County: KAUFMAN Highway: IH 20 Date: 07/12/2017 (7 years ago) Engineer's Estimate: $10,384,459 Control Number: 0495-01-074
Project: NH 1702(759) District: DALLAS Time: 120 WORKING DAYS Type: MILL AND OVERLAY EXISTING FREEWAY

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $10,384,458.79
OLDCASTLE MATERIALS TEXAS, INC.   $9,178,944.71 1
-11.61% | -$1,205,514.08
AUSTIN BRIDGE & ROAD SERVICES, LP   $9,424,937.03 2
-9.24% | -$959,521.76
2.68% | $245,992.32
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY   $9,726,748.08 3
-6.33% | -$657,710.71
5.97% | $547,803.37
3.20% | $301,811.05
PEACHTREE CONSTRUCTION, LTD.   $10,508,610.04 4
1.2% | $124,151.25
14.49% | $1,329,665.33
8.04% | $781,861.96
EAST TEXAS BRIDGE, INC.   $13,145,097.80 5
26.58% | $2,760,639.01
43.21% | $3,966,153.09
25.09% | $2,636,487.76
RK HALL, LLC   $14,786,732.11 6
42.39% | $4,402,273.32
61.09% | $5,607,787.40
12.49% | $1,641,634.31

Bid Items

Items: 39, 0 filtered
KAUFMAN IH 20  |  DALLAS  |  0495-01-074  |  07/12/2017  |  $10,384,459  |  NH 1702(759)  |  MILL AND OVERLAY EXIST FREEWAY  |  120 WORKING DAYS
Alt Item code Description Unit Quantity Engineer's Estimate OLDCASTLE MATERIALS TEXAS, INC. AUSTIN BRIDGE & ROAD SERVICES, LP JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY PEACHTREE CONSTRUCTION, LTD. EAST TEXAS BRIDGE, INC. RK HALL, LLC
134 6004 BACKFILL (TY A OR B) STA 640.360 $175.000 $190.000 $370.000 $150.000 $300.000 $350.000 $320.000
164 6066 DRILL SEEDING (PERM)(WARM OR COOL) SY 248,292.000 $0.150 $0.205 $0.090 $0.140 $0.200 $0.300 $0.130
247 6133 FL BS (RDWY DEL) (TY D GR 1-2) TON 638.000 $25.000 $30.000 $31.000 $60.000 $50.000 $75.000 $52.000
251 6035 REWORK BS MTL (TY C) (6") (DENS CONT) SY 3,355.000 $1.900 $6.350 $14.000 $12.000 $31.000 $15.000 $16.110
310 6027 PRIME COAT(MC-30 OR AE-P) GAL 671.000 $4.150 $4.450 $6.500 $4.000 $7.500 $10.000 $5.650
344 6106 SUPERPAVE MIXTURES SP-D PG64-22 TON 14,582.000 $68.000 $71.500 $70.600 $66.000 $69.500 $95.000 $100.400
344 6168 SUPERPAVE MIXTURES SP-D PG64-22(LEV-UP) TON 290.000 $100.000 $78.000 $92.000 $110.000 $140.000 $200.000 $155.000
346 6002 STONE-MTRX-ASPH SMA-C SAC-A PG76-22 TON 67,259.000 $98.000 $85.500 $84.000 $90.000 $95.500 $122.000 $143.000
351 6008 FLEXIBLE PAVEMENT STRUCTURE REPAIR(12") SY 3,355.000 $50.000 $62.500 $55.000 $100.000 $75.000 $100.000 $84.000
354 6045 PLANE ASPH CONC PAV (2") SY 98,321.000 $1.500 $2.400 $1.500 $1.750 $2.800 $2.500 $2.600
356 6021 PAV JT UNDERSEAL (24") LF 3,000.000 $23.150 $44.000 $12.150 $30.000 $62.000 $30.000 $20.000
438 6010 RESIZING AND SEALING JOINTS LF 3,000.000 $18.700 $23.500 $12.500 $12.000 $44.000 $20.000 $15.500
500 6001 MOBILIZATION LS 1.000 $850,000.000 $231,330.000 $930,450.000 $655,000.000 $550,000.000 $1,000,000.000 $1,225,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 6.000 $12,500.000 $19,000.000 $16,200.000 $15,000.000 $10,500.000 $20,000.000 $2,500.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 3,000.000 $2.200 $1.550 $1.500 $1.500 $1.600 $4.000 $2.700
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 3,000.000 $0.490 $0.520 $0.500 $0.500 $0.560 $1.000 $0.540
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 1,200.000 $2.500 $4.300 $4.250 $4.250 $4.000 $7.000 $4.860
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 1,200.000 $1.000 $0.780 $0.750 $0.750 $1.300 $1.000 $1.080
533 6001 RUMBLE STRIPS (SHOULDER) LF 174,684.000 $0.140 $0.132 $0.080 $0.100 $0.130 $0.250 $0.130
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 15,881.000 $20.400 $20.500 $22.000 $18.500 $20.000 $22.000 $21.600
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 41.000 $1,820.000 $1,400.000 $1,390.000 $1,390.000 $1,700.000 $1,700.000 $1,485.000
540 6016 DOWNSTREAM ANCHOR TERMINAL SECTION EA 37.000 $1,008.000 $1,230.000 $890.000 $890.000 $1,100.000 $1,300.000 $1,323.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 15,881.000 $2.500 $4.020 $1.500 $1.500 $2.200 $3.000 $4.320
542 6003 REMOVE DOWNSTREAM ANCHOR TERMINAL EA 37.000 $100.000 $126.000 $100.000 $100.000 $275.000 $250.000 $135.000
542 6004 RM MTL BM GD FENCE TRANS (THRIE-BEAM) EA 41.000 $215.000 $252.000 $100.000 $100.000 $275.000 $250.000 $270.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 55.000 $2,303.000 $1,985.000 $1,910.000 $1,910.000 $2,450.000 $2,400.000 $2,122.200
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 55.000 $256.000 $252.000 $150.000 $150.000 $275.000 $300.000 $270.000
658 6061 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2 EA 139.000 $23.500 $42.200 $20.000 $34.000 $38.000 $40.000 $45.360
658 6064 INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2 EA 104.000 $28.000 $42.200 $20.000 $37.000 $41.000 $40.000 $45.360
662 6111 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 EA 3,704.000 $0.250 $1.000 $0.680 $0.500 $1.800 $2.000 $2.000
666 6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL) LF 4,500.000 $0.270 $0.760 $0.850 $0.850 $1.000 $1.000 $0.920
666 6300 RE PM W/RET REQ TY I (W)4"(BRK)(100MIL) LF 32,018.000 $0.460 $0.360 $0.300 $0.350 $0.400 $0.350 $0.320
666 6303 RE PM W/RET REQ TY I (W)4"(SLD)(100MIL) LF 131,262.000 $0.350 $0.305 $0.300 $0.250 $0.380 $0.350 $0.320
666 6315 RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) LF 127,572.000 $0.350 $0.305 $0.300 $0.250 $0.380 $0.350 $0.320
672 6007 REFL PAV MRKR TY I-C EA 1,653.000 $3.000 $3.050 $2.750 $3.250 $3.800 $3.500 $2.970
672 6009 REFL PAV MRKR TY II-A-A EA 3,004.000 $3.000 $3.050 $2.750 $3.250 $3.800 $3.500 $2.970
3019 6001 TRACKLESS TACK COAT GAL 103,529.000 $4.000 $3.350 $0.000 $4.000 $3.200 $0.000 $0.000
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 2.000 $12,500.000 $9,500.000 $6,000.000 $5,500.000 $20,000.000 $20,000.000 $20,000.000
1 3002 6001 MEMBRANE UNDERSEAL GAL 103,529.000 $4.000 $0.000 $2.140 $0.000 $0.000 $3.000 $5.500
Totals: $10,798,574.79 $9,178,944.72 $9,424,937.03 $9,726,748.08 $10,508,610.04 $13,145,097.80 $14,786,732.11