Show Job Controls
Bid Cobra

KIMBLE IH 10 (0141-09-071)

Items: 18

County: KIMBLE
Length: N/A
Highway: IH 10
District: SAN ANGELO
Control Number: 0141-09-071
DBE Goal: N/A
Project: C 141-9-71
Guaranty: N/A
Time: 39 WORKING DAYS
Engineer's Estimate: $2,484,819.75
Date: 08/05/2020 (5 years ago)
Contract Number: N/A
Type: MEDIAN CABLE BARRIER
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$2,484,819.75
1
$2,752,521.00
Over/Under Est: 10.77% $267,701.25
Over/Under Est: 19.85% $493,250.31
Amt Left: 8.19% $225,549.06
$3,379,489.00
Over/Under Est: 36.01% $894,669.25
Amt Left: 22.78% $626,968.00
Delta: -13.48% -$401,418.94
$4,114,305.20
Over/Under Est: 65.58% $1,629,485.45
Amt Left: 49.47% $1,361,784.20
Delta: -21.74% -$734,816.20

Bid Items & Bid Tabulations

18 Total 0 of 18
KIMBLE  |  IH 10  |  SAN ANGELO  |  0141-09-071  |  08/05/2020  |  $2,484,819.75  |  C 141-9-71  |  MEDIAN CABLE BARRIER  |  39 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
MASSANA, INC.
SCR CIVIL CONSTRUCTION, LLC
FNH CONSTRUCTION, LLC
VANN/ELLI, INC.
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 72,187.000 $0.250 $0.300 $0.280 $0.500 $0.500
DRILL SEEDING (TEMP) (WARM)
SY 36,093.000 $0.250 $0.280 $0.200 $0.500 $0.400
DRILL SEEDING (TEMP) (COOL)
SY 36,093.000 $0.250 $0.280 $0.200 $0.500 $0.400
LRA PAV TY-I GR-A
TON 481.000 $150.000 $100.000 $410.000 $240.000 $250.000
RIPRAP (CONC)(CL B)
CY 3,208.500 $450.000 $425.000 $492.000 $650.000 $810.000
MOBILIZATION
LS 1.000 $134,000.000 $400,448.320 $146,000.000 $340,000.000 $300,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $5,000.000 $24,000.000 $16,000.000 $8,500.000 $25,000.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 222.000 $30.000 $35.000 $18.000 $30.000 $25.000
CONSTRUCTION EXITS (REMOVE)
SY 222.000 $12.000 $19.000 $8.350 $15.000 $15.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 2,220.000 $15.000 $8.000 $6.600 $18.000 $8.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 2,220.000 $2.500 $3.000 $0.950 $9.000 $1.000
CABLE BARRIER SYSTEM (TL-4)
LF 57,993.000 $8.500 $8.000 $10.800 $7.500 $11.100
CABLE BARRIER SYSTEM (TL-4) (10'-0")
LF 5,676.000 $12.000 $10.000 $15.900 $10.000 $13.750
CABLE BARRIER TERMINAL SECTION (TL-4)
EA 48.000 $2,750.000 $4,500.000 $3,800.000 $2,500.000 $2,800.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 7.000 $750.000 $1,000.000 $1,960.000 $850.000 $950.000
INSTL DEL ASSM (D-DY)SZ 1(BRF)GF2
EA 675.000 $35.000 $30.000 $25.000 $50.000 $58.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 39.000 $100.000 $350.000 $225.000 $150.000 $250.000
TMA (STATIONARY)
DAY 39.000 $250.000 $320.000 $325.000 $350.000 $375.000
Totals: $2,484,819.750 $2,752,521.000 $2,978,070.060 $3,379,489.000 $4,114,305.200