Job Info for 0908-27-006

County: KENT Highway: CR Date: 12/06/2023 (11 months ago) Engineer's Estimate: $897,003 Control Number: 0908-27-006
Project: BR 2023(941) District: ABILENE Time: 89 WORKING DAYS Type: BRIDGE REPLACEMENT
Bidder's List
Informational:
Email All | Notice
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $897,003.00
EARTH BUILDERS, L.P.   $878,015.00 1
-2.12% | -$18,988.00
COPPELL CONSTRUCTION CO., INC.   $880,127.00 2
-1.88% | -$16,876.00
0.24% | $2,112.00
HODGES AND SON CONSTRUCTION COMPANY, INC.   $986,074.60 3
9.93% | $89,071.60
12.31% | $108,059.60
12.04% | $105,947.60
Subcontractor Percentage Amount
MORRIS COUNTY CONTRACTORS, L.L.C. 2.45% $21,511.37
V-TECH ENVIROMENTAL SERVICES 1.38% $12,116.61
BARRICADES UNLIMITED 0.52% $4,565.68
Total: 4.35% $38,193.66

Bid Items

Items: 30, 0 filtered
KENT CR  |  ABILENE  |  0908-27-006  |  12/06/2023  |  $897,003  |  BR 2023(941)  |  BRIDGE REPL  |  89 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate EARTH BUILDERS, L.P. COPPELL CONSTRUCTION CO., INC. HODGES AND SON CONSTRUCTION COMPANY, INC.
100 6001 PREPARING ROW AC 1.000 $2,350.000 $30,000.000 $15,600.000 $30,000.000
110 6001 EXCAVATION (ROADWAY) CY 16.000 $50.000 $25.000 $142.000 $100.000
110 6002 EXCAVATION (CHANNEL) CY 824.000 $35.000 $25.000 $45.000 $50.000
132 6004 EMBANKMENT (FINAL)(DENS CONT)(TY B) CY 558.000 $85.000 $55.000 $50.000 $50.000
150 6002 BLADING HR 16.000 $250.000 $150.000 $150.000 $50.000
247 6237 FL BS (CMP IN PLC)(TY A OR B GR 4)(6") SY 948.000 $55.000 $40.000 $100.000 $50.000
400 6005 CEM STABIL BKFL CY 49.000 $300.000 $400.000 $450.000 $300.000
409 6002 PRESTR CONC PIL (18 IN SQ) LF 360.000 $250.000 $250.000 $360.000 $455.000
420 6013 CL C CONC (ABUT) CY 27.200 $2,000.000 $2,500.000 $1,760.000 $2,000.000
420 6066 CL C CONC (RAIL FOUNDATION) CY 18.600 $1,100.000 $1,000.000 $1,070.000 $1.000
422 6005 REINF CONC SLAB (BOX BEAM) SF 1,723.000 $35.000 $35.000 $28.000 $50.000
425 6001 PRESTR CONC BOX BEAM (4B20) LF 260.000 $400.000 $420.000 $370.000 $510.000
425 6002 PRESTR CONC BOX BEAM (5B20) LF 130.000 $400.000 $420.000 $420.000 $510.000
432 6002 RIPRAP (CONC)(5 IN) CY 54.000 $700.000 $880.000 $605.000 $800.000
434 6002 ELASTOMERIC BEARING (LAMINATED) EA 18.000 $400.000 $100.000 $800.000 $2,000.000
450 6006 RAIL (TY T223) LF 162.000 $200.000 $250.000 $220.000 $180.000
454 6018 SEALED EXPANSION JOINT (4 IN) (SEJ - M) LF 52.000 $250.000 $350.000 $310.000 $200.000
496 6009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) EA 1.000 $35,000.000 $100,000.000 $46,000.000 $50,000.000
500 6001 MOBILIZATION LS 1.000 $144,084.000 $85,000.000 $85,000.000 $90,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 5.000 $12,500.000 $1,500.000 $4,500.000 $6,500.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 578.000 $7.000 $7.000 $5.000 $1.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 578.000 $1.000 $3.000 $1.500 $1.000
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 370.000 $10.000 $7.000 $5.000 $1.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 370.000 $3.000 $3.000 $1.000 $1.000
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 50.000 $32.000 $40.000 $30.000 $30.000
540 6007 MTL BEAM GD FEN TRANS (TL2) EA 4.000 $1,500.000 $1,600.000 $1,500.000 $1,800.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 4.000 $3,750.000 $3,800.000 $3,500.000 $4,000.000
644 6076 REMOVE SM RD SN SUP&AM EA 3.000 $120.000 $300.000 $200.000 $50.000
658 6014 INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) EA 12.000 $50.000 $50.000 $50.000 $50.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 12.000 $50.000 $50.000 $50.000 $50.000
Totals: $897,003.00 $878,015.00 $880,127.00 $986,074.60