KLEBERG US 77 (0102-04-099)

Items: 211

County: KLEBERG
Length: N/A
Highway: US 77
District: CORPUS CHRISTI
Control Number: 0102-04-099
DBE Goal: N/A
Project: NH 2020(871)
Guaranty: N/A
Time: 660 WORKING DAYS
Engineer's Estimate: $48,109,866.82
Date: 05/08/2020 (6 years ago)
Contract Number: N/A
Type: CONSTRUCT MAINLANES, FRONTAGE ROADS AND STRUCTURES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$48,109,866.82
1
Awarded
$55,237,175.26
Over/Under Est: 14.81% $7,127,308.44
Over/Under Est: 32.42% $15,597,946.06
Amt Left: 15.34% $8,470,637.62
Over/Under Est: 35.11% $16,889,859.39
Amt Left: 17.67% $9,762,550.95
Delta: -2.03% -$1,291,913.33
Over/Under Est: 51.95% $24,994,246.74
Amt Left: 32.35% $17,866,938.30
Delta: -12.47% -$8,104,387.35
Subcontractor Percentage Amount
A. H. BECK FOUNDATION CO., INC. 4.06% $2,345,441.94
THE LEVY COMPANY, INC. 3.52% $2,033,486.61
TEXAS ICON CONSTRUCTION, LLC 1.61% $930,089.05
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. 1.61% $930,089.05
LIGHT IT UP ELECTRIC 1.58% $912,758.20
JB PINNACLE GROUP, LLC 1.19% $687,457.12
HIGHWAY BARRICADES AND SERVICES, LLC 1.03% $595,025.91
PERFORMANCE EQUIPMENT SERVICE 0.53% $306,178.38
ELITE CONSTRUCTION & CONSULTANTS LLC 0.38% $219,524.12
LONE STAR EROSION CONTROL 0.37% $213,747.17
TEXAS STEEL INDUSTRIAL PLACING, LLC 0.31% $179,085.47
DEPENDABLE FENCE 0.23% $132,869.86
CAMACHO DEMOLITION, LLC 0.15% $86,654.26
GREGORY PILE DRIVING, INC. 0.12% $69,323.41
MARTIN MARIETTA MATERIALS, INC. 0.10% $57,769.51
ADVANCED PUMPING, LLC 0.06% $34,661.70
PRIMATE CONSTRUCTION, LP 0.04% $23,107.80
HIGHWAY PAVEMENT SPECIALTIES, INC. 0.04% $23,107.80
D & C CONCRETE CUTTING, INC. 0.02% $11,553.90
BREDA COMPANY, INC. 0.00% $0.00
WEBER-BALKE FOUNDATION COMPANY, INC 0.00% $0.00
Total: 16.95% $9,791,931.26

Bid Items & Bid Tabulations

211 Total 0 of 211
KLEBERG  |  US 77  |  CORPUS CHRISTI  |  0102-04-099  |  05/08/2020  |  $48,109,866.82  |  NH 2020(871)  |  CONSTRUCT MAINLANES, FRONTAGE ROADS...  |  660 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BAY LTD.
ANDERSON COLUMBIA CO., INC.
ZACHRY CONSTRUCTION CORPORATION
HAAS-ANDERSON CONSTRUCTION, LTD.
PREPARING ROW
STA 226.000 $2,000.000 $7,600.000 $5,000.000 $27,654.870 $5,000.000
REMOVING CONC (PAV)
SY 1,166.000 $4.700 $13.250 $20.000 $9.810 $18.000
REMOVING CONC (RIPRAP)
SY 2,110.000 $11.000 $13.750 $9.000 $3.730 $11.000
REMOVING CONC (DRIVEWAYS)
SY 1,210.000 $10.000 $21.000 $11.000 $3.640 $13.000
REMOVING CONC (CURB)
LF 425.000 $4.300 $11.500 $8.000 $5.850 $4.950
REMOVING CONCRETE(MOW STRIP)
LF 6,626.000 $8.500 $14.750 $10.000 $2.100 $3.450
REMOVING STAB BASE & ASPH PAV(12"-27")
SY 76,945.000 $3.000 $7.800 $6.000 $25.000 $8.900
OBLITERATING ABANDONED ROAD
SY 11,411.000 $3.000 $3.600 $3.000 $6.320 $8.900
EXCAVATION (ROADWAY)
CY 151,703.000 $6.000 $7.000 $4.400 $3.440 $7.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 485,360.000 $7.000 $5.000 $8.400 $7.300 $6.000
EMBANKMENT (FINAL)(DC)(TY C)(RWAL FND)
CY 8,671.000 $70.000 $8.700 $12.500 $22.140 $23.000
BACKFILL (TY A OR B)
STA 148.000 $135.000 $450.000 $90.000 $462.690 $164.000
FURNISHING AND PLACING TOPSOIL (4")
SY 425,920.000 $0.800 $0.290 $0.700 $0.920 $0.900
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 423,547.000 $0.100 $0.150 $0.150 $0.130 $0.200
DRILL SEED (TEMP)(WARM OR COOL)
SY 427,585.000 $0.100 $0.140 $0.140 $0.080 $0.100
FERTILIZER
TON 33.000 $560.000 $690.000 $1,100.000 $450.000 $1,120.000
VEGETATIVE WATERING
MG 15,663.000 $12.500 $21.000 $26.000 $20.160 $37.000
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 82,298.000 $60.000 $66.000 $75.000 $65.880 $84.000
LIME (HYDRATED LIME (SLURRY))
TON 5,589.000 $180.000 $190.000 $170.000 $179.250 $164.000
LIME TRT (SUBGRADE)(8")
SY 282,252.000 $2.000 $1.950 $3.700 $2.200 $5.000
CEMENT
TON 2,858.000 $150.000 $190.000 $158.000 $176.940 $193.000
CEMENT TREAT (NEW BASE) (10")
SY 167,160.000 $3.000 $1.300 $4.000 $1.920 $2.150
CEMENT TREAT (NEW BASE)(12")
SY 107,555.000 $3.500 $1.300 $4.500 $1.920 $2.250
PRIME COAT (MC-30)
GAL 52,831.000 $4.000 $3.700 $5.000 $3.250 $4.700
ASPH (MULTI OPTION)
GAL 113,755.000 $3.000 $2.500 $5.000 $2.100 $3.050
AGGR(TY-PB GR-4S OR TY-PB GR-4)(SAC-B)
CY 2,956.000 $85.000 $140.000 $120.000 $125.170 $163.000
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
TON 17,916.000 $100.000 $130.000 $120.000 $114.000 $175.000
FLEX PAVEMENT STRUCTURE REPAIR (8"-15")
SY 3,719.000 $115.000 $78.000 $114.000 $15.250 $64.000
PLAN & TEXT ASPH CONC PAV(0" TO 2")
SY 1,688.000 $2.500 $4.000 $10.000 $3.500 $3.050
PLAN & TEXT ASPH CONC PAV(0" TO 3")
SY 67,001.000 $3.000 $2.200 $2.000 $1.240 $2.050
STRUCT EXCAV
CY 4,653.000 $10.000 $9.100 $9.000 $6.970 $7.450
CEM STABIL BKFL
CY 4,017.400 $50.000 $62.000 $90.000 $95.000 $51.000
CEMENT STAB BACKFILL (INLET OR MH)
CY 184.000 $75.000 $68.000 $50.000 $95.000 $51.000
TRENCH EXCAVATION PROTECTION
LF 1,492.000 $2.000 $7.900 $6.000 $7.000 $6.900
TEMPORARY SPL SHORING
SF 16,767.000 $12.000 $15.000 $30.000 $15.000 $17.000
DRILL SHAFT (18 IN)
LF 982.000 $70.000 $140.000 $170.000 $67.140 $75.000
DRILL SHAFT (24 IN)
LF 784.000 $140.000 $150.000 $150.000 $75.190 $94.000
DRILL SHAFT (36 IN)
LF 5,826.000 $170.000 $190.000 $200.000 $180.600 $207.000
DRILL SHAFT (42 IN)
LF 54.000 $235.000 $290.000 $670.000 $242.000 $311.000
DRILL SHAFT (48 IN)
LF 3,165.000 $400.000 $290.000 $290.000 $308.660 $369.000
DRILL SHAFT (54 IN)
LF 1,593.000 $430.000 $370.000 $374.000 $385.240 $471.000
DRILL SHAFT (SIGN MTS) (24 IN)
LF 328.000 $178.000 $280.000 $240.000 $215.000 $267.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 410.000 $220.000 $300.000 $280.000 $142.000 $176.000
CL C CONC (ABUT)
CY 451.900 $750.000 $920.000 $900.000 $1,030.920 $953.000
CL C CONC (BENT)
CY 186.100 $1,000.000 $1,100.000 $2,000.000 $1,093.680 $953.000
CL C CONC (CAP)
CY 593.100 $1,000.000 $990.000 $960.000 $1,172.400 $953.000
CL C CONC (COLUMN)
CY 419.700 $745.000 $820.000 $1,080.000 $1,234.030 $953.000
CL C CONC (RAIL FOUNDATION)
CY 367.000 $500.000 $630.000 $400.000 $558.340 $631.000
REINF CONC SLAB
SF 135,238.000 $17.000 $17.000 $18.000 $18.100 $23.000
REINF CONC SLAB (HPC)
SF 1,607.360 $19.000 $27.000 $66.000 $25.000 $123.000
APPROACH SLAB
CY 491.400 $515.000 $540.000 $550.000 $493.630 $664.000
RETAINING WALL (MSE)
SF 138,959.000 $28.000 $59.000 $64.000 $65.520 $83.000
PRESTR CONC GIRDER (TX34)
LF 3,039.000 $130.000 $160.000 $138.000 $135.070 $219.000
PRESTR CONC GIRDER (TX46)
LF 14,200.380 $120.000 $150.000 $144.000 $158.300 $173.000
PNEUMATICALLY PLACED CONCRETE (2")
SF 5,844.000 $9.000 $11.250 $14.000 $8.270 $19.000
RIPRAP (CONC)(4 IN)
CY 371.500 $380.000 $485.000 $465.000 $389.740 $606.000
RIPRAP (CONC)(5 IN)
CY 444.000 $400.000 $490.000 $465.000 $372.280 $568.000
RIPRAP (CONC)(CL B)
CY 14.350 $550.000 $590.000 $450.000 $767.130 $1,240.000
RIPRAP (CONC)(CL B)(RR8&RR9)
CY 437.000 $470.000 $410.000 $475.000 $367.820 $541.000
RIPRAP (MOW STRIP)(4 IN)
CY 1,332.000 $460.000 $500.000 $465.000 $349.240 $603.000
RAIL (TY T223)
LF 6,819.500 $85.000 $84.000 $135.000 $111.950 $113.000
RAIL (TY T552)
LF 963.000 $71.000 $120.000 $75.000 $90.050 $114.000
RAIL (TY SSTR)
LF 10,314.200 $30.000 $85.000 $52.000 $36.940 $70.000
RETROFIT RAIL (TY T552)
LF 832.000 $240.000 $140.000 $127.000 $130.860 $199.000
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 993.060 $75.000 $99.000 $110.000 $121.030 $144.000
CONC BOX CULV (3 FT X 2 FT)
LF 616.000 $180.000 $170.000 $153.000 $136.760 $248.000
CONC BOX CULV (4 FT X 2 FT)
LF 80.000 $200.000 $170.000 $193.000 $169.740 $255.000
CONC BOX CULV (5 FT X 2 FT)
LF 924.000 $235.000 $190.000 $254.000 $225.190 $297.000
CONC BOX CULV (5 FT X 4 FT)
LF 229.000 $260.000 $220.000 $304.000 $269.430 $424.000
CONC BOX CULV (6 FT X 5 FT)
LF 313.000 $450.000 $390.000 $324.000 $361.530 $505.000
CONC BOX CULV (6 FT X 2 FT)
LF 423.000 $425.000 $220.000 $413.000 $278.210 $381.000
RC PIPE (CL III)(24 IN)
LF 4,600.000 $68.000 $98.000 $52.000 $53.300 $85.000
RC PIPE (CL III)(36 IN)
LF 322.000 $120.000 $84.000 $95.000 $85.380 $138.000
MANH (COMPL)(PRM)(48IN)
EA 3.000 $2,500.000 $7,200.000 $3,650.000 $2,466.980 $5,560.000
INLET (COMPL)(PSL)(RC)(4FTX4FT)
EA 2.000 $3,800.000 $5,500.000 $3,250.000 $3,425.460 $6,220.000
INLET (COMPL)(PSL)(RC)(8FTX8FT)
EA 3.000 $9,600.000 $8,000.000 $7,450.000 $10,793.720 $18,700.000
INLET (COMPL)(PSL)(FG)(3FTX3FT-3FTX3FT)
EA 1.000 $3,990.000 $4,300.000 $2,900.000 $3,097.870 $4,680.000
INLET (COMPL)(PSL)(FG)(4FTX4FT-4FTX4FT)
EA 1.000 $5,000.000 $5,500.000 $3,650.000 $4,616.490 $6,610.000
INLET (COMPL)(PSL)(FG)(8FTX8FT-3FTX3FT)
EA 9.000 $7,890.000 $7,100.000 $8,500.000 $11,836.090 $16,600.000
INLET (COMPL)(TY MSE1)
EA 10.000 $3,200.000 $5,200.000 $3,300.000 $4,080.930 $6,520.000
WINGWALL (PW - 1) (HW=3 FT)
EA 2.000 $7,700.000 $11,200.000 $8,500.000 $21,189.610 $12,100.000
WINGWALL (PW - 1) (HW=4 FT)
EA 3.000 $12,250.000 $15,800.000 $9,400.000 $22,491.440 $14,000.000
WINGWALL (PW - 1) (HW=6 FT)
EA 1.000 $13,000.000 $25,400.000 $11,900.000 $29,852.860 $18,900.000
WINGWALL (PW - 1) (HW=7 FT)
EA 2.000 $16,500.000 $31,300.000 $13,500.000 $35,693.000 $30,500.000
SET (TY I)(S=3 FT)(HW=3FT)(4:1)(C)
EA 7.000 $5,500.000 $5,400.000 $4,500.000 $8,022.860 $7,710.000
SET (TY I)(S=3 FT)(HW= 3 FT)(6:1)(P)
EA 4.000 $6,417.000 $5,600.000 $5,500.000 $8,468.260 $8,560.000
SET (TY I)(S= 4 FT)(HW= 3 FT)(4:1) (C)
EA 1.000 $8,750.000 $5,500.000 $5,200.000 $8,288.940 $7,850.000
SET (TY I)(S= 5 FT)(HW= 3 FT)(4:1) (C)
EA 3.000 $12,700.000 $5,700.000 $5,750.000 $8,736.050 $8,140.000
SET (TY I)(S= 5 FT)(HW= 4 FT)(4:1) (P)
EA 2.000 $12,700.000 $6,000.000 $7,300.000 $9,549.180 $6,790.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 16.000 $1,300.000 $2,300.000 $1,400.000 $1,325.810 $1,680.000
SET (TY II) (24 IN) (RCP) (4: 1) (P)
EA 23.000 $1,300.000 $2,600.000 $1,400.000 $1,352.840 $1,440.000
SET (TY II) (24 IN) (RCP) (6: 1) (C)
EA 1.000 $1,150.000 $7,300.000 $1,500.000 $1,416.460 $1,910.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 28.000 $2,630.000 $4,000.000 $1,650.000 $1,247.380 $1,910.000
SET (TY II) (36 IN) (RCP) (4: 1) (C)
EA 2.000 $3,700.000 $5,400.000 $4,000.000 $2,085.210 $3,650.000
SET (TY II) (36 IN) (RCP) (6: 1) (P)
EA 4.000 $4,000.000 $6,100.000 $5,350.000 $3,013.120 $6,530.000
REMOV STR (SET)
EA 71.000 $650.000 $730.000 $550.000 $155.120 $198.000
REMOV STR (PIPE)
LF 2,063.000 $18.000 $31.000 $11.000 $14.040 $5.800
REMOV STR (BOX CULVERT)
LF 803.000 $40.000 $56.000 $32.000 $45.480 $64.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 2.000 $70,000.000 $49,300.000 $77,000.000 $49,218.000 $184,000.000
REMOVE STR (RAIL)
LF 832.000 $13.000 $48.000 $42.000 $5.690 $11.000
MOBILIZATION
LS 1.000 $3,116,428.110 $1,100,000.000 $6,070,000.000 $6,005,000.000 $7,185,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 42.000 $8,000.000 $20,000.000 $10,000.000 $8,953.960 $20,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 696.000 $28.000 $36.000 $28.000 $27.000 $35.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 613.000 $50.000 $61.000 $44.000 $55.000 $62.000
ROCK FILTER DAMS (REMOVE)
LF 1,309.000 $8.000 $17.250 $13.000 $9.000 $12.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 390.000 $18.000 $26.000 $28.000 $15.000 $29.000
CONSTRUCTION EXITS (REMOVE)
SY 390.000 $6.000 $11.250 $13.200 $2.000 $9.250
TEMP SEDMT CONT FENCE (INSTALL)
LF 7,628.000 $2.500 $4.700 $2.600 $2.150 $4.100
TEMP SEDMT CONT FENCE (REMOVE)
LF 7,628.000 $0.900 $1.150 $1.100 $0.850 $1.100
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 1,341.000 $6.300 $6.900 $90.000 $4.750 $6.300
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,341.000 $1.000 $1.150 $1.100 $1.250 $1.450
CONSTRUCTING DETOURS
SY 21,955.000 $35.000 $55.000 $56.000 $59.870 $73.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 15,510.000 $34.000 $36.000 $30.000 $29.470 $34.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 25,290.000 $5.000 $7.100 $12.000 $3.580 $12.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 15,510.000 $7.000 $12.500 $18.000 $8.110 $15.000
CONC CURB (TY II)
LF 4,459.000 $11.000 $15.250 $21.000 $9.270 $17.000
CONC CURB (MOUNTABLE)
LF 278.000 $8.200 $24.000 $25.000 $10.100 $17.000
DRIVEWAYS (CONC)
SY 422.000 $74.000 $81.000 $65.000 $66.470 $95.000
DRIVEWAYS (ACP)
SY 561.000 $55.000 $68.000 $85.000 $58.350 $80.000
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 56,311.000 $0.150 $2.300 $0.400 $0.100 $0.250
MTL W-BEAM GD FEN (TIM POST)
LF 1,074.000 $20.000 $35.000 $23.000 $23.000 $26.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,850.000 $2,900.000 $2,200.000 $1,900.000 $1,830.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 3.000 $1,400.000 $2,900.000 $1,140.000 $1,350.000 $1,280.000
REMOVE METAL BEAM GUARD FENCE
LF 1,975.000 $2.500 $11.250 $160.000 $2.000 $1.850
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 9.000 $280.000 $1,700.000 $190.000 $275.000 $213.000
CABLE BARRIER SYSTEM (TL-4) (10'-0")
LF 15,937.000 $11.000 $10.500 $10.000 $8.380 $11.000
CABLE BARRIER TERMINAL SECTION (TL-4)
EA 8.000 $2,800.000 $1,700.000 $2,860.000 $2,863.310 $3,220.000
REMOVE CABLE BARRIER
LF 6,227.000 $3.500 $5.700 $2.000 $3.710 $2.250
REMOVE CABLE BARRIER TERMINAL SECTION
EA 8.000 $1,600.000 $1,200.000 $510.000 $445.400 $573.000
GUARDRAIL END TREATMENT (INSTALL)
EA 7.000 $2,500.000 $3,500.000 $3,000.000 $2,800.000 $3,350.000
GUARDRAIL END TREATMENT (REMOVE)
EA 9.000 $200.000 $1,700.000 $410.000 $280.000 $462.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 36.000 $1,300.000 $3,500.000 $3,150.000 $1,350.000 $2,140.000
CRASH CUSH ATTEN (REMOVE)
EA 19.000 $920.000 $2,300.000 $1,090.000 $850.000 $1,430.000
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
EA 20.000 $14,000.000 $8,800.000 $23,900.000 $24,389.000 $26,000.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 19.000 $14,000.000 $8,600.000 $11,180.000 $8,070.000 $10,200.000
WIRE FENCE (TY C)
LF 1,515.000 $10.000 $23.000 $22.000 $9.220 $25.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 2.000 $200.000 $570.000 $192.000 $180.500 $217.000
REMOVE RD IL ASM (TRANS-BASE)
EA 21.000 $675.000 $370.000 $530.000 $300.000 $372.000
IN RD IL (U/P) (TY 2) (250W EQ) LED
EA 16.000 $2,300.000 $990.000 $2,090.000 $975.000 $1,210.000
IN RD IL (TY SA) 50T-8 (400W EQ) LED
EA 41.000 $3,827.000 $4,300.000 $4,070.000 $3,150.000 $3,910.000
CONDT (PVC) (SCH 40) (2")
LF 9,560.000 $7.500 $6.400 $11.000 $5.900 $7.300
CONDT (PVC) (SCH 40) (3")
LF 36,870.000 $15.000 $7.500 $21.000 $6.250 $7.750
CONDT (PVC) (SCH 80) (2") (BORE)
LF 1,700.000 $34.350 $16.250 $55.000 $13.600 $17.000
CONDT (PVC) (SCH 80) (3") (BORE)
LF 1,630.000 $37.000 $21.000 $40.000 $14.150 $18.000
CONDT (RM) (1")
LF 650.000 $41.700 $24.000 $38.000 $13.350 $17.000
CONDT (RM) (3")
LF 1,560.000 $62.000 $44.000 $58.000 $70.340 $87.000
ELEC CONDR (NO.8) INSULATED
LF 43,376.000 $1.000 $1.750 $1.500 $0.970 $1.200
ELEC CONDR (NO.6) BARE
LF 605.000 $1.400 $1.800 $2.000 $1.100 $1.350
ELEC CONDR (NO.6) INSULATED
LF 1,210.000 $1.600 $2.000 $2.000 $1.180 $1.450
GROUND BOX TY A (122311)W/APRON
EA 44.000 $900.000 $950.000 $1,100.000 $625.000 $775.000
REMOVE GROUND BOX
EA 13.000 $239.000 $120.000 $165.000 $175.000 $217.000
REMOVE ELECTRICAL SERVICES
EA 4.000 $890.000 $480.000 $450.000 $650.000 $806.000
ELC SRV TY A 240/480 060(SS)SS(E)GC(O)
EA 7.000 $5,900.000 $6,300.000 $9,900.000 $7,735.000 $9,590.000
ELC SRV TY D 120/240 060(NS)SS(N)GC(O)
EA 2.000 $6,636.000 $7,100.000 $7,800.000 $6,625.000 $8,210.000
ALUMINUM SIGNS (TY A)
SF 2,736.000 $23.000 $29.000 $27.000 $20.500 $25.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 42.000 $475.000 $550.000 $530.000 $485.000 $601.000
IN SM RD SN SUP&AM TYS80(1)SA(P-BM)
EA 10.000 $622.000 $860.000 $825.000 $750.000 $930.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 96.000 $550.000 $720.000 $690.000 $625.000 $775.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 23.000 $650.000 $950.000 $910.000 $825.000 $1,020.000
IN SM RD SN SUP&AM TYS80(2)SA(P)
EA 3.000 $864.000 $1,200.000 $1,150.000 $1,050.000 $1,300.000
IN SM RD SN SUP&AM TYS80(2)SA(P-EXAL)
EA 5.000 $1,650.000 $1,800.000 $1,680.000 $1,525.000 $1,890.000
IN BRIDGE MNT CLEARANCE SGN ASSM(TY N)
EA 4.000 $1,706.000 $2,200.000 $2,100.000 $1,600.000 $1,980.000
IN SM RD SN SUP&AM (RAIL MOUNT)
EA 9.000 $2,948.000 $5,400.000 $5,170.000 $4,700.000 $5,830.000
REMOVE SM RD SN SUP&AM
EA 141.000 $78.000 $63.000 $60.000 $55.000 $68.000
INSTALL LRSS (STRUCT STEEL)
LB 15,140.000 $5.300 $4.000 $3.750 $3.850 $4.750
REMOVE LRSA
EA 9.000 $1,218.000 $810.000 $780.000 $950.000 $1,180.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 163.000 $25.000 $17.250 $16.000 $15.000 $19.000
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
EA 67.000 $14.000 $17.250 $16.000 $15.000 $19.000
INSTL DEL ASSM (D-DW)SZ 1(FLX)SRF
EA 30.000 $120.000 $86.000 $82.000 $75.000 $93.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 18.000 $63.000 $51.000 $50.000 $45.000 $56.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 11.000 $20.000 $26.000 $24.000 $22.000 $27.000
INSTL DEL ASSM (D-DY)SZ 1(BRF)GF2
EA 15.000 $24.000 $26.000 $24.000 $22.000 $27.000
WK ZN PAV MRK NON-REMOV (W)(ENTR GORE)
EA 1.000 $325.000 $1,400.000 $1,320.000 $1,200.000 $1,490.000
WK ZN PAV MRK NON-REMOV (W)(EXIT GORE)
EA 1.000 $285.000 $1,400.000 $1,320.000 $1,200.000 $1,490.000
WK ZN PAV MRK REMOV (W)4"(BRK)
LF 11,320.000 $0.590 $0.700 $0.650 $0.600 $0.750
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 65,102.000 $0.600 $0.650 $0.600 $0.550 $0.700
WK ZN PAV MRK REMOV (W)8"(SLD)
LF 3,196.000 $1.350 $1.450 $1.400 $1.250 $1.550
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 322.000 $12.700 $11.250 $11.000 $10.000 $12.000
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 61,565.000 $0.600 $0.650 $0.600 $0.550 $0.700
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 1,110.000 $1.000 $1.150 $1.500 $1.340 $1.300
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 383.000 $0.900 $1.150 $1.500 $1.030 $1.300
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 13,380.000 $2.500 $1.000 $1.000 $0.850 $1.050
RE PM W/RET REQ TY I (W)4"(BRK)(090MIL)
LF 16,580.000 $3.000 $0.480 $0.450 $0.420 $0.500
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 82,230.000 $0.330 $0.450 $0.450 $0.400 $0.500
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 78,275.000 $0.330 $0.450 $0.450 $0.400 $0.500
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 362.000 $12.000 $17.250 $16.000 $15.000 $19.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 4.000 $200.000 $230.000 $215.000 $195.000 $242.000
PREFAB PAV MRK TY C (W) (DBL ARROW)
EA 10.000 $350.000 $330.000 $315.000 $285.000 $353.000
PREFAB PAV MRK TY C (W) (UTURN ARROW)
EA 4.000 $380.000 $410.000 $385.000 $350.000 $434.000
PREFAB PAV MRK TY C (W) (WORD)
EA 4.000 $250.000 $290.000 $270.000 $250.000 $310.000
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
EA 168.000 $30.000 $29.000 $27.000 $25.000 $31.000
REFL PAV MRKR TY II-A-A
EA 441.000 $4.000 $4.600 $4.400 $4.000 $4.950
REFL PAV MRKR TY II-C-R
EA 3,787.000 $3.390 $4.100 $3.850 $3.500 $4.350
ELIM EXT PAV MRK & MRKS (4")
LF 25,028.000 $0.800 $1.250 $0.550 $0.360 $1.350
ELIM EXT PAV MRK & MRKS (8")
LF 1,280.000 $0.650 $1.250 $0.750 $0.870 $1.350
ELIM EXT PAV MRK & MRKS (24")
LF 64.000 $1.400 $7.700 $3.300 $3.060 $2.000
FULL - WIDTH MOWING
AC 530.000 $175.000 $58.000 $113.000 $170.750 $76.000
TREE AND BRUSH REMOVAL
AC 4.550 $11,200.000 $6,200.000 $3,700.000 $1,967.450 $20,000.000
DITCH CLEANING AND RESHAPING (FOOT)
LF 3,609.000 $12.500 $15.250 $4.500 $2.830 $3.200
D-GR HMA TY-B SAC-B PG70-22
TON 27,712.000 $66.000 $94.000 $72.000 $84.110 $112.000
D-GR HMA TY-D SAC-B PG70-22
TON 25,700.000 $75.000 $99.000 $81.000 $90.660 $119.000
TACK COAT
GAL 58,253.000 $3.280 $3.800 $3.650 $3.300 $3.900
GEOGRID REINFORCE EMBANKMENTS (TY A)
SY 17,341.000 $3.000 $1.950 $2.000 $1.930 $1.700
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 660.000 $65.000 $220.000 $70.000 $157.450 $74.000
FIBER OPTIC CABLE ROAD MARKER
EA 41.000 $100.000 $170.000 $250.000 $160.000 $198.000
CCTV FIELD EQUIPMENT (DIGITAL)
EA 2.000 $7,105.000 $12,500.000 $11,990.000 $12,000.000 $14,900.000
ITS POLE (55 FT)(130 MPH)
EA 2.000 $12,000.000 $17,700.000 $19,400.000 $12,332.000 $15,300.000
ITS POLE MNT CAB (TY 1)(CONF 1)
EA 2.000 $4,703.000 $6,700.000 $8,360.000 $5,920.000 $7,340.000
TMA (STATIONARY)
DAY 205.000 $130.000 $250.000 $175.000 $230.600 $201.000
TMA (MOBILE OPERATION)
DAY 80.000 $350.000 $550.000 $230.000 $230.600 $10.000
ITS GND BOX(PCAST) TY 1 (243636)W/APRN
EA 41.000 $3,629.000 $3,100.000 $4,500.000 $3,270.000 $4,050.000
Totals: $48,109,866.820 $55,237,175.260 $63,707,812.880 $64,999,726.261 $73,104,113.560