Job Info for 0538-01-027

County: KNOX Highway: FM 267 Date: 04/04/2023 (1 year ago) Engineer's Estimate: $6,289,656 Control Number: 0538-01-027
Project: STP 2023(580)HES District: CHILDRESS Time: 177 WORKING DAYS Type: WIDENING
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14
Plans: Plans | Revision | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $6,289,655.79
A. L. HELMCAMP, INC.   $6,913,833.35 1
9.92% | $624,177.56
DUININCK, INC.   $6,995,621.63 2
11.22% | $705,965.84
1.18% | $81,788.28
Subcontractor Percentage Amount
W. S. CONSTRUCTION COMPANY 5.35% $369,890.08
LINEAR TRAFFIC MARKINGS LLC 1.24% $85,731.53
DUSTIN ALLEN, INC. 0.59% $40,791.62
CONTRACTORS SERVICE, LTD. 0.48% $33,186.40
WOLFE CONSTRUCTION GROUP, INCORPORATED 0.42% $29,038.10
WEST TEXAS ROCK RESOURCES, LLC 0.24% $16,593.20
Total: 8.32% $575,230.93

Bid Items

Items: 53, 0 filtered
KNOX FM 267  |  CHILDRESS  |  0538-01-027  |  04/04/2023  |  $6,289,656  |  STP 2023(580)HES  |  WIDENING  |  177 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate A. L. HELMCAMP, INC. DUININCK, INC.
104 6017 REMOVING CONC (DRIVEWAYS) SY 43.000 $200.000 $33.000 $71.000
104 6054 REMOVING CONCRETE(MOW STRIP) LF 600.000 $10.000 $11.000 $20.500
110 6002 EXCAVATION (CHANNEL) CY 522.000 $35.000 $22.000 $25.500
110 6004 EXCAVATION (ROADWAY AND CHANNEL) CY 2,335.000 $20.000 $43.400 $26.500
112 6002 SUBGRADE WIDENING (DENS CONT) STA 507.000 $700.000 $227.000 $450.000
132 6002 EMBANKMENT (FINAL)(DENS CONT)(TY A) CY 59.000 $75.000 $282.000 $54.500
132 6007 EMBANKMENT (FINAL)(ORD COMP)(TY D) CY 4,626.000 $35.000 $47.600 $31.000
134 6004 BACKFILL (TY A OR B) STA 555.000 $175.000 $93.000 $175.000
164 6034 DRILL SEEDING (PERM) (RURAL) (SANDY) AC 27.000 $500.000 $495.000 $485.000
164 6053 DRILL SEEDING (TEMP)(WARM OR COOL) AC 27.000 $500.000 $510.000 $495.000
168 6001 VEGETATIVE WATERING MG 1,053.000 $12.000 $2.000 $28.500
314 6013 EMULS ASPH (EROSN CONT)(CSS-1H) GAL 25,259.000 $1.500 $4.500 $3.850
354 6021 PLANE ASPH CONC PAV(0" TO 2") SY 3,225.000 $4.000 $25.000 $7.850
401 6001 FLOWABLE BACKFILL CY 65.000 $250.000 $275.000 $270.000
432 6035 RIPRAP (STONE PROTECTION)(24 IN) CY 15.000 $150.000 $248.000 $270.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 30.000 $750.000 $830.000 $805.000
460 6001 CMP (GAL STL 12 IN) LF 189.000 $90.000 $83.000 $64.500
460 6011 CMP AR (GAL STL DES 4) LF 53.000 $110.000 $253.000 $190.000
460 6012 CMP AR (GAL STL DES 5) LF 78.000 $150.000 $358.000 $215.000
464 6007 RC PIPE (CL III)(30 IN) LF 23.000 $175.000 $275.000 $190.000
464 6008 RC PIPE (CL III)(36 IN) LF 44.000 $200.000 $330.000 $240.000
464 6010 RC PIPE (CL III)(48 IN) LF 54.000 $215.000 $550.000 $375.000
466 6099 HEADWALL (CH - PW - 0) (DIA= 30 IN) EA 2.000 $8,000.000 $7,200.000 $10,500.000
466 6101 HEADWALL (CH - PW - 0) (DIA= 36 IN) EA 2.000 $4,500.000 $15,400.000 $12,500.000
466 6103 HEADWALL (CH - PW - 0) (DIA= 48 IN) EA 4.000 $4,000.000 $23,100.000 $13,500.000
466 6111 HEADWALL (CH - PW - A - 0) (DES= 4) EA 4.000 $7,000.000 $9,350.000 $10,500.000
466 6112 HEADWALL (CH - PW - A - 0) (DES= 5) EA 2.000 $7,500.000 $16,500.000 $12,000.000
467 6557 SET (TY II) (DES 5) (CMP) (4: 1) (C) EA 2.000 $1,500.000 $5,000.000 $8,600.000
480 6001 CLEAN EXIST CULVERTS EA 8.000 $3,500.000 $2,200.000 $2,700.000
500 6001 MOBILIZATION LS 1.000 $564,192.440 $500,000.000 $695,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 11.000 $7,500.000 $9,300.000 $18,500.000
506 6042 BIODEG EROSN CONT LOGS (INSTL) (18") LF 1,000.000 $15.000 $5.500 $5.300
530 6002 INTERSECTIONS (ACP) SY 3,113.000 $35.000 $80.000 $36.500
533 6001 RUMBLE STRIPS (SHOULDER) LF 113,566.000 $0.250 $0.190 $0.090
533 6004 RUMBLE STRIPS (CENTERLINE) ASPHALT LF 56,783.000 $0.250 $0.270 $0.130
540 6002 MTL W-BEAM GD FEN (STEEL POST) LF 400.000 $35.000 $33.000 $36.000
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 4.000 $2,500.000 $2,500.000 $2,900.000
540 6037 MTL BM GD FEN TRANS (ANCHOR PLATE) EA 4.000 $750.000 $1,100.000 $645.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 400.000 $25.000 $4.400 $3.200
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 4.000 $3,500.000 $3,400.000 $3,600.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 4.000 $500.000 $440.000 $320.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 15.000 $250.000 $46.200 $37.500
666 6048 REFL PAV MRK TY I (W)24"(SLD)(100MIL) LF 60.000 $15.000 $14.300 $14.000
666 6309 RE PM W/RET REQ TY I (W)6"(SLD)(100MIL) LF 113,566.000 $0.350 $0.650 $0.620
666 6318 RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL) LF 14,196.000 $1.750 $0.650 $0.630
666 6321 RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL) LF 9,750.000 $2.250 $0.650 $0.640
672 6009 REFL PAV MRKR TY II-A-A EA 1,420.000 $3.500 $3.800 $3.750
3076 6009 D-GR HMA TY-B PG70-28 TON 10,388.000 $145.000 $160.000 $190.000
3076 6045 D-GR HMA TY-D SAC-A PG70-28 TON 19,134.000 $140.000 $155.000 $140.300
3076 6066 TACK COAT GAL 14,143.000 $6.000 $5.500 $4.300
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 2.000 $8,500.000 $10,000.000 $8,000.000
6185 6002 TMA (STATIONARY) DAY 69.000 $500.000 $200.000 $270.000
6185 6003 TMA (MOBILE OPERATION) HR 27.000 $95.000 $75.000 $105.000
Totals: $6,289,655.79 $6,913,833.35 $6,995,621.63