Job Info for 0327-04-039

County: KENEDY Highway: US 77 Date: 08/02/2024 (3 months ago) Engineer's Estimate: $106,176,094 Control Number: 0327-04-039
Project: F 2B24(314) District: PHARR Time: 685 WORKING DAYS Type: INTERSTATE DESIGNATION
Bidder's List
Informational:

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $106,176,094.30
FOREMOST PAVING, INC.   $93,082,026.74 1
-12.33% | -$13,094,067.56
POSILLICO CIVIL, INC.   $95,073,599.93 2
-10.46% | -$11,102,494.37
2.14% | $1,991,573.19
PULICE CONSTRUCTION, INC.   $138,908,169.00 3
30.83% | $32,732,074.70
49.23% | $45,826,142.26
46.11% | $43,834,569.07

Bid Items

Items: 168, 0 filtered
KENEDY US 77  |  PHARR  |  0327-04-039  |  08/02/2024  |  $106,176,094  |  F 2B24(314)  |  INTERSTATE DESIGNATION  |  685 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate FOREMOST PAVING, INC. POSILLICO CIVIL, INC. PULICE CONSTRUCTION, INC.
100 6002 PREPARING ROW STA 259.000 $15,000.000 $14,000.000 $6,000.000 $53,632.490
110 6001 EXCAVATION (ROADWAY) CY 57,260.000 $6.000 $7.500 $3.750 $5.000
132 6002 EMBANKMENT (FINAL)(DENS CONT)(TY A) CY 498.000 $61.000 $32.000 $6.250 $52.410
132 6006 EMBANKMENT (FINAL)(DENS CONT)(TY C) CY 720,790.000 $30.000 $11.500 $26.500 $13.500
134 6001 BACKFILL (TY A) STA 89.000 $400.000 $300.000 $1,056.000 $419.980
160 6005 FURNISHING AND PLACING TOPSOIL CY 50.000 $50.000 $30.000 $21.000 $907.680
164 6001 BROADCAST SEED (PERM) (RURAL) (SANDY) SY 594,343.000 $0.450 $0.250 $0.220 $0.140
164 6029 CELL FBR MLCH SEED(TEMP)(WARM) SY 297,172.000 $0.400 $0.300 $0.310 $0.400
164 6031 CELL FBR MLCH SEED(TEMP)(COOL) SY 297,172.000 $0.400 $0.300 $0.310 $0.400
168 6001 VEGETATIVE WATERING MG 4,832.000 $40.000 $55.000 $30.000 $54.490
247 6225 FL BS (RDWY DEL)(TY E GR 4)(FNAL POS) CY 47,291.000 $50.000 $45.000 $45.000 $50.420
251 6028 REWORK BS MTL (TY B) (8") (DENS CONT) SY 186,947.000 $2.000 $1.500 $2.250 $4.090
275 6001 CEMENT TON 7,337.000 $200.000 $210.000 $209.000 $205.000
275 6015 CEMENT TREAT (MX EXST MTL & NW BS)(11") SY 65,013.000 $3.000 $3.250 $2.500 $3.980
275 6065 CEM TRT(MX EXST MTL & NEW BS)(14") SY 196,263.000 $3.000 $2.000 $3.000 $3.990
275 6080 CEMENT TREAT (SUBGRADE)(12") SY 273,006.000 $2.750 $2.250 $2.500 $3.230
305 6006 SLV, HAUL & STKPL RCL APH PV (8 TO 10") SY 186,947.000 $3.500 $4.000 $4.750 $4.250
310 6009 PRIME COAT (MC-30) GAL 49,883.000 $5.500 $5.000 $6.000 $5.150
351 6038 FLEXIBLE PAVEMENT STRUCTURE REPAIR(1") SY 4,026.000 $100.000 $30.000 $32.000 $24.000
354 6002 PLAN & TEXT ASPH CONC PAV(0" TO 2") SY 21,728.000 $20.000 $2.500 $1.750 $2.000
354 6119 PLAN & TEXT ASPH CONC PAV (1.5") SY 3,314.000 $6.000 $15.000 $9.000 $2.000
400 6002 STRUCT EXCAV (BOX) CY 1,052.000 $50.000 $5.000 $134.000 $22.600
400 6003 STRUCT EXCAV (PIPE) CY 999.000 $85.000 $5.000 $134.000 $66.950
400 6005 CEM STABIL BKFL CY 366.000 $250.000 $300.000 $115.000 $66.950
400 6008 CUT & RESTORE ASPH PAVING SY 89.000 $125.000 $185.000 $435.000 $431.900
401 6001 FLOWABLE BACKFILL CY 246.000 $500.000 $200.000 $309.000 $463.500
402 6001 TRENCH EXCAVATION PROTECTION LF 1,064.000 $20.000 $1.000 $2.000 $2.060
409 6002 PRESTR CONC PIL (18 IN SQ) LF 3,630.000 $200.000 $200.000 $220.000 $214.970
416 6015 DRILL SHAFT (NON - REINFORCED) (12 IN) LF 21.000 $120.000 $190.000 $190.000 $75.000
416 6018 DRILL SHAFT (SIGN MTS) (24 IN) LF 90.000 $180.000 $205.000 $205.000 $145.000
416 6029 DRILL SHAFT (RDWY ILL POLE) (30 IN) LF 160.000 $240.000 $250.000 $251.000 $245.000
420 6011 CL B CONC (FLUME) CY 32.000 $700.000 $900.000 $762.000 $614.000
420 6013 CL C CONC (ABUT) CY 276.800 $1,800.000 $1,800.000 $1,450.000 $1,606.980
420 6071 CL C CONC (COLLAR) EA 25.000 $1,500.000 $4,000.000 $2,500.000 $3,605.000
420 6074 CL C CONC (MISC) CY 76.000 $1,000.000 $1,400.000 $850.000 $1,029.670
422 6001 REINF CONC SLAB SF 18,400.000 $30.000 $30.000 $35.000 $47.980
422 6007 REINF CONC SLAB (SLAB BEAM) SF 5,279.000 $30.000 $25.000 $37.000 $30.440
423 6002 RETAINING WALL (MSE) (ASHLAR STONE FIN) SF 221,828.000 $80.000 $110.000 $46.500 $203.340
423 6003 RETAINING WALL (TEMP WALL) SF 35,831.000 $26.000 $42.000 $32.500 $100.310
425 6011 PRESTR CONC SLAB BEAM (4SB15) LF 544.500 $250.000 $190.000 $650.000 $366.380
425 6012 PRESTR CONC SLAB BEAM (5SB15) LF 594.000 $275.000 $190.000 $800.000 $364.420
425 6039 PRESTR CONC GIRDER (TX54) LF 2,290.000 $250.000 $210.000 $250.000 $347.640
432 6001 RIPRAP (CONC)(4 IN) CY 257.000 $500.000 $611.000 $700.000 $611.000
432 6002 RIPRAP (CONC)(5 IN) CY 286.000 $600.000 $635.000 $670.000 $634.000
432 6016 RIPRAP (STONE TY R)(DRY)(12 IN) CY 37.000 $300.000 $350.000 $256.000 $325.000
432 6031 RIPRAP (STONE PROTECTION)(12 IN) CY 21.000 $300.000 $350.000 $387.000 $325.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 555.000 $490.000 $625.000 $801.000 $609.000
450 6023 RAIL (TY SSTR) LF 12,400.200 $65.000 $45.000 $64.000 $80.210
454 6018 SEALED EXPANSION JOINT (4 IN) (SEJ - M) LF 520.000 $225.000 $300.000 $321.000 $458.610
462 6005 CONC BOX CULV (4 FT X 4 FT) LF 164.000 $600.000 $550.000 $912.000 $864.850
462 6011 CONC BOX CULV (6 FT X 4 FT) LF 816.000 $1,000.000 $585.000 $700.000 $1,103.920
462 6012 CONC BOX CULV (6 FT X 5 FT) LF 362.000 $1,100.000 $650.000 $950.000 $1,183.380
462 6020 CONC BOX CULV (8 FT X 5 FT) LF 87.000 $2,000.000 $1,000.000 $2,048.000 $1,698.140
462 6064 CONC BOX CULV (8 FT X 5 FT)(EXTEND) LF 216.000 $2,500.000 $930.000 $1,100.000 $1,762.700
464 6038 RC PIPE (CL III)(18 IN)(SPL) LF 430.000 $100.000 $130.000 $179.000 $91.900
464 6039 RC PIPE (CL III)(24 IN)(SPL) LF 8,741.000 $115.000 $140.000 $150.000 $111.420
464 6040 RC PIPE (CL III)(30 IN)(SPL) LF 1,548.000 $150.000 $200.000 $165.000 $156.820
464 6042 RC PIPE (CL III)(42 IN)(SPL) LF 234.000 $275.000 $280.000 $255.000 $297.930
465 6070 INLET (COMPL)(PSL)(RC)(3FTX3FT) EA 20.000 $5,000.000 $6,000.000 $8,736.000 $4,296.730
465 6071 INLET (COMPL)(PSL)(RC)(4FTX4FT) EA 4.000 $8,000.000 $6,700.000 $9,748.000 $5,899.810
465 6126 INLET (COMPL)(PSL)(FG)(3FTX3FT-3FTX3FT) EA 15.000 $6,500.000 $8,500.000 $9,207.000 $5,172.750
465 6127 INLET (COMPL)(PSL)(FG)(4FTX4FT-3FTX3FT) EA 4.000 $8,700.000 $9,500.000 $10,571.000 $5,927.300
465 6147 INLET(COMPL)(PSL)(SFG)(4FTX4FT-4FTX4FT) EA 1.000 $10,000.000 $10,000.000 $11,997.000 $8,382.780
465 6178 INLET (COMPL)(TY MSE1) EA 41.000 $6,000.000 $16,000.000 $8,875.000 $4,604.100
465 6257 INLET(COMPL)(WALL)(SPL) EA 8.000 $6,000.000 $9,000.000 $14,871.000 $14,626.000
466 6097 HEADWALL (CH - PW - 0) (DIA= 24 IN) EA 1.000 $9,000.000 $14,000.000 $13,716.000 $18,540.000
466 6099 HEADWALL (CH - PW - 0) (DIA= 30 IN) EA 1.000 $11,000.000 $15,000.000 $15,043.000 $18,540.000
466 6153 WINGWALL (FW - 0) (HW=6 FT) EA 3.000 $15,000.000 $71,000.000 $27,953.000 $18,540.000
466 6154 WINGWALL (FW - 0) (HW=7 FT) EA 2.000 $15,000.000 $58,000.000 $81,501.000 $18,540.000
466 6182 WINGWALL (PW - 1) (HW=7 FT) EA 3.000 $27,000.000 $100,000.000 $29,151.000 $18,540.000
467 6152 SET (TY I)(S= 4 FT)(HW= 5 FT)(6:1) (C) EA 4.000 $20,000.000 $30,000.000 $29,225.000 $51,993.960
467 6358 SET (TY II) (18 IN) (RCP) (4: 1) (C) EA 1.000 $2,000.000 $1,500.000 $3,778.000 $1,802.500
467 6362 SET (TY II) (18 IN) (RCP) (6: 1) (C) EA 6.000 $2,300.000 $1,900.000 $2,953.000 $1,905.500
467 6390 SET (TY II) (24 IN) (RCP) (4: 1) (C) EA 13.000 $3,000.000 $1,800.000 $2,573.000 $2,060.000
467 6394 SET (TY II) (24 IN) (RCP) (6: 1) (C) EA 6.000 $3,000.000 $2,400.000 $3,384.000 $2,214.500
467 6419 SET (TY II) (30 IN) (RCP) (4: 1) (C) EA 6.000 $3,000.000 $2,500.000 $3,672.000 $9,424.500
467 6422 SET (TY II) (30 IN) (RCP) (6: 1) (C) EA 7.000 $4,200.000 $3,400.000 $3,683.000 $9,630.500
467 6463 SET (TY II) (42 IN) (RCP) (4: 1) (C) EA 2.000 $6,000.000 $5,200.000 $6,470.000 $14,935.000
467 6465 SET (TY II) (42 IN) (RCP) (6: 1) (C) EA 2.000 $6,000.000 $8,900.000 $6,650.000 $16,995.000
480 6001 CLEAN EXIST CULVERTS EA 9.000 $10,000.000 $2,000.000 $3,050.000 $10,300.000
496 6004 REMOV STR (SET) EA 30.000 $1,500.000 $900.000 $1,148.000 $557.110
496 6005 REMOV STR (WINGWALL) EA 12.000 $3,250.000 $6,000.000 $2,864.000 $1,289.200
496 6006 REMOV STR (HEADWALL) EA 6.000 $1,500.000 $6,000.000 $2,864.000 $1,289.200
496 6007 REMOV STR (PIPE) LF 1,195.000 $25.000 $50.000 $58.000 $15.590
496 6008 REMOV STR (BOX CULVERT) LF 574.000 $200.000 $420.000 $60.000 $38.140
500 6001 MOBILIZATION LS 1.000 $11,322,867.250 $8,000,000.000 $7,777,777.000 $13,890,817.120
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 43.000 $12,000.000 $8,500.000 $2,777.910 $32,265.000
506 6002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 3,574.000 $55.000 $57.000 $48.000 $56.460
506 6011 ROCK FILTER DAMS (REMOVE) LF 3,574.000 $15.000 $47.000 $33.000 $17.730
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 156.000 $50.000 $46.000 $46.000 $53.210
506 6024 CONSTRUCTION EXITS (REMOVE) SY 156.000 $15.000 $23.000 $33.000 $14.220
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 49,440.000 $3.500 $3.500 $3.250 $3.480
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 49,440.000 $1.000 $1.500 $1.500 $1.290
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 1,500.000 $7.500 $7.000 $7.000 $8.840
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 1,500.000 $2.000 $1.500 $1.500 $2.140
508 6001 CONSTRUCTING DETOURS SY 143,642.000 $40.000 $56.500 $69.000 $60.330
512 6001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) LF 38,940.000 $65.000 $38.000 $80.000 $17.700
512 6025 PORT CTB (MOVE)(SGL SLP)(TY 1) LF 134,910.000 $15.000 $7.000 $5.000 $4.930
512 6037 PORT CTB (STKPL)(SGL SLP)(TY 1) LF 29,040.000 $6.000 $6.000 $22.000 $14.280
512 6049 PORT CTB (REMOVE)(SGL SLP)(TY 1) LF 38,940.000 $10.000 $13.000 $10.000 $16.730
530 6005 DRIVEWAYS (ACP) SY 500.000 $50.000 $75.000 $67.000 $94.010
533 6001 RUMBLE STRIPS (SHOULDER) LF 96,720.000 $0.150 $0.350 $0.250 $0.100
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 3,225.000 $25.000 $24.000 $25.000 $26.450
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 11.000 $1,650.000 $2,100.000 $2,273.000 $2,168.010
540 6016 DOWNSTREAM ANCHOR TERMINAL SECTION EA 9.000 $1,650.000 $1,400.000 $2,380.000 $1,266.880
542 6001 REMOVE METAL BEAM GUARD FENCE LF 400.000 $6.000 $5.000 $3.250 $2.120
542 6002 REMOVE TERMINAL ANCHOR SECTION EA 2.000 $180.000 $750.000 $179.000 $212.030
543 6002 CABLE BARRIER SYSTEM (TL-4) LF 24,150.000 $15.000 $19.000 $11.000 $17.860
543 6020 CABLE BARRIER TERMINAL SECTION (TL-4) EA 12.000 $4,000.000 $3,800.000 $2,975.000 $3,922.560
543 6021 REMOVE CABLE BARRIER LF 23,946.000 $6.000 $5.000 $4.090 $2.970
543 6022 REMOVE CABLE BARRIER TERMINAL SECTION EA 10.000 $400.000 $200.000 $542.800 $386.960
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 20.000 $3,500.000 $2,900.000 $2,965.000 $3,021.430
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 2.000 $500.000 $500.000 $262.000 $318.050
545 6003 CRASH CUSH ATTEN (MOVE & RESET) EA 25.000 $1,300.000 $225.000 $1,381.000 $1,463.010
545 6004 CRASH CUSH ATTEN (STKPL) EA 10.000 $1,200.000 $1,300.000 $3,400.000 $773.910
545 6005 CRASH CUSH ATTEN (REMOVE) EA 10.000 $1,500.000 $230.000 $693.000 $773.910
545 6019 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) EA 10.000 $15,000.000 $15,000.000 $7,948.000 $8,194.980
550 6008 CHAIN LINK FENCE (INSTALL) (8') LF 9,268.000 $70.000 $40.000 $31.000 $42.410
610 6106 IN RD IL (U/P) (TY 2) (150W EQ) LED EA 4.000 $1,350.000 $1,650.000 $1,640.000 $1,600.000
610 6214 IN RD IL (TY SA) 40T-8 (250W EQ) LED EA 20.000 $4,700.000 $4,500.000 $4,614.000 $4,500.000
618 6023 CONDT (PVC) (SCH 40) (2") LF 7,185.000 $12.000 $12.000 $11.000 $11.000
618 6047 CONDT (PVC) (SCH 80) (2") (BORE) LF 541.000 $33.000 $36.000 $36.000 $35.000
618 6062 CONDT (RM) (3/4") LF 372.000 $18.000 $31.000 $31.000 $30.000
620 6007 ELEC CONDR (NO.8) BARE LF 8,398.000 $1.500 $1.600 $1.500 $1.500
620 6008 ELEC CONDR (NO.8) INSULATED LF 19,984.000 $1.500 $1.600 $1.500 $1.500
624 6002 GROUND BOX TY A (122311)W/APRON EA 16.000 $1,000.000 $1,125.000 $1,128.000 $1,100.000
628 6050 ELC SRV TY A 240/480 060(NS)SS(T)TP(O) EA 2.000 $5,000.000 $5,505.000 $5,639.000 $5,500.000
636 6002 ALUMINUM SIGNS (TY G) SF 852.000 $31.000 $26.000 $27.000 $23.900
644 6027 IN SM RD SN SUP&AM TYS80(1)SA(P) EA 40.000 $692.000 $815.000 $724.000 $680.000
644 6028 IN SM RD SN SUP&AM TYS80(1)SA(P-BM) EA 9.000 $800.000 $910.000 $778.000 $760.000
644 6030 IN SM RD SN SUP&AM TYS80(1)SA(T) EA 19.000 $806.000 $1,050.000 $806.000 $870.000
644 6033 IN SM RD SN SUP&AM TYS80(1)SA(U) EA 12.000 $875.000 $1,150.000 $1,009.000 $995.000
644 6064 IN BRIDGE MNT CLEARANCE SGN ASSM(TY N) EA 4.000 $1,140.000 $2,625.000 $2,359.000 $2,030.000
644 6066 IN SM RD SN SUP&AM (RAIL MOUNT) EA 6.000 $4,000.000 $7,200.000 $3,781.000 $3,670.000
644 6076 REMOVE SM RD SN SUP&AM EA 36.000 $80.000 $165.000 $109.000 $80.000
647 6001 INSTALL LRSS (STRUCT STEEL) LB 5,008.000 $6.250 $7.500 $7.000 $6.000
658 6013 INSTL DEL ASSM (D-SW)SZ (BRF)CTB EA 117.000 $40.000 $28.000 $12.000 $21.200
658 6026 INSTL DEL ASSM (D-SY)SZ (BRF)CTB EA 12.000 $30.000 $27.000 $12.000 $22.260
658 6061 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2 EA 43.000 $30.000 $53.000 $32.000 $27.560
658 6064 INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2 EA 48.000 $30.000 $44.000 $32.000 $27.560
658 6080 INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND EA 60.000 $70.000 $85.000 $64.000 $53.010
662 6052 WK ZN PAV MRK REMOV (REFL) TY II-C-R EA 89.000 $4.000 $5.000 $5.000 $5.000
662 6067 WK ZN PAV MRK REMOV (W)6"(SLD) LF 129,397.000 $0.500 $0.350 $0.500 $0.340
662 6071 WK ZN PAV MRK REMOV (W)8"(SLD) LF 1,814.000 $1.000 $0.900 $1.000 $0.880
662 6075 WK ZN PAV MRK REMOV (W)24"(SLD) LF 72.000 $0.700 $16.000 $16.000 $16.000
662 6078 WK ZN PAV MRK REMOV (W)6"(BKN W/MRKR) LF 28,255.000 $5.000 $0.650 $0.500 $0.600
662 6098 WK ZN PAV MRK REMOV (Y)6"(SLD) LF 129,181.000 $0.500 $0.350 $0.250 $0.340
662 6109 WK ZN PAV MRK SHT TERM (TAB)TY W EA 48,564.000 $0.250 $1.150 $1.700 $1.000
666 6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL) LF 3,185.000 $1.500 $1.100 $1.000 $1.100
666 6042 REFL PAV MRK TY I (W)12"(SLD)(100MIL) LF 500.000 $6.500 $2.250 $2.000 $2.100
666 6048 REFL PAV MRK TY I (W)24"(SLD)(100MIL) LF 225.000 $11.000 $16.000 $16.000 $16.000
666 6306 RE PM W/RET REQ TY I (W)6"(BRK)(100MIL) LF 16,160.000 $0.650 $0.900 $1.000 $0.880
666 6309 RE PM W/RET REQ TY I (W)6"(SLD)(100MIL) LF 68,185.000 $0.780 $0.800 $0.750 $0.780
666 6321 RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL) LF 67,505.000 $0.780 $0.800 $0.750 $0.780
668 6083 PREFAB PAV MRK TY C (W) (LNDP ARROW) EA 2.000 $500.000 $500.000 $500.000 $500.000
672 6009 REFL PAV MRKR TY II-A-A EA 28.000 $5.500 $7.500 $7.500 $7.500
672 6010 REFL PAV MRKR TY II-C-R EA 987.000 $5.500 $7.500 $7.500 $7.500
2001 6002 INSTL TIED CONCRETE EROSN CONTROL MATS SF 7,429.000 $6.000 $18.000 $6.000 $12.340
3077 6003 SP MIXES SP-B SAC-B PG64-22 TON 66,877.000 $115.000 $118.000 $135.000 $118.000
3077 6065 SP MIXES SP-D SAC-A PG76-22 TON 10,366.000 $130.000 $131.000 $133.000 $133.400
3077 6066 SP MIXES SP-D SAC-B PG76-22 TON 19,261.000 $120.000 $131.000 $146.000 $126.000
3080 6013 STONE-MTRX-ASPH SMA-F SAC-A PG76-22 TON 37,126.000 $150.000 $72.000 $135.000 $151.000
3084 6001 BONDING COURSE GAL 47,230.000 $3.500 $3.000 $8.000 $3.000
4014 6001 INTRLCK ART CONC BLKS (4" MIN) SF 24,285.000 $12.000 $35.000 $8.000 $11.470
5001 6002 GEOGRID BASE REINFORCEMENT (TY II) SY 47,563.000 $2.000 $1.650 $1.670 $1.500
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 2.000 $22,000.000 $8,000.000 $23,408.000 $31,226.510
6185 6002 TMA (STATIONARY) DAY 1,546.000 $250.000 $25.000 $170.000 $195.090
6185 6005 TMA (MOBILE OPERATION) DAY 314.000 $450.000 $0.010 $574.000 $195.090
Totals: $106,176,094.30 $93,082,026.74 $95,073,599.93 $138,908,169.01