KIMBLE PR 73 (0474-01-005)

Items: 71

County: KIMBLE
Length: N/A
Highway: PR 73
District: SAN ANGELO
Control Number: 0474-01-005
DBE Goal: N/A
Project: C 474-1-5
Guaranty: N/A
Time: 150 WORKING DAYS
Engineer's Estimate: $2,705,633.45
Date: 08/04/2021 (4 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (5)
E
Engineer's Estimate
$2,705,633.45
1
$2,649,387.40
Over/Under Est: -2.08% -$56,246.05
Over/Under Est: 13.4% $362,434.99
Amt Left: 15.8% $418,681.04
Over/Under Est: 28.71% $776,840.55
Amt Left: 31.44% $833,086.60
Delta: -13.51% -$414,405.56
Over/Under Est: 28.95% $783,295.23
Amt Left: 31.69% $839,541.28
Delta: -0.19% -$6,454.68
Over/Under Est: 43.35% $1,172,981.61
Amt Left: 46.4% $1,229,227.66
Delta: -11.17% -$389,686.38
Subcontractor Percentage Amount
TEXAS SHAFTS, INC. 5.28% $145,012.86
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. 1.87% $51,358.72
DIIBS SPECIALISTS, LLC 1.07% $29,387.08
FLASHER EQUIPMENT COMPANY 0.53% $14,556.21
Total: 8.75% $240,314.87

Bid Items & Bid Tabulations

71 Total 0 of 71
KIMBLE  |  PR 73  |  SAN ANGELO  |  0474-01-005  |  08/04/2021  |  $2,705,633.45  |  C 474-1-5  |  BRIDGE REPL  |  150 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RELMCO, INC.
ACME BRIDGE COMPANY, INC.
DELGADO'S CONTRACTORS, LLC
PGC GENERAL CONTRACTORS, LLC
INTEGRITY SERVICES, LLC
PREPARING ROW
STA 11.000 $1,000.000 $6,000.000 $3,140.000 $2,000.000 $4,141.510 $1,200.000
REMOVING CONC (PAV)
SY 1,681.000 $10.000 $10.000 $12.400 $24.000 $19.330 $15.250
REMOVING CONC (RIPRAP)
SY 1,098.000 $15.000 $10.000 $10.500 $9.000 $17.950 $11.000
REMOVING CONC (CURB)
LF 1,212.000 $10.000 $8.000 $12.500 $5.000 $1.380 $15.500
REM STAB BASE & ASPH (6"-12")
SY 1,192.000 $10.000 $6.500 $9.700 $7.000 $5.520 $8.900
EXCAVATION (ROADWAY)
CY 142.000 $15.000 $20.000 $30.000 $10.000 $41.420 $20.000
EXCAVATION (CHANNEL)
CY 556.000 $20.000 $18.000 $20.100 $10.000 $41.420 $25.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 8,137.000 $10.000 $23.000 $21.100 $42.000 $50.000 $20.000
FURNISHING AND PLACING TOPSOIL (4")
SY 5,534.000 $2.000 $4.000 $2.600 $7.000 $5.520 $4.500
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 5,534.000 $1.000 $0.470 $0.460 $1.000 $0.590 $0.480
BROADCAST SEED (TEMP) (WARM)
SY 2,767.000 $0.500 $0.470 $0.790 $1.000 $1.040 $0.840
BROADCAST SEED (TEMP) (COOL)
SY 2,767.000 $0.500 $0.470 $0.800 $1.000 $1.050 $0.850
PROOF ROLLING
HR 3.000 $100.000 $150.000 $63.900 $150.000 $110.440 $125.000
LRA PAV TY-I GR-C
TON 571.000 $105.000 $105.000 $107.000 $150.000 $207.080 $125.000
CONC PVMT (CONT REINF - CRCP) (7")
SY 2,714.000 $95.000 $92.230 $109.000 $110.000 $118.030 $90.000
CEM STABIL BKFL
CY 96.300 $150.000 $165.000 $125.000 $165.000 $117.340 $230.000
TEMPORARY SPL SHORING
SF 1,063.000 $20.000 $20.000 $35.000 $15.500 $15.190 $35.000
DRILL SHAFT (36 IN)
LF 404.000 $250.000 $435.000 $332.000 $325.000 $295.200 $542.700
CL C CONC (ABUT)
CY 45.300 $1,200.000 $1,052.180 $1,000.000 $1,100.000 $984.310 $1,200.000
CL C CONC (CAP)
CY 31.400 $1,400.000 $1,164.410 $1,200.000 $1,100.000 $1,097.090 $1,250.000
CL C CONC (COLUMN)
CY 29.800 $1,400.000 $1,096.200 $1,200.000 $1,100.000 $981.370 $1,250.000
REINF CONC SLAB
SF 7,820.000 $35.000 $19.110 $26.000 $25.000 $28.930 $25.000
APPROACH SLAB
CY 72.800 $450.000 $784.000 $602.000 $1,000.000 $737.040 $650.000
PRESTR CONC GIRDER (TX40)
LF 913.920 $150.000 $165.000 $240.000 $200.000 $235.340 $234.250
RIPRAP (STONE PROTECTION)(18 IN)
CY 439.000 $125.000 $108.440 $149.000 $135.000 $138.050 $150.000
RIPRAP (STONE PROTECTION) (36 IN)
CY 4,380.000 $175.000 $88.840 $142.000 $185.000 $124.250 $220.000
RIPRAP (MOW STRIP)(6 IN)
CY 39.000 $350.000 $616.000 $750.000 $600.000 $613.090 $550.000
RAIL (TY C66)
LF 500.000 $150.000 $110.000 $219.000 $100.000 $260.830 $158.000
ARMOR JOINT
LF 62.000 $75.000 $134.400 $121.000 $180.000 $107.580 $125.000
REMOV STR (BOX CULVERT)
EA 1.000 $15,000.000 $18,000.000 $12,000.000 $12,500.000 $27,517.580 $23,100.000
REMOV STR (WINGWALL)
EA 2.000 $3,000.000 $5,000.000 $2,000.000 $2,500.000 $2,070.760 $2,500.000
REMOV STR (SMALL FENCE)
LF 62.000 $10.000 $100.000 $5.000 $100.000 $6.900 $15.000
MOBILIZATION
LS 1.000 $135,000.000 $250,000.000 $235,000.000 $200,000.000 $255,000.000 $405,310.300
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $8,000.000 $4,000.000 $2,290.000 $2,500.000 $948.120 $1,500.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 175.000 $30.000 $31.420 $30.200 $125.000 $39.430 $31.990
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 160.000 $60.000 $100.730 $96.900 $125.000 $126.410 $102.560
ROCK FILTER DAMS (REMOVE)
LF 335.000 $10.000 $17.050 $16.400 $20.000 $21.400 $17.360
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 224.000 $30.000 $29.440 $28.300 $60.000 $36.930 $29.960
CONSTRUCTION EXITS (REMOVE)
SY 224.000 $10.000 $7.980 $7.700 $15.000 $10.010 $8.120
TEMP SEDMT CONT FENCE (INSTALL)
LF 422.000 $3.000 $3.610 $3.450 $7.000 $4.530 $3.670
TEMP SEDMT CONT FENCE (REMOVE)
LF 422.000 $1.000 $1.290 $1.250 $1.000 $1.620 $1.310
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 2,077.000 $5.000 $4.630 $4.450 $8.000 $5.810 $4.720
BIODEG EROSN CONT LOGS (REMOVE)
LF 2,077.000 $1.000 $0.940 $0.900 $1.000 $1.170 $0.950
CONSTRUCTING DETOURS
SY 3,342.000 $50.000 $60.000 $95.400 $100.000 $100.780 $150.000
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
LF 1,780.000 $25.000 $25.000 $40.500 $65.000 $47.220 $79.360
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
LF 1,780.000 $6.000 $18.000 $6.800 $10.000 $25.990 $14.000
MTL W-BEAM GD FEN (STEEL POST)
LF 200.000 $30.000 $30.820 $42.600 $45.000 $55.570 $34.720
MTL BEAM GD FEN TRANS (TL2)
EA 2.000 $1,200.000 $2,420.000 $1,380.000 $1,500.000 $1,794.660 $1,568.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,320.000 $3,520.000 $1,590.000 $2,000.000 $2,070.760 $1,428.000
MTL BM GD FEN TRANS (NON - SYM)
EA 2.000 $775.000 $2,750.000 $1,060.000 $1,000.000 $1,380.500 $896.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $2,600.000 $3,520.000 $3,280.000 $3,250.000 $4,279.570 $3,360.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $900.000 $800.000 $185.000 $2,000.000 $241.590 $1,120.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL2)
EA 2.000 $6,500.000 $7,500.000 $9,520.000 $10,000.000 $12,424.540 $11,200.000
GATE (REMOVE)
EA 1.000 $300.000 $600.000 $529.000 $400.000 $552.200 $500.000
WIRE FENCE (TY C)
LF 62.000 $20.000 $25.000 $10.600 $20.000 $19.330 $22.500
GATE (TY 1)
EA 1.000 $1,500.000 $2,500.000 $1,060.000 $1,500.000 $1,656.600 $1,500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 14.000 $700.000 $641.300 $617.000 $700.000 $773.080 $980.000
IN SM RD SN SUP&AM TYFRP(1)UA(P)
EA 2.000 $600.000 $739.200 $711.000 $800.000 $897.330 $1,120.000
REMOVE SM RD SN SUP&AM
EA 14.000 $115.000 $101.200 $97.400 $102.000 $124.250 $112.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 10.000 $20.000 $26.400 $25.400 $30.000 $14.570 $16.800
INSTL OM ASSM (OM-2Y)(WC)GND
EA 4.000 $75.000 $97.900 $94.200 $100.000 $90.770 $50.400
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 5.000 $30.000 $30.800 $29.600 $32.000 $36.930 $28.000
INSTL OM ASSM (OM-3L)(WFLX)SRF)SRF
EA 2.000 $530.000 $247.500 $238.000 $250.000 $111.130 $550.000
INSTL OM ASSM (OM-3R)(WFLX)SRF)SRF
EA 2.000 $640.000 $247.500 $238.000 $250.000 $111.130 $550.000
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 4,807.000 $0.350 $0.830 $1.050 $1.000 $1.380 $1.120
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 4,865.000 $0.400 $0.830 $1.050 $1.000 $1.380 $1.120
REFL PAV MRKR TY II-A-A
EA 95.000 $4.000 $11.000 $5.300 $11.000 $6.900 $5.600
ELIM EXT PAV MRK & MRKS (4")
LF 394.000 $1.000 $11.000 $1.300 $11.000 $1.730 $1.400
PAV SURF PREP FOR MRK (4")
LF 4,916.000 $0.250 $0.550 $0.320 $1.000 $0.410 $0.340
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 300.000 $70.000 $200.000 $42.500 $125.000 $121.480 $52.500
TMA (MOBILE OPERATION)
DAY 2.000 $100.000 $350.000 $410.000 $750.000 $345.130 $975.000
Totals: $2,705,633.450 $2,649,387.408 $3,068,068.440 $3,482,474.000 $3,488,928.702 $3,878,615.060