County: KENDALL Highway: CS Date: 10/04/2017 (7 years ago) Engineer's Estimate: $569,951 Control Number: 0915-11-028
Project: BR 1102(443) District: SAN ANTONIO Time: 86 WORKING DAYS Type: REPLACE BRIDGE AND APPROACHES

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $569,951.38
CURRAN CONTRACTING COMPANY   $514,522.70 1
-9.73% | -$55,428.68
SB CONTRACTORS LLC   $523,056.65 2
-8.23% | -$46,894.73
1.66% | $8,533.95
RELMCO, INC.   $535,442.05 3
-6.05% | -$34,509.33
4.07% | $20,919.35
2.37% | $12,385.40
J3 COMPANY, LLC   $548,468.32 4
-3.77% | -$21,483.06
6.6% | $33,945.62
2.43% | $13,026.27
ACME BRIDGE COMPANY, INC.   $555,092.16 5
-2.61% | -$14,859.22
7.88% | $40,569.46
1.21% | $6,623.84
CAPITAL EXCAVATION COMPANY   $557,084.82 6
-2.26% | -$12,866.56
8.27% | $42,562.12
0.36% | $1,992.66
TMES LLC   $579,688.93 7
1.71% | $9,737.55
12.67% | $65,166.23
4.06% | $22,604.11
HODGES AND SON CONSTRUCTION COMPANY, INC.   $625,417.00 8
9.73% | $55,465.62
21.55% | $110,894.30
7.89% | $45,728.07
HILL COUNTRY BRIDGE, INC.   $658,249.25 9
15.49% | $88,297.87
27.93% | $143,726.55
5.25% | $32,832.25
A GREATER AUSTIN DEVELOPMENT COMPANY, LTD.   $708,974.83 10
24.39% | $139,023.45
37.79% | $194,452.13
7.71% | $50,725.58
3LW CIVIL LLC   $744,144.00 11
30.56% | $174,192.62
44.63% | $229,621.30
4.96% | $35,169.17

Bid Items

Items: 46, 0 filtered
KENDALL CS  |  SAN ANTONIO  |  0915-11-028  |  10/04/2017  |  $569,951  |  BR 1102(443)  |  REPLACE BRIDGE AND APPROACHES  |  86 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate CURRAN CONTRACTING COMPANY SB CONTRACTORS LLC RELMCO, INC. J3 COMPANY, LLC ACME BRIDGE COMPANY, INC. CAPITAL EXCAVATION COMPANY TMES LLC HODGES AND SON CONSTRUCTION COMPANY, INC. HILL COUNTRY BRIDGE, INC. A GREATER AUSTIN DEVELOPMENT COMPANY, LTD. 3LW CIVIL LLC
100 6002 PREPARING ROW STA 3.000 $5,000.000 $11,500.000 $3,000.000 $5,000.000 $9,635.640 $2,250.000 $8,000.000 $1,385.000 $4,000.000 $8,120.000 $1,500.000 $8,500.000
105 6058 REMOVING STAB BASE & ASPH PAV (10"-12") SY 483.000 $8.000 $4.000 $12.000 $6.000 $12.000 $10.500 $10.000 $15.970 $20.000 $23.100 $25.000 $10.000
110 6001 EXCAVATION (ROADWAY) CY 108.000 $8.630 $5.500 $15.000 $15.000 $15.000 $16.900 $30.000 $18.220 $20.000 $18.700 $35.000 $35.000
110 6002 EXCAVATION (CHANNEL) CY 1,119.000 $13.500 $21.200 $10.000 $12.000 $10.000 $25.000 $20.000 $12.770 $20.000 $40.950 $32.000 $35.000
132 6003 EMBANKMENT (FINAL)(ORD COMP)(TY B) CY 181.000 $10.250 $15.800 $10.000 $35.000 $10.000 $18.300 $25.000 $19.550 $20.000 $18.700 $28.000 $45.000
160 6003 FURNISHING AND PLACING TOPSOIL (4") SY 311.000 $1.400 $4.500 $3.500 $5.000 $3.000 $6.400 $7.000 $8.560 $8.000 $8.150 $3.000 $3.000
164 6007 BROADCAST SEED (PERM) (URBAN) (CLAY) SY 311.000 $1.250 $2.650 $2.500 $2.200 $2.000 $2.650 $0.200 $0.300 $3.000 $2.700 $0.210 $1.000
168 6001 VEGETATIVE WATERING MG 5.000 $65.000 $25.000 $75.000 $100.000 $43.000 $76.000 $100.000 $100.000 $1.000 $182.000 $500.000 $50.000
169 6001 SOIL RETENTION BLANKETS (CL 1) (TY A) SY 311.000 $3.300 $1.350 $1.250 $1.925 $2.000 $1.350 $2.500 $3.200 $3.000 $1.400 $2.700 $3.000
247 6041 FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS) CY 128.000 $93.500 $92.000 $105.000 $75.000 $80.000 $69.200 $65.000 $85.540 $80.000 $129.900 $140.000 $150.000
275 6001 CEMENT TON 7.000 $140.000 $169.000 $185.000 $200.000 $175.000 $384.000 $350.000 $325.000 $300.000 $225.000 $240.000 $275.000
275 6009 CEMENT TREAT (NEW BASE) (8") SY 573.000 $4.000 $2.500 $7.000 $4.000 $15.000 $12.300 $11.000 $12.620 $16.000 $33.900 $22.000 $6.000
310 6009 PRIME COAT (MC-30) GAL 115.000 $4.000 $6.700 $26.000 $7.000 $5.000 $15.220 $15.000 $9.720 $12.000 $9.750 $9.000 $8.000
316 6240 AGGR(TY-PD GR-4 SAC-B) CY 11.000 $80.000 $396.000 $1,000.000 $500.000 $690.000 $845.600 $850.000 $540.000 $1,000.000 $542.000 $500.000 $350.000
316 6410 ASPH(AC-15P,AC-20-5TR,AC-20XP,AC10-2TR) GAL 367.000 $5.000 $6.100 $38.000 $7.000 $6.000 $12.680 $13.000 $8.100 $16.000 $8.150 $7.500 $9.000
400 6005 CEM STABIL BKFL CY 23.000 $104.150 $112.000 $170.000 $100.000 $150.000 $216.000 $180.000 $165.000 $250.000 $181.500 $250.000 $250.000
416 6002 DRILL SHAFT (24 IN) LF 372.000 $263.900 $186.000 $150.000 $250.000 $180.000 $215.000 $200.000 $241.570 $180.000 $257.750 $200.000 $300.000
420 6013 CL C CONC (ABUT) CY 13.800 $860.000 $964.000 $1,000.000 $1,205.100 $1,700.000 $1,100.000 $860.000 $1,265.000 $1,200.000 $958.000 $1,400.000 $1,500.000
420 6029 CL C CONC (CAP) CY 12.600 $640.000 $1,590.000 $1,200.000 $1,023.100 $1,700.000 $1,400.000 $900.000 $1,554.000 $1,200.000 $1,230.000 $1,600.000 $1,500.000
420 6037 CL C CONC (COLUMN) CY 8.400 $895.000 $1,390.000 $1,200.000 $1,023.100 $1,000.000 $1,100.000 $1,000.000 $1,450.000 $1,200.000 $1,410.000 $2,000.000 $900.000
420 6156 CL C CONC (WEBWALL) CY 17.800 $800.000 $1,150.000 $1,100.000 $851.500 $1,000.000 $1,500.000 $930.000 $1,060.000 $1,200.000 $1,165.000 $1,300.000 $1,400.000
422 6015 APPROACH SLAB CY 46.000 $407.000 $440.000 $500.000 $630.500 $750.000 $550.000 $555.000 $550.000 $650.000 $530.000 $620.000 $750.000
422 6019 SLAB SPAN CY 84.500 $1,120.000 $925.000 $875.000 $819.000 $1,000.000 $1,000.000 $900.000 $725.000 $1,200.000 $860.000 $1,400.000 $650.000
432 6036 RIPRAP (STONE PROTECTION)(30 IN) CY 525.000 $155.000 $125.000 $160.000 $125.000 $100.000 $131.000 $180.000 $165.000 $180.000 $151.750 $180.000 $175.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 25.000 $465.000 $360.000 $525.000 $475.000 $500.000 $526.000 $500.000 $450.000 $500.000 $610.000 $540.000 $500.000
450 6006 RAIL (TY T223) LF 174.000 $200.000 $140.000 $115.000 $75.000 $150.000 $97.500 $80.000 $119.000 $120.000 $96.000 $170.000 $200.000
496 6001 REMOV STR (BOX CULVERT) EA 1.000 $5,100.000 $5,900.000 $7,500.000 $17,500.000 $25,000.000 $22,100.000 $21,000.000 $15,775.000 $16,000.000 $42,600.000 $33,600.000 $25,000.000
500 6001 MOBILIZATION LS 1.000 $50,234.130 $50,000.000 $50,000.000 $50,000.000 $50,000.000 $45,000.000 $58,000.000 $82,000.000 $60,000.000 $65,000.000 $70,000.000 $92,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 6.000 $8,000.000 $1,000.000 $4,000.000 $5,500.000 $2,000.000 $2,000.000 $829.920 $2,620.000 $3,200.000 $2,160.000 $3,500.000 $10,000.000
506 6001 ROCK FILTER DAMS (INSTALL) (TY 1) LF 60.000 $18.000 $17.350 $35.000 $28.600 $22.000 $26.600 $30.300 $28.750 $40.000 $27.100 $32.500 $35.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 60.000 $7.670 $5.850 $15.000 $7.700 $8.000 $15.900 $9.800 $11.500 $20.000 $15.750 $10.500 $10.000
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 156.000 $20.180 $20.000 $15.000 $21.940 $12.000 $11.700 $14.700 $12.650 $30.000 $12.000 $15.500 $15.000
506 6024 CONSTRUCTION EXITS (REMOVE) SY 156.000 $6.370 $5.700 $9.000 $7.700 $5.000 $9.600 $4.750 $10.350 $10.000 $9.500 $5.100 $5.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 144.000 $2.190 $3.000 $6.000 $3.300 $3.500 $5.300 $3.000 $3.500 $4.000 $5.500 $3.200 $3.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 144.000 $0.610 $1.250 $1.000 $1.650 $1.500 $1.050 $0.500 $2.000 $1.000 $1.000 $0.530 $1.000
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 100.000 $20.550 $29.000 $27.450 $24.695 $27.450 $29.200 $27.450 $31.560 $26.000 $29.800 $23.500 $22.000
540 6007 MTL BEAM GD FEN TRANS (TL2) EA 4.000 $1,471.240 $948.000 $890.000 $869.000 $890.000 $945.000 $890.000 $1,023.500 $1,000.000 $965.000 $940.000 $1,250.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 4.000 $2,201.050 $2,265.000 $2,126.000 $2,706.490 $2,126.000 $2,260.000 $2,126.000 $2,445.000 $2,800.000 $2,310.000 $3,000.000 $2,450.000
644 6001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 2.000 $448.300 $541.000 $508.000 $522.500 $508.000 $514.000 $508.000 $585.000 $800.000 $525.000 $450.000 $490.000
644 6023 IN SM RD SN SUP&AM TYFRP(1)UA(P) EA 2.000 $530.000 $490.000 $460.000 $522.500 $460.000 $461.000 $460.000 $529.000 $800.000 $470.000 $510.000 $550.000
644 6076 REMOVE SM RD SN SUP&AM EA 3.000 $100.000 $14.000 $150.000 $126.500 $100.000 $159.000 $100.000 $150.000 $100.000 $165.000 $130.000 $145.000
658 6016 INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI) EA 16.000 $17.000 $14.000 $13.000 $16.500 $13.000 $14.300 $12.000 $15.000 $60.000 $15.000 $36.500 $29.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 16.000 $20.000 $22.000 $20.300 $19.800 $20.300 $16.700 $20.300 $25.000 $60.000 $17.000 $41.500 $29.000
666 6170 REFL PAV MRK TY II (W) 4" (SLD) LF 514.000 $0.100 $3.750 $3.450 $3.575 $3.450 $3.450 $3.450 $4.000 $6.000 $2.000 $3.700 $4.000
666 6207 REFL PAV MRK TY II (Y) 4" (SLD) LF 714.000 $0.100 $3.750 $3.450 $3.575 $3.450 $3.450 $3.450 $4.000 $6.000 $2.000 $3.700 $4.000
672 6009 REFL PAV MRKR TY II-A-A EA 10.000 $5.000 $80.000 $75.000 $110.000 $75.000 $106.000 $75.000 $85.000 $12.000 $10.000 $80.000 $88.000
Totals: $569,951.38 $514,522.70 $523,056.65 $535,442.05 $548,468.32 $555,092.16 $557,084.82 $579,688.93 $625,417.00 $658,249.25 $708,974.83 $744,144.00