Show Job Controls
Bid Cobra

KIMBLE IH 10 (0141-09-070)

Items: 57

County: KIMBLE
Length: N/A
Highway: IH 10
District: SAN ANGELO
Control Number: 0141-09-070
DBE Goal: N/A
Project: C 141-9-70
Guaranty: N/A
Time: 145 WORKING DAYS
Engineer's Estimate: $8,434,547.67
Date: 06/06/2018 (7 years ago)
Contract Number: N/A
Type: HOT RECYCLE AND ACP OVERLAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$8,434,547.67
$8,342,120.02
Over/Under Est: -1.1% -$92,427.65
$9,051,810.36
Over/Under Est: 7.32% $617,262.69
Amt Left: 8.51% $709,690.34
Over/Under Est: 17.93% $1,512,346.21
Amt Left: 19.24% $1,604,773.86
Delta: -9.89% -$895,083.52

Bid Items & Bid Tabulations

57 Total 0 of 57
KIMBLE  |  IH 10  |  SAN ANGELO  |  0141-09-070  |  06/06/2018  |  $8,434,547.67  |  C 141-9-70  |  HOT RECYCLE AND ACP OVERLAY  |  145 WORKING DAYS
Alt
Item Code
Description
Unit
Quantity
Engineer's Estimate
LONE STAR PAVING COMPANY
ALLEN KELLER COMPANY
HUNTER INDUSTRIES, LTD.
BACKFILL (TY B)
STA 1,466.800 $40.000 $50.000 $25.000 $95.550
BLADING
HR 25.000 $100.000 $95.000 $110.000 $85.500
DRILL SEEDING (PERM) (RURAL) (CLAY)
AC 60.000 $575.000 $650.000 $510.000 $871.000
EMULS ASPH (EROSN CONT)(MULTI)
GAL 13,130.000 $2.500 $2.500 $5.500 $3.520
ASPH (AC-20XP)
GAL 225,490.000 $3.000 $3.000 $3.250 $3.470
AGGR(TY-PB GR-4 SAC-B)
CY 6,276.000 $70.000 $70.000 $65.000 $75.850
LRA PAV TY-I GR-D
TON 737.000 $100.000 $100.000 $95.000 $97.530
PFC (ASPHALT) A-R-BNDR
TON 3,639.000 $95.210 $0.000 $0.000 $0.000
PFC-C (AGGREGATE)(PG76 MIX) SAC-A
TON 39,033.000 $92.000 $0.000 $0.000 $0.000
SUPERPAVE MIXTURES SP-C SAC-B PG70-22
TON 16,446.000 $37.750 $0.000 $0.000 $0.000
SUPERPAVE MIXTURES SP-D SAC-B PG70-22
TON 5,726.000 $80.000 $100.000 $80.000 $91.470
PLANE ASPH CONC PAV(0" TO 2")
SY 2,620.000 $1.500 $1.000 $3.450 $1.490
PLANE ASPH CONC PAV(0" TO 3")
SY 5,068.000 $1.500 $1.000 $2.000 $1.490
PLANE ASPH CONC PAV(0" TO 4")
SY 20,268.000 $1.500 $1.000 $1.850 $1.650
PLANE CONC PAV(0" TO 1-1/2")
SY 20,268.000 $0.750 $1.000 $1.250 $1.490
PLANE ASPH CONC PAV (1.5")
SY 171,823.000 $1.000 $1.000 $1.000 $1.590
PLANE ASPH CONC PAV (2")
SY 13,679.000 $1.250 $1.000 $1.750 $1.700
PLANE ASPH CONC PAV (2")
SY 149,450.000 $1.250 $0.000 $0.000 $0.000
PLANE ASPH CONC PAV (3")
SY 2,044.000 $1.250 $1.500 $2.750 $2.330
PLANE ASPH CONC PAV (4")
SY 6,984.000 $2.000 $1.750 $2.500 $3.380
CLEANING EXISTING JOINTS
LF 4,186.660 $16.500 $7.000 $6.300 $9.000
HEADER TYPE EXPANSION JOINT
LF 4,186.660 $180.000 $55.000 $73.000 $58.000
JOINT SEALANT
LF 4,186.660 $10.000 $15.000 $10.500 $16.000
MOBILIZATION
LS 1.000 $347,491.000 $235,000.000 $400,000.000 $705,666.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $6,000.000 $4,500.000 $13,000.000 $9,381.180
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 78.000 $20.000 $20.000 $15.900 $35.710
CONSTRUCTION EXITS (REMOVE)
SY 78.000 $10.000 $5.000 $6.360 $13.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,000.000 $2.500 $3.500 $2.650 $3.750
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,000.000 $0.500 $1.500 $0.530 $1.500
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 3,041.000 $3.000 $5.000 $7.000 $4.710
BIODEG EROSN CONT LOGS (REMOVE)
LF 3,041.000 $0.500 $1.000 $1.060 $0.840
RUMBLE STRIPS (SHOULDER)
LF 284,385.000 $0.150 $0.100 $0.110 $0.120
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 10,680.000 $0.500 $0.500 $1.650 $1.760
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 672.000 $0.500 $0.500 $1.700 $1.760
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 9,452.000 $0.750 $0.700 $0.670 $0.630
REFL PAV MRK TY II (W) 4" (BRK)
LF 106,710.000 $0.140 $0.100 $0.110 $0.100
REFL PAV MRK TY II (W) 4" (SLD)
LF 450,395.000 $0.140 $0.100 $0.100 $0.090
REFL PAV MRK TY II (W) 8" (SLD)
LF 9,452.000 $0.300 $0.350 $0.350 $0.330
REFL PAV MRK TY II (Y) 4" (BRK)
LF 480.000 $0.140 $0.200 $0.210 $0.200
REFL PAV MRK TY II (Y) 4" (SLD)
LF 314,650.000 $0.140 $0.100 $0.100 $0.090
RE PM W/RET REQ TY I (W)4"(BRK)(090MIL)
LF 35,570.000 $0.260 $0.300 $0.300 $0.280
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 158,992.000 $0.260 $0.300 $0.300 $0.280
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
LF 240.000 $0.260 $0.300 $0.300 $0.280
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 158,080.000 $0.260 $0.300 $0.300 $0.280
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 203.000 $20.000 $10.000 $11.660 $11.000
PREFAB PAV MRK TY C (W) (NUMBER)
EA 5.000 $200.000 $300.000 $305.280 $288.000
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
EA 28.000 $35.000 $35.000 $34.980 $33.000
REFL PAV MRKR TY I-R
EA 84.000 $3.250 $8.500 $8.480 $8.000
REFL PAV MRKR TY II-A-A
EA 101.000 $3.250 $3.000 $3.180 $3.000
REFL PAV MRKR TY II-C-R
EA 2,280.000 $3.250 $3.000 $3.180 $3.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 212.000 $100.000 $65.000 $43.000 $106.950
TMA (STATIONARY)
DAY 248.000 $200.000 $150.000 $200.000 $75.000
TMA (MOBILE OPERATION)
HR 780.000 $15.000 $75.000 $85.000 $45.000
1
PFC (ASPHALT) PG76-22
TON 2,701.000 $96.330 $100.000 $111.250 $113.340
1
PFC-C (AGGREGATE)(PG76 MIX) SAC-A
TON 39,971.000 $92.000 $100.000 $111.250 $113.340
2
HIR (SURFACE) (2")
SY 149,450.000 $4.400 $4.500 $4.250 $5.930
2
HIR (RECYCLING AGENT)
GAL 74,760.000 $2.010 $3.500 $3.250 $3.150
Totals: $13,179,859.480 $8,342,120.020 $9,051,810.368 $9,946,893.880