Job Info for 0751-03-043

County: KAUFMAN Highway: FM 148 Date: 04/04/2024 (7 months ago) Engineer's Estimate: $10,945,983 Control Number: 0751-03-043
Project: F 2024(168) District: DALLAS Time: 294 WORKING DAYS Type: REHABILITATE EXISTING ROADWAY
Bidder's List
Informational:
Email All | Notice | Questions
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $10,945,982.68
BAKER & COMPANY CONSTRUCTION, LLC   $9,345,341.95 1
-14.62% | -$1,600,640.73
A. K. GILLIS & SONS, LLC   $9,974,948.77 2
-8.87% | -$971,033.91
6.74% | $629,606.82
A. L. HELMCAMP, INC.   $11,841,139.22 3
8.18% | $895,156.54
26.71% | $2,495,797.27
18.71% | $1,866,190.45
ED BELL CONSTRUCTION COMPANY   $12,149,627.75 4
11% | $1,203,645.07
30.01% | $2,804,285.80
2.61% | $308,488.53
FNH CONSTRUCTION, LLC   $12,345,383.75 5
12.78% | $1,399,401.07
32.1% | $3,000,041.80
1.61% | $195,756.00
Subcontractor Percentage Amount
TEXANA LAND & ASPHALT, INC. 28.15% $2,630,713.76
JM YANEZ CONSTRUCTION, INC. 6.51% $608,381.76
NEED GRASS NOW LLC 3.09% $288,771.07
USA SWPPP INSPECTIONS, INC.DBA USA EROSION 1.94% $181,299.63
STRIPING TECHNOLOGY, L.P. 1.26% $117,751.31
COLD CREEK CONSTRUCTION, LTD 1.16% $108,405.97
SOUTHWEST ENVIRONMENT SERVICES LLC 0.73% $68,221.00
AWP SAFETY 0.69% $64,482.86
A. L. HELMCAMP, INC. 0.34% $31,774.16
FLEX SUPPLY, LLC 0.32% $29,905.09
DUSTROL, INC. 0.13% $12,148.94
PROFESSIONAL TRAFFIC CONTROL LLC 0.13% $12,148.94
CARTHAGE DRILLING, LLC 0.01% $934.53
Total: 44.46% $4,154,939.02

Bid Items

Items: 111, 0 filtered
KAUFMAN FM 148  |  DALLAS  |  0751-03-043  |  04/04/2024  |  $10,945,983  |  F 2024(168)  |  REHAB EXIST ROADWAY  |  294 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate BAKER & COMPANY CONSTRUCTION, LLC A. K. GILLIS & SONS, LLC A. L. HELMCAMP, INC. ED BELL CONSTRUCTION COMPANY FNH CONSTRUCTION, LLC
100 6002 PREPARING ROW STA 250.640 $1,500.000 $642.000 $699.000 $500.000 $1,500.000 $4,000.000
104 6017 REMOVING CONC (DRIVEWAYS) SY 51.000 $45.000 $18.300 $15.000 $20.000 $31.500 $50.000
105 6043 REMOVING STAB BASE & ASPH PAV (0-6") SY 6,221.000 $15.000 $6.000 $17.500 $20.000 $8.400 $20.000
105 6137 REMOVE TRT BASE & ASPH PAV (12"-20") SY 14,956.000 $20.450 $11.750 $23.000 $15.000 $15.750 $20.000
110 6001 EXCAVATION (ROADWAY) CY 936.300 $21.670 $26.750 $14.970 $30.000 $52.500 $20.000
112 6001 SUBGRADE WIDENING (ORD COMP) STA 188.330 $487.500 $189.000 $243.400 $500.000 $997.500 $450.000
132 6005 EMBANKMENT (FINAL)(ORD COMP)(TY C) CY 5,376.750 $55.000 $29.000 $15.640 $75.000 $43.000 $30.000
134 6004 BACKFILL (TY A OR B) STA 249.420 $269.000 $303.000 $405.770 $200.000 $315.000 $450.000
152 6001 ROAD GRADER WORK (ORD COMP) STA 249.420 $250.000 $192.000 $245.050 $250.000 $525.000 $450.000
161 6017 COMPOST MANUF TOPSOIL (4") SY 144,802.000 $4.500 $1.650 $1.500 $1.500 $1.000 $3.000
164 6035 DRILL SEEDING (PERM) (RURAL) (CLAY) SY 144,802.000 $0.360 $0.300 $0.150 $0.140 $0.150 $0.500
164 6051 DRILL SEED (TEMP)(WARM OR COOL) SY 144,802.000 $1.000 $0.300 $0.150 $0.120 $0.130 $0.500
168 6001 VEGETATIVE WATERING MG 43,085.000 $1.500 $1.000 $0.950 $1.000 $1.050 $2.000
247 6073 FL BS (CMP IN PLC)(TY D GR 1-2) (6") SY 18,691.000 $14.000 $16.750 $14.200 $22.000 $20.000 $20.000
247 6313 FL BS (CMP IN PLC)(TY D GR1-2)(12") SY 76,039.000 $29.000 $28.600 $28.450 $35.000 $33.000 $29.000
251 6073 REWRKING BS MATL (TY C)(10")(ORD COMP) SY 50,220.000 $3.160 $4.000 $3.110 $4.000 $3.000 $6.000
275 6001 CEMENT TON 479.000 $295.000 $303.000 $275.000 $310.000 $275.000 $325.000
275 6002 CEMENT TREAT (EXIST MATL) (6") SY 62,775.000 $5.000 $2.650 $3.250 $4.000 $3.000 $6.000
275 6003 CEMENT TREAT (NEW BASE) (6") SY 18,691.000 $5.000 $5.600 $3.270 $6.000 $3.000 $6.000
314 6021 EMULS ASPH (PRIME)(MS-2 OR SS-1) GAL 15,213.000 $5.000 $9.500 $4.550 $7.000 $10.500 $6.000
316 6024 ASPH (CRS-2P) GAL 37,548.000 $5.000 $7.950 $4.820 $6.000 $5.250 $6.000
316 6419 ASPH (AC-15P, AC-20-5TR OR AC-20XP) GAL 15,972.000 $5.000 $7.750 $5.240 $6.000 $6.300 $6.000
316 6435 AGGR (TY-B GR-4 OR TY-L GR-4 SAC-B) CY 356.000 $265.000 $178.000 $160.190 $500.000 $288.200 $300.000
316 6440 AGGR (TY-B GR-3 OR TY-L GR-3)(SAC-B) CY 727.000 $265.000 $189.000 $169.550 $300.000 $310.200 $300.000
351 6002 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") SY 197.000 $85.000 $109.000 $195.000 $400.000 $189.000 $85.000
354 6045 PLANE ASPH CONC PAV (2") SY 1,958.000 $3.500 $7.000 $7.130 $10.000 $6.300 $20.000
400 6008 CUT & RESTORE ASPH PAVING SY 72.000 $210.000 $195.000 $100.000 $110.000 $315.000 $200.000
402 6001 TRENCH EXCAVATION PROTECTION LF 128.000 $15.000 $49.000 $15.000 $16.500 $52.500 $10.000
403 6001 TEMPORARY SPL SHORING SF 4,754.000 $45.000 $52.400 $25.000 $55.000 $73.500 $55.000
432 6002 RIPRAP (CONC)(5 IN) CY 29.600 $650.000 $963.000 $650.000 $715.000 $1,365.000 $650.000
432 6026 RIPRAP (STONE COMMON)(DRY)(18 IN) CY 367.000 $200.000 $140.000 $310.400 $275.000 $525.000 $250.000
462 6045 CONC BOX CULV (3 FT X 2 FT)(EXTEND) LF 19.000 $800.000 $495.000 $800.000 $880.000 $760.000 $1,000.000
462 6046 CONC BOX CULV (3 FT X 3 FT)(EXTEND) LF 14.000 $800.000 $605.000 $850.000 $935.000 $900.000 $1,000.000
462 6048 CONC BOX CULV (4 FT X 3 FT)(EXTEND) LF 16.000 $900.000 $688.000 $900.000 $990.000 $1,025.000 $1,000.000
462 6049 CONC BOX CULV (4 FT X 4 FT)(EXTEND) LF 18.000 $900.000 $770.000 $950.000 $1,045.000 $1,105.000 $1,250.000
462 6050 CONC BOX CULV (5 FT X 2 FT)(EXTEND) LF 14.000 $1,000.000 $798.000 $850.000 $935.000 $1,175.000 $1,500.000
462 6051 CONC BOX CULV (5 FT X 3 FT)(EXTEND) LF 40.000 $1,000.000 $825.000 $950.000 $1,045.000 $1,225.000 $1,600.000
462 6054 CONC BOX CULV (6 FT X 3 FT)(EXTEND) LF 30.000 $1,250.000 $880.000 $1,000.000 $1,100.000 $1,275.000 $1,700.000
462 6056 CONC BOX CULV (6 FT X 5 FT)(EXTEND) LF 45.000 $1,500.000 $935.000 $1,100.000 $1,210.000 $1,375.000 $1,800.000
462 6057 CONC BOX CULV (6 FT X 6 FT)(EXTEND) LF 28.000 $1,500.000 $990.000 $1,200.000 $1,320.000 $1,525.000 $1,900.000
462 6095 CONC BOX CULV (6 FT X 2 FT) (EXTEND) LF 14.000 $1,250.000 $798.000 $900.000 $990.000 $1,475.000 $1,500.000
464 6003 RC PIPE (CL III)(18 IN) LF 1,466.000 $110.000 $61.000 $60.000 $66.000 $80.000 $85.000
464 6005 RC PIPE (CL III)(24 IN) LF 308.000 $133.000 $92.000 $95.000 $105.000 $100.000 $125.000
464 6008 RC PIPE (CL III)(36 IN) LF 38.000 $175.000 $262.000 $245.000 $270.000 $150.000 $165.000
464 6018 RC PIPE (CL IV)(24 IN) LF 116.000 $150.000 $134.000 $130.000 $145.000 $280.000 $160.000
464 6019 RC PIPE (CL IV)(30 IN) LF 98.000 $190.000 $158.000 $185.000 $204.000 $300.000 $185.000
466 6097 HEADWALL (CH - PW - 0) (DIA= 24 IN) EA 2.000 $5,500.000 $6,325.000 $6,500.000 $7,150.000 $6,300.000 $3,500.000
466 6099 HEADWALL (CH - PW - 0) (DIA= 30 IN) EA 2.000 $6,500.000 $7,975.000 $8,000.000 $8,800.000 $8,400.000 $4,500.000
466 6192 WINGWALL (PW - 2) (HW=3 FT) EA 2.000 $9,000.000 $10,450.000 $10,000.000 $11,000.000 $7,350.000 $8,500.000
466 6193 WINGWALL (PW - 2) (HW=4 FT) EA 4.000 $10,000.000 $13,365.000 $13,000.000 $14,300.000 $9,450.000 $12,500.000
466 6194 WINGWALL (PW - 2) (HW=5 FT) EA 2.000 $12,000.000 $16,775.000 $19,000.000 $20,900.000 $14,700.000 $15,000.000
466 6195 WINGWALL (PW - 2) (HW=6 FT) EA 2.000 $14,000.000 $18,535.000 $25,000.000 $27,500.000 $23,100.000 $22,000.000
466 6196 WINGWALL (PW - 2) (HW=7 FT) EA 2.000 $16,000.000 $19,525.000 $30,000.000 $33,000.000 $34,650.000 $30,000.000
467 6111 SET (TY I)(S=3 FT)(HW= 4 FT)(3:1)(C) EA 2.000 $10,000.000 $11,070.000 $9,500.000 $10,450.000 $13,650.000 $12,500.000
467 6144 SET (TY I)(S= 4 FT)(HW= 4 FT)(4:1) (C) EA 2.000 $12,000.000 $11,920.000 $10,000.000 $11,000.000 $14,700.000 $14,500.000
467 6171 SET (TY I)(S= 5 FT)(HW= 3 FT)(3:1) (C) EA 2.000 $14,000.000 $14,460.000 $10,000.000 $11,000.000 $9,450.000 $17,500.000
467 6204 SET (TY I)(S= 6 FT)(HW= 3 FT)(3:1) (C) EA 2.000 $16,000.000 $14,735.000 $10,500.000 $11,550.000 $10,500.000 $18,500.000
467 6211 SET (TY I)(S= 6 FT)(HW= 4 FT)(3:1) (C) EA 2.000 $18,000.000 $17,060.000 $12,000.000 $13,200.000 $16,800.000 $19,000.000
467 6363 SET (TY II) (18 IN) (RCP) (6: 1) (P) EA 117.000 $1,000.000 $915.000 $900.000 $990.000 $840.000 $1,250.000
467 6390 SET (TY II) (24 IN) (RCP) (4: 1) (C) EA 4.000 $1,500.000 $1,826.000 $1,200.000 $1,320.000 $945.000 $2,200.000
467 6395 SET (TY II) (24 IN) (RCP) (6: 1) (P) EA 28.000 $1,500.000 $1,435.000 $1,400.000 $1,540.000 $1,050.000 $2,200.000
467 6419 SET (TY II) (30 IN) (RCP) (4: 1) (C) EA 2.000 $2,500.000 $2,755.000 $2,500.000 $2,750.000 $1,260.000 $3,650.000
467 6454 SET (TY II) (36 IN) (RCP) (6: 1) (P) EA 2.000 $3,200.000 $7,050.000 $7,500.000 $8,250.000 $3,150.000 $4,500.000
480 6001 CLEAN EXIST CULVERTS EA 12.000 $1,600.000 $2,060.000 $1,200.000 $1,320.000 $2,100.000 $1,500.000
496 6004 REMOV STR (SET) EA 72.000 $500.000 $515.000 $300.000 $330.000 $210.000 $500.000
496 6005 REMOV STR (WINGWALL) EA 22.000 $1,600.000 $2,190.000 $1,200.000 $1,320.000 $3,675.000 $1,000.000
496 6007 REMOV STR (PIPE) LF 175.800 $50.000 $47.000 $15.000 $16.500 $63.000 $50.000
496 6016 REMOV STR (PIPE) EA 60.000 $500.000 $412.000 $350.000 $385.000 $420.000 $500.000
500 6001 MOBILIZATION LS 1.000 $976,789.330 $480,000.000 $969,506.000 $975,000.000 $1,148,000.000 $1,200,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 18.000 $10,000.000 $14,370.000 $28,668.330 $35,000.000 $42,000.000 $8,500.000
506 6003 ROCK FILTER DAMS (INSTALL) (TY 3) LF 1,170.000 $65.000 $110.000 $75.000 $82.500 $105.000 $30.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 1,170.000 $10.000 $11.000 $15.000 $14.000 $26.250 $15.000
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 328.000 $30.000 $49.000 $40.000 $30.000 $36.750 $50.000
506 6024 CONSTRUCTION EXITS (REMOVE) SY 328.000 $15.000 $17.000 $15.000 $5.000 $15.750 $20.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 2,042.000 $3.000 $3.850 $4.500 $4.000 $3.150 $4.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 2,042.000 $1.000 $1.650 $1.500 $1.000 $1.050 $2.000
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 2,111.000 $6.000 $3.850 $5.000 $6.000 $5.250 $18.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 2,111.000 $1.000 $1.650 $1.000 $1.250 $1.050 $9.000
530 6005 DRIVEWAYS (ACP) SY 5,791.000 $60.000 $44.000 $103.220 $80.000 $94.500 $40.000
530 6017 DRIVEWAYS (CONC) (HES) SY 52.000 $150.000 $204.000 $125.000 $140.000 $175.000 $150.000
533 6003 RUMBLE STRIPS (SHOULDER) ASPHALT LF 49,535.000 $0.250 $0.250 $0.120 $0.250 $0.150 $0.500
533 6004 RUMBLE STRIPS (CENTERLINE) ASPHALT LF 25,062.000 $0.250 $0.250 $0.120 $0.300 $0.150 $0.500
542 6001 REMOVE METAL BEAM GUARD FENCE LF 375.000 $3.000 $2.300 $5.000 $20.000 $5.330 $3.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 4.000 $250.000 $216.000 $300.000 $500.000 $319.500 $1,500.000
560 6011 MAILBOX INSTALL-S (TWW-POST) TY 4 EA 40.000 $300.000 $325.000 $295.000 $308.000 $314.180 $850.000
560 6012 MAILBOX INSTALL-D (TWW-POST) TY 4 EA 6.000 $320.000 $370.000 $305.000 $330.000 $324.830 $850.000
560 6013 MAILBOX INSTALL-M (TWW-POST) TY 4 EA 3.000 $725.000 $755.000 $695.000 $605.000 $740.180 $850.000
644 6001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 52.000 $1,000.000 $720.000 $650.000 $687.500 $692.250 $1,150.000
644 6004 IN SM RD SN SUP&AM TY10BWG(1)SA(T) EA 1.000 $1,000.000 $820.000 $725.000 $742.500 $772.130 $1,150.000
644 6007 IN SM RD SN SUP&AM TY10BWG(1)SA(U) EA 4.000 $1,100.000 $1,030.000 $960.000 $935.000 $1,022.400 $1,150.000
644 6033 IN SM RD SN SUP&AM TYS80(1)SA(U) EA 1.000 $1,250.000 $1,144.000 $835.000 $792.000 $889.280 $1,150.000
644 6036 IN SM RD SN SUP&AM TYS80(1)SA(U-BM) EA 5.000 $1,500.000 $1,293.000 $1,250.000 $1,078.000 $1,331.250 $1,150.000
658 6100 INSTL OM ASSM (OM-2Z)(WFLX)GND(BI) EA 44.000 $70.000 $94.000 $55.000 $60.500 $58.580 $100.000
662 6111 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 EA 3,133.000 $1.630 $1.650 $2.350 $0.820 $4.910 $6.000
666 6048 REFL PAV MRK TY I (W)24"(SLD)(100MIL) LF 140.000 $10.350 $7.150 $12.650 $13.920 $13.470 $9.000
666 6174 REFL PAV MRK TY II (W) 6" (SLD) LF 126,185.000 $0.330 $0.300 $0.230 $0.250 $0.240 $0.350
666 6208 REFL PAV MRK TY II (Y) 6" (BRK) LF 7,025.000 $0.330 $0.350 $0.250 $0.280 $0.270 $0.750
666 6210 REFL PAV MRK TY II (Y) 6" (SLD) LF 73,443.000 $0.330 $0.300 $0.230 $0.250 $0.240 $0.500
666 6225 PAVEMENT SEALER 6" LF 366.000 $2.000 $1.100 $0.500 $0.550 $0.530 $6.000
666 6309 RE PM W/RET REQ TY I (W)6"(SLD)(100MIL) LF 49,535.000 $1.040 $0.850 $0.660 $0.730 $0.700 $0.750
666 6318 RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL) LF 2,789.000 $1.000 $1.100 $0.670 $0.740 $0.710 $1.500
666 6321 RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL) LF 29,338.000 $1.040 $0.850 $0.660 $0.730 $0.700 $0.750
672 6009 REFL PAV MRKR TY II-A-A EA 562.000 $5.950 $4.950 $5.250 $5.780 $5.590 $6.000
678 6002 PAV SURF PREP FOR MRK (6") LF 366.000 $1.000 $1.100 $0.250 $0.280 $0.270 $6.000
730 6107 FULL - WIDTH MOWING CYC 3.000 $3,500.000 $5,500.000 $5,000.000 $6,500.000 $5,250.000 $5,000.000
3077 6013 SP MIXES SP-C SAC-B PG64-22 TON 8,588.000 $145.000 $153.000 $150.700 $170.000 $168.000 $155.000
3077 6075 TACK COAT GAL 4,788.000 $4.450 $0.110 $3.750 $5.000 $4.200 $5.000
5001 6002 GEOGRID BASE REINFORCEMENT (TY II) SY 40,097.000 $2.650 $2.150 $1.800 $3.000 $2.500 $4.000
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 3.000 $15,000.000 $5,250.000 $17,500.000 $20,000.000 $15,750.000 $22,000.000
6185 6002 TMA (STATIONARY) DAY 294.000 $300.000 $320.000 $150.000 $300.000 $157.500 $250.000
6185 6005 TMA (MOBILE OPERATION) DAY 20.000 $500.000 $1,600.000 $150.000 $750.000 $1,050.000 $550.000
Totals: $10,945,982.68 $9,345,341.95 $9,974,948.78 $11,841,139.22 $12,149,627.76 $12,345,383.75