PAV MRK TY II (W) 24" (SLD) LF 505.000 $0.270 $5.570 $3.800 $20.000
666 6305 RE PM W/RET REQ TY I (W)6"(BRK)(090MIL) LF 14,395.000 $0.900 $0.700 $0.700 $1.000
666 6308 RE PM W/RET REQ TY I (W)6"(SLD)(090MIL) LF 115,158.000 $0.750 $0.630 $0.700 $0.750
666 6317 RE PM W/RET REQ TY I (Y)6"(BRK)(090MIL) LF 28,794.000 $0.750 $0.800 $0.700 $1.000
666 6320 RE PM W/RET REQ TY I (Y)6"(SLD)(090MIL) LF 115,158.000 $0.750 $0.630 $0.700 $0.750
672 6007 REFL PAV MRKR TY I-C EA 808.000 $4.700 $6.000 $5.850 $6.000
672 6009 REFL PAV MRKR TY II-A-A EA 3,068.000 $4.250 $5.500 $5.850 $6.000
3081 6001 TOM PG76-22 TON 14,808.000 $152.000 $202.100 $279.520 $250.000
3085 6001 UNDERSEAL COURSE GAL 80,764.000 $4.800 $6.980 $6.550 $6.000
5092 6001 FILLING MILLED ASPHALT RUMBLE STRIPS LF 29,822.000 $7.000 $3.100 $3.850 $4.000
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 2.000 $10,752.380 $12,500.000 $15,450.260 $16,500.000
6185 6002 TMA (STATIONARY) DAY 25.000 $137.500 $425.000 $607.860 $250.000
6185 6003 TMA (MOBILE OPERATION) HR 120.000 $190.000 $85.000 $153.860 $55.000
Totals: $3,775,099.95 $4,740,741.02 $5,821,318.47 $6,053,711.00