LA SALLE FM 469 (0852-02-013)

Items: 74

County: LA SALLE
Length: N/A
Highway: FM 469
District: LAREDO
Control Number: 0852-02-013
DBE Goal: 0.0%
Project: C 852-2-13
Guaranty: N/A
Time: 580 WORKING DAYS
Engineer's Estimate: $14,758,445.79
Date: 08/02/2024 (1 year ago)
Contract Number: N/A
Type: REHABILITATE EXISTING ROADWAY
Mail/Deliver Bids To: N/A
CYNTHIA GARCIA
ANGEL MARTINEZ
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$14,758,445.79
$12,342,227.72
Over/Under Est: -16.37% -$2,416,218.07
Over/Under Est: -16.33% -$2,409,964.55
Amt Left: 0.05% $6,253.52
$12,825,010.32
Over/Under Est: -13.1% -$1,933,435.47
Amt Left: 3.91% $482,782.60
Delta: -3.86% -$476,529.08
Over/Under Est: -6.51% -$961,387.26
Amt Left: 11.79% $1,454,830.81
Delta: -7.58% -$972,048.21
$13,999,639.30
Over/Under Est: -5.14% -$758,806.49
Amt Left: 13.43% $1,657,411.58
Delta: -1.47% -$202,580.77
Subcontractor Percentage Amount
ANDERSON COLUMBIA CO., INC. 58.10% $7,270,853.94
ACEE CONSTRUCTION LLC. 3.87% $484,306.45
HIGHWAY BARRICADES AND SERVICES, LLC 1.09% $136,406.73
4E TREE WORX LLC 0.58% $72,583.40
MURRAY CONSTRUCTION 0.47% $58,817.58
AVILA AND SON'S L.L.C. 0.12% $15,017.25
Total: 64.23% $8,037,985.35

Bid Items & Bid Tabulations

74 Total 0 of 74
LA SALLE  |  FM 469  |  LAREDO  |  0852-02-013  |  08/02/2024  |  $14,758,445.79  |  C 852-2-13  |  REHAB EXIST ROADWAY  |  580 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
J. CARROLL WEAVER, INC.
ANDERSON COLUMBIA CO., INC.
HUNTER INDUSTRIES, LTD.
TEXAS MATERIALS GROUP, INC.
CK NEWBERRY, LLC
PREPARING ROW
STA 325.000 $600.000 $133.200 $400.000 $661.400 $300.000 $500.000
REMOVING CONC (DRIVEWAYS)
SY 86.000 $45.000 $29.520 $30.000 $29.300 $25.000 $50.000
EXCAVATION (ROADWAY)
CY 34,649.000 $15.000 $13.170 $3.500 $10.500 $27.000 $10.000
SUBGRADE WIDENING (ORD COMP)
STA 325.000 $600.000 $265.280 $1,000.000 $388.500 $960.000 $225.000
EMBANKMENT (FINAL)(ORD COMP)(TY A)
CY 10,939.000 $35.000 $5.410 $22.000 $10.600 $28.000 $11.000
DRILL SEEDING (PERM) (RURAL) (SANDY)
AC 22.400 $700.000 $888.000 $1,351.540 $1,315.320 $1,202.000 $1,200.000
CEMENT
TON 2,196.000 $262.000 $215.180 $200.000 $209.000 $209.000 $200.000
CEMENT TREAT (EXIST MATL) (10")
SY 133,025.000 $4.000 $1.750 $2.760 $2.600 $2.700 $2.250
ASPHALT STAB BASE (GR 1)(PG 64)
TON 44,674.000 $115.000 $119.870 $108.000 $96.400 $97.400 $95.000
PRIME COAT (RC-250)
GAL 24,120.000 $5.000 $4.890 $5.200 $5.240 $4.570 $5.000
AGGR(TY-PB GR-5 SAC-A)
CY 862.000 $145.000 $208.590 $220.000 $160.020 $240.000 $200.000
CEM STABIL BKFL
CY 315.000 $190.000 $126.530 $150.000 $470.170 $197.000 $200.000
TEMPORARY SPL SHORING
SF 665.000 $27.500 $13.320 $20.000 $4.680 $58.000 $25.000
RIPRAP (CONC) (CL B) (4")
CY 26.000 $300.000 $1,332.000 $525.000 $850.000 $985.000 $800.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 28.000 $240.000 $333.000 $200.000 $215.000 $275.000 $300.000
RIPRAP (MOW STRIP)(4 IN)
CY 42.000 $770.000 $777.000 $525.000 $825.000 $840.000 $800.000
RAIL (TY T631)
LF 80.000 $112.000 $94.350 $120.000 $112.500 $105.000 $125.000
CONC BOX CULV (5 FT X 2 FT)
LF 666.000 $653.000 $488.520 $500.000 $600.000 $565.000 $725.000
CONC BOX CULV (8 FT X 3 FT)
LF 68.000 $755.000 $1,173.750 $1,000.000 $1,100.000 $913.000 $1,325.000
RC PIPE (CL III)(24 IN)
LF 30.000 $250.000 $88.520 $94.000 $160.000 $141.000 $225.000
RC PIPE (ARCH)(CL IV)(DES 3)
LF 233.000 $430.000 $225.250 $274.000 $350.000 $302.000 $325.000
RC PIPE (ARCH)(CL IV)(DES 1)
LF 182.000 $296.000 $200.600 $234.000 $250.000 $222.000 $350.000
WINGWALL (PW - 1) (HW=4 FT)
EA 2.000 $15,000.000 $15,540.000 $16,000.000 $18,000.000 $23,800.000 $25,000.000
SET (TY I)(S= 5 FT)(HW= 3 FT)(4:1) (C)
EA 28.000 $5,500.000 $11,655.000 $5,500.000 $5,800.000 $8,900.000 $12,500.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 2.000 $1,690.000 $3,885.000 $2,000.000 $4,800.000 $2,950.000 $4,000.000
SET (TY II) (DES 1) (RCP) (6: 1) (P)
EA 2.000 $2,300.000 $2,775.000 $2,000.000 $3,800.000 $3,450.000 $4,500.000
SET (TY II) (DES 3) (RCP) (4: 1) (C)
EA 10.000 $2,600.000 $3,330.000 $2,800.000 $4,600.000 $4,850.000 $5,000.000
REMOV STR (SET)
EA 38.000 $590.000 $423.080 $150.000 $750.000 $640.000 $1,500.000
REMOV STR (PIPE)
EA 22.000 $280.000 $461.540 $300.000 $1,250.000 $1,200.000 $1,500.000
MOBILIZATION
LS 1.000 $1,341,326.890 $566,000.000 $750,000.000 $1,144,404.550 $1,375,000.000 $1,300,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 29.000 $4,500.000 $1,665.000 $1,500.000 $4,802.840 $9,700.000 $19,500.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 265.000 $71.000 $72.150 $74.000 $100.870 $93.000 $95.000
ROCK FILTER DAMS (REMOVE)
LF 265.000 $30.000 $27.750 $38.000 $12.720 $15.000 $12.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,210.000 $5.200 $4.440 $3.500 $4.890 $4.500 $4.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,210.000 $2.730 $0.560 $2.000 $1.050 $2.000 $1.000
CONSTRUCTING DETOURS
SY 16,247.000 $90.000 $33.910 $41.000 $41.400 $42.000 $65.000
ONE-WAY TRAF CONT (FLAGGER CONT)
HR 960.000 $89.000 $85.770 $78.000 $96.000 $70.000 $150.000
ONE-WAY TRAFFIC CONTROL (PORT TRAF SIG)
DAY 600.000 $185.000 $149.850 $200.000 $492.130 $25.000 $250.000
PTB (FRN&INSTL)(SGL SLP)(TY 1) OR (STL)
LF 450.000 $73.000 $36.450 $23.000 $85.000 $38.000 $100.000
PTB (MOVE)(SGL SLP)(TY 1) OR (STL)
LF 8,550.000 $6.500 $13.710 $13.000 $52.000 $22.000 $30.000
PTB (REMOVE)(SGL SLP)(TY 1) OR (STL)
LF 450.000 $14.000 $36.450 $11.000 $50.000 $33.000 $50.000
INTERSECTIONS (SURF TREAT)
SY 1,048.000 $50.000 $9.660 $100.000 $48.300 $63.000 $85.000
DRIVEWAYS (CONC)
SY 135.000 $120.000 $138.750 $140.000 $120.000 $175.000 $125.000
DRIVEWAYS (SURF TREAT)
SY 2,200.000 $45.000 $9.650 $100.000 $48.300 $61.000 $95.000
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 64,970.000 $0.130 $0.220 $0.150 $0.150 $0.110 $0.150
RUMBLE STRIPS (CENTERLINE) ASPHALT
LF 32,485.000 $0.130 $0.220 $0.150 $0.160 $0.110 $0.150
MTL W-BEAM GD FEN (TIM POST)
LF 625.000 $28.000 $27.750 $25.000 $23.300 $28.250 $30.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $4,150.000 $3,219.000 $3,600.000 $3,400.000 $3,100.000 $3,100.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 30.000 $1,370.000 $1,665.000 $800.000 $900.000 $1,100.000 $600.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $911.000 $555.000 $900.000 $875.000 $725.000 $700.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $9,000.000 $8,325.000 $7,400.000 $8,125.000 $8,000.000 $9,500.000
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 4.000 $375.000 $199.800 $370.000 $180.000 $350.000 $200.000
MAILBOX INSTALL-M (TWW-POST) TY 4
EA 4.000 $650.000 $666.000 $630.000 $600.000 $590.000 $600.000
TEMP RD IL (RD IL ASM)
MO 29.000 $3,360.000 $3,330.000 $1,100.000 $762.840 $1,800.000 $3,000.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 76.000 $695.000 $638.250 $650.000 $575.000 $615.000 $575.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 1.000 $1,100.000 $1,054.500 $910.000 $800.000 $855.000 $800.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 1.000 $1,200.000 $1,054.500 $950.000 $950.000 $895.000 $950.000
REMOVE SM RD SN SUP&AM
EA 80.000 $81.000 $88.800 $75.000 $100.000 $70.000 $100.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 10.000 $47.300 $49.950 $38.000 $45.000 $35.000 $40.000
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
EA 20.000 $75.000 $88.800 $155.000 $80.000 $145.000 $80.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 3,243.000 $1.700 $1.110 $2.000 $1.690 $1.750 $1.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 24.000 $8.120 $55.500 $53.000 $50.000 $50.000 $17.000
PAVEMENT SEALER 6"
LF 217,908.000 $0.340 $0.240 $0.250 $0.220 $0.220 $0.250
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 64,987.000 $0.680 $0.730 $0.700 $0.660 $0.660 $0.700
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 4,174.000 $0.850 $0.980 $1.000 $0.880 $0.880 $0.700
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 39,793.000 $0.680 $0.730 $0.700 $0.660 $0.660 $0.700
REFL PAV MRKR TY II-A-A
EA 707.000 $2.850 $5.550 $6.000 $5.000 $5.000 $5.000
STRIP MOWING
CYC 3.000 $3,100.000 $5,550.000 $2,300.000 $4,880.000 $2,500.000 $5,000.000
FULL - WIDTH MOWING
CYC 3.000 $3,500.000 $7,770.000 $2,500.000 $6,710.000 $3,800.000 $6,500.000
D-GR HMA TY-C SAC-A PG76-22
TON 13,508.000 $130.000 $156.910 $140.000 $127.300 $145.000 $145.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $12,175.000 $6,105.000 $30,000.000 $10,000.000 $18,000.000 $25,000.000
TMSP RADAR SPEED CONTROL MONITOR
EA 2.000 $11,000.000 $12,210.000 $11,000.000 $12,000.000 $10,875.000 $15,000.000
TMA (STATIONARY)
DAY 510.000 $276.000 $72.150 $188.000 $350.000 $200.000 $300.000
TMA (MOBILE OPERATION)
HR 920.000 $80.000 $16.650 $66.000 $95.000 $80.000 $25.000
Totals: $14,758,445.790 $12,342,227.720 $12,348,481.246 $12,825,010.328 $13,797,058.530 $13,999,639.300