Job Info for 0916-02-021

County: KLEBERG Highway: CR Date: 04/05/2023 (1 year ago) Engineer's Estimate: $1,495,012 Control Number: 0916-02-021
Project: BR 2023(040) District: CORPUS CHRISTI Time: 138 WORKING DAYS Type: BRIDGE REPLACEMENT
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $1,495,011.75
CROSS PLUS CONSTRUCTION, LLC   $1,830,905.05 1
22.47% | $335,893.30
LISKA CONSTRUCTION COMPANY, INC.   $1,919,892.82 2
28.42% | $424,881.07
4.86% | $88,987.77
FOREMOST PAVING, INC.   $2,762,823.87 3
84.8% | $1,267,812.12
50.9% | $931,918.82
43.91% | $842,931.05
Subcontractor Percentage Amount
LONE STAR EROSION CONTROL 7.86% $143,909.14
CARTHAGE DRILLING, LLC 5.53% $101,249.05
BATTEN DRILLING, INC. 5.40% $98,868.87
AWP SAFETY 2.95% $54,011.70
IVY ROD, INC. 0.95% $17,393.60
DCC CONSTRUCTION AND SERVICES, L.L.C. 0.54% $9,886.89
HOUSTON SAWING & DRILLING 0.51% $9,337.62
Total: 23.74% $434,656.87

Bid Items

Items: 66, 0 filtered
KLEBERG CR  |  CORPUS CHRISTI  |  0916-02-021  |  04/05/2023  |  $1,495,012  |  BR 2023(040)  |  BRIDGE REPL  |  138 WORKING DAYS
Alt Item code Description Unit Quantity Engineer's Estimate CROSS PLUS CONSTRUCTION, LLC LISKA CONSTRUCTION COMPANY, INC. FOREMOST PAVING, INC.
100 6002 PREPARING ROW STA 9.000 $2,500.000 $1,100.000 $1,110.000 $20,000.000
110 6001 EXCAVATION (ROADWAY) CY 313.000 $12.000 $33.000 $21.000 $45.000
132 6004 EMBANKMENT (FINAL)(DENS CONT)(TY B) CY 347.000 $25.000 $55.000 $20.000 $65.000
164 6001 BROADCAST SEED (PERM) (RURAL) (SANDY) SY 1,042.000 $2.000 $2.200 $3.000 $1.000
164 6009 BROADCAST SEED (TEMP) (WARM) SY 570.000 $1.000 $2.200 $1.000 $1.000
164 6011 BROADCAST SEED (TEMP) (COOL) SY 570.000 $1.000 $2.200 $1.000 $1.000
168 6001 VEGETATIVE WATERING MG 19.000 $90.000 $110.000 $200.000 $225.000
169 6002 SOIL RETENTION BLANKETS (CL 1) (TY B) SY 1,140.000 $1.250 $11.000 $3.000 $2.000
247 6391 FL BS (RDWY DEL)(TY A GR 5) TON 427.000 $20.000 $0.000 $0.000 $0.000
275 6031 CEMENT TREAT (NEW BASE) (10") SY 845.000 $20.000 $0.000 $0.000 $0.000
310 6009 PRIME COAT (MC-30) GAL 140.000 $12.000 $5.500 $57.000 $25.000
316 6001 ASPH (MULTI OPTION) GAL 627.000 $4.400 $11.000 $18.000 $35.000
316 6002 AGGR (MULTI OPTION) CY 12.000 $220.530 $550.000 $1,720.000 $150.000
400 6005 CEM STABIL BKFL CY 148.000 $170.000 $165.000 $220.000 $200.000
403 6006 TEMPORARY SPL SHORING (COFFERDAM) SF 1,168.000 $62.000 $27.500 $79.000 $0.010
416 6001 DRILL SHAFT (18 IN) LF 140.000 $600.000 $253.000 $245.000 $200.000
416 6004 DRILL SHAFT (36 IN) LF 280.000 $550.000 $308.000 $455.000 $220.000
420 6014 CL C CONC (ABUT)(HPC) CY 61.800 $1,350.000 $1,100.000 $1,560.000 $2,000.000
422 6001 REINF CONC SLAB SF 2,600.000 $25.000 $33.000 $37.000 $30.000
422 6015 APPROACH SLAB CY 59.700 $730.000 $1,100.000 $665.000 $1,000.000
423 6003 RETAINING WALL (TEMP WALL) SF 1,041.000 $75.000 $55.000 $36.000 $0.010
425 6037 PRESTR CONC GIRDER (TX40) LF 397.170 $180.000 $275.000 $246.000 $250.000
432 6002 RIPRAP (CONC)(5 IN) CY 20.000 $640.000 $165.000 $595.000 $800.000
432 6032 RIPRAP (STONE PROTECTION)(15 IN) CY 484.000 $210.000 $165.000 $200.000 $220.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 37.000 $625.000 $550.000 $587.000 $1,200.000
450 6007 RAIL (TY T223)(HPC) LF 288.000 $155.000 $275.000 $180.000 $200.000
454 6021 TYPE A JOINT LF 70.000 $70.000 $440.000 $40.000 $20.000
464 6003 RC PIPE (CL III)(18 IN) LF 34.000 $140.000 $550.000 $135.000 $115.000
464 6008 RC PIPE (CL III)(36 IN) LF 54.000 $280.000 $550.000 $550.000 $230.000
467 6363 SET (TY II) (18 IN) (RCP) (6: 1) (P) EA 2.000 $1,800.000 $3,300.000 $2,300.000 $1,400.000
496 6009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) EA 1.000 $30,000.000 $27,500.000 $61,600.000 $120,000.000
496 6016 REMOV STR (PIPE) EA 3.000 $1,500.000 $1.100 $500.000 $2,000.000
500 6001 MOBILIZATION LS 1.000 $135,910.160 $260,000.000 $227,000.000 $250,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 9.000 $5,300.000 $4,400.000 $1,500.000 $5,000.000
506 6002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 45.000 $45.000 $110.000 $70.000 $75.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 45.000 $15.000 $11.000 $20.000 $40.000
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 67.000 $29.000 $82.500 $70.000 $85.000
506 6024 CONSTRUCTION EXITS (REMOVE) SY 67.000 $8.000 $1.100 $20.000 $35.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 1,115.000 $4.500 $16.500 $5.500 $5.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 1,115.000 $1.400 $1.100 $1.000 $2.000
506 6042 BIODEG EROSN CONT LOGS (INSTL) (18") LF 30.000 $7.000 $55.000 $10.000 $12.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 30.000 $2.300 $1.100 $5.000 $7.000
508 6001 CONSTRUCTING DETOURS SY 882.000 $110.000 $82.500 $396.000 $1,172.000
510 6003 ONE-WAY TRAF CONT (PORT TRAF SIG) MO 9.000 $4,700.000 $4,400.000 $7,000.000 $6,000.000
512 6009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) LF 540.000 $60.000 $220.000 $92.000 $70.000
512 6010 PORT CTB (FUR & INST)(LOW PROF)(TY 2) LF 80.000 $60.000 $220.000 $36.000 $70.000
512 6033 PORT CTB (MOVE)(LOW PROF)(TY 1) LF 460.000 $12.000 $55.000 $19.000 $10.000
512 6034 PORT CTB (MOVE)(LOW PROF)(TY 2) LF 40.000 $12.000 $55.000 $37.000 $10.000
512 6057 PORT CTB (REMOVE)(LOW PROF)(TY 1) LF 540.000 $26.000 $110.000 $25.000 $30.000
512 6058 PORT CTB (REMOVE)(LOW PROF)(TY 2) LF 80.000 $26.000 $55.000 $35.000 $30.000
530 6006 DRIVEWAYS (SURF TREAT) SY 37.000 $43.000 $330.000 $90.000 $450.000
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 325.000 $38.000 $44.000 $29.000 $35.000
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 3.000 $2,500.000 $3,300.000 $2,500.000 $2,000.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 3.000 $3,800.000 $4,400.000 $3,500.000 $3,500.000
545 6012 CRASH CUSH ATTEN (INSTL)(R)(N)(TL2) EA 1.000 $17,500.000 $38,500.000 $22,000.000 $26,000.000
560 6007 MAILBOX INSTALL-S (WC-POST) TY 3 EA 1.000 $250.000 $220.000 $500.000 $1,500.000
644 6076 REMOVE SM RD SN SUP&AM EA 2.000 $150.000 $220.000 $75.000 $225.000
658 6014 INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) EA 4.000 $35.000 $33.000 $40.000 $40.000
658 6060 REMOVE DELIN & OBJECT MARKER ASSMS EA 4.000 $25.000 $1.100 $25.000 $30.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 7.000 $50.000 $11.000 $40.000 $45.000
662 6016 WK ZN PAV MRK NON-REMOV (W)24"(SLD) LF 40.000 $10.000 $11.000 $38.500 $50.000
740 6005 ANTI - GRAFFITI COATNG(PERMNENT-TY III) SF 2,424.000 $2.000 $5.500 $12.000 $1.800
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 540.000 $75.000 $165.000 $55.000 $65.000
6185 6002 TMA (STATIONARY) DAY 30.000 $230.000 $275.000 $130.000 $200.000
6185 6003 TMA (MOBILE OPERATION) HR 8.000 $68.000 $550.000 $125.000 $0.010
1 247 6041 FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS) CY 193.000 $131.810 $110.000 $182.000 $350.000
Totals: $1,520,451.75 $1,830,905.05 $1,919,892.82 $2,762,823.87