KAUFMAN SH 274 (0561-01-024)

Items: 49

County: KAUFMAN
Length: N/A
Highway: SH 274
District: DALLAS
Control Number: 0561-01-024
DBE Goal: N/A
Project: STP 2019(719)
Guaranty: N/A
Time: 96 WORKING DAYS
Engineer's Estimate: $3,733,824.66
Date: 04/03/2019 (7 years ago)
Contract Number: N/A
Type: REHABILITATE EXISTING PAVMENT AND SLOPE FAIL RPR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$3,733,824.66
$3,753,154.82
Over/Under Est: 0.52% $19,330.16
Over/Under Est: 3.64% $135,948.43
Amt Left: 3.11% $116,618.27
Over/Under Est: 9.91% $369,946.04
Amt Left: 9.34% $350,615.88
Delta: -6.05% -$233,997.61
$4,182,119.69
Over/Under Est: 12.01% $448,295.03
Amt Left: 11.43% $428,964.87
Delta: -1.91% -$78,348.99
Over/Under Est: 25% $933,290.36
Amt Left: 24.35% $913,960.20
Delta: -11.60% -$484,995.33
$5,080,832.55
Over/Under Est: 36.08% $1,347,007.89
Amt Left: 35.37% $1,327,677.73
Delta: -8.86% -$413,717.53

Bid Items & Bid Tabulations

49 Total 0 of 49
KAUFMAN  |  SH 274  |  DALLAS  |  0561-01-024  |  04/03/2019  |  $3,733,824.66  |  STP 2019(719)  |  REHAB EXIST PAVMENT AND SLOPE FAIL R...  |  96 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS MATERIALS GROUP, INC.
ED BELL CONSTRUCTION COMPANY
EAST TEXAS BRIDGE, INC.
A. L. HELMCAMP, INC.
LONGVIEW BRIDGE AND ROAD, LTD.
FNH CONSTRUCTION, LLC
PREPARING ROW
STA 52.000 $2,500.000 $1,230.000 $1,575.000 $1,000.000 $600.000 $1,250.000 $6,500.000
REMOVING STAB BASE AND ASPH PAV(15")
SY 3,280.000 $6.750 $10.250 $11.000 $10.000 $12.000 $7.000 $20.000
EXCAVATION (ROADWAY)
CY 10,000.000 $7.200 $12.500 $10.000 $10.000 $11.000 $15.000 $17.500
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 10,000.000 $11.550 $16.000 $10.000 $10.000 $18.000 $18.000 $25.000
BACKFILL (TY A OR B)
STA 320.000 $140.000 $183.000 $150.000 $300.000 $180.000 $210.000 $250.000
COMPOST MANUF TOPSOIL (4")
SY 19,360.000 $0.700 $0.950 $0.800 $2.000 $1.150 $3.000 $2.500
BLOCK SODDING
SY 19,360.000 $3.000 $3.300 $3.150 $4.000 $4.000 $4.250 $4.000
DRILL SEED (TEMP)(WARM OR COOL)
SY 6,446.000 $0.700 $0.420 $0.100 $0.400 $0.600 $0.280 $1.000
VEGETATIVE WATERING
MG 1,969.000 $5.000 $0.010 $1.050 $8.000 $10.000 $11.500 $25.000
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
CY 1,185.000 $72.000 $66.000 $57.500 $45.000 $65.000 $90.000 $90.000
SUPERPAVE MIXTURES SP-C SAC-B PG64-22
TON 18,267.000 $80.000 $85.000 $87.500 $95.000 $95.000 $100.000 $98.000
SUPERPAVE MIXTURES SP-C PG64-22(LEV-UP)
TON 1,030.000 $78.000 $93.300 $101.000 $115.000 $113.000 $116.000 $140.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(13")
SY 7,000.000 $120.000 $75.000 $84.000 $105.000 $85.000 $120.000 $75.000
PLANE ASPH CONC PAV (2")
SY 165,942.000 $1.250 $1.340 $1.420 $1.500 $1.600 $2.150 $2.500
RIPRAP (MOW STRIP)(4 IN)
CY 74.000 $450.000 $600.000 $630.000 $475.000 $700.000 $480.000 $500.000
MOBILIZATION
LS 1.000 $280,000.000 $298,000.000 $380,000.000 $200,000.000 $400,000.000 $365,000.000 $500,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $8,500.000 $15,745.000 $21,000.000 $6,000.000 $18,000.000 $4,500.000 $8,500.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 126.000 $24.000 $29.000 $22.840 $33.000 $40.000 $23.000 $30.000
ROCK FILTER DAMS (REMOVE)
LF 126.000 $5.000 $10.000 $10.500 $10.000 $7.500 $7.700 $15.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 250.000 $20.000 $16.000 $22.050 $26.000 $10.000 $22.250 $40.000
CONSTRUCTION EXITS (REMOVE)
SY 250.000 $5.000 $8.000 $11.550 $10.000 $2.000 $9.000 $20.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 6,085.000 $1.700 $1.500 $1.470 $3.500 $2.500 $1.850 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 6,085.000 $0.400 $0.440 $0.110 $1.000 $1.000 $0.550 $2.000
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 49,826.000 $0.100 $0.130 $0.090 $0.300 $0.200 $0.170 $0.250
RUMBLE STRIPS (CENTERLINE) ASPHALT
LF 24,913.000 $0.160 $0.180 $0.090 $0.300 $0.200 $0.170 $0.250
MTL W-BEAM GD FEN (TIM POST)
LF 2,339.000 $19.000 $20.000 $19.340 $23.000 $18.250 $22.000 $20.000
TERMINAL ANCHOR SECTION
EA 16.000 $1,800.000 $2,650.000 $2,651.250 $3,000.000 $960.000 $2,750.000 $1,500.000
MTL THRIE-BEAM GD FEN (TIM POST)
EA 4.000 $1,929.000 $1,395.000 $1,401.750 $1,800.000 $1,710.000 $1,500.000 $1,500.000
REMOVE METAL BEAM GUARD FENCE
LF 2,339.000 $2.700 $3.050 $3.150 $3.000 $2.100 $2.500 $3.000
REMOVE TERMINAL ANCHOR SECTION
EA 16.000 $215.000 $235.000 $236.250 $250.000 $270.000 $220.000 $850.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 11.000 $400.000 $525.000 $472.500 $700.000 $375.000 $825.000 $550.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 63,056.000 $0.180 $0.350 $0.370 $0.380 $0.370 $0.380 $0.400
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 63,056.000 $0.180 $0.350 $0.370 $0.380 $0.370 $0.380 $0.400
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 655.000 $0.950 $1.020 $2.100 $2.000 $0.510 $1.200 $5.000
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 2,526.000 $0.950 $1.020 $2.100 $2.000 $0.510 $1.200 $5.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 1,265.000 $0.750 $1.050 $1.050 $1.100 $1.050 $1.100 $6.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 180.000 $4.700 $5.750 $5.780 $6.000 $5.780 $6.000 $20.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 11.000 $106.000 $145.000 $147.000 $150.000 $147.000 $155.000 $250.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 11.000 $130.000 $185.000 $189.000 $200.000 $189.000 $200.000 $250.000
PAVEMENT SEALER 4"
LF 3,760.000 $0.800 $0.520 $0.530 $0.550 $0.530 $0.550 $1.000
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 21,016.000 $0.150 $0.500 $0.500 $0.540 $0.500 $0.520 $0.500
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 64,936.000 $0.120 $0.420 $0.420 $0.450 $0.420 $0.440 $0.500
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 64,936.000 $0.300 $0.420 $0.420 $0.450 $0.420 $0.440 $0.500
REFL PAV MRKR TY I-C
EA 724.000 $3.450 $3.450 $3.470 $4.000 $3.500 $3.650 $15.000
REFL PAV MRKR TY II-A-A
EA 449.000 $2.700 $3.450 $3.470 $4.000 $3.500 $3.650 $15.000
ELIM EXT PAV MRK & MRKS (4")
LF 3,760.000 $0.450 $1.050 $1.050 $1.100 $1.100 $1.100 $0.500
PAV SURF PREP FOR MRK (4")
LF 3,760.000 $0.350 $0.260 $0.260 $0.300 $0.250 $0.280 $0.500
TMA (STATIONARY)
EA 3.000 $5,000.000 $14,000.000 $7,350.000 $30,000.000 $15,000.000 $15,000.000 $15,000.000
TMA (MOBILE OPERATION)
HR 264.000 $80.000 $57.000 $10.500 $30.000 $40.000 $11.000 $85.000
Totals: $3,733,824.660 $3,753,154.820 $3,869,773.090 $4,103,770.700 $4,182,119.690 $4,667,115.020 $5,080,832.550