KAUFMAN US 175 (0197-04-086)

Items: 66

County: KAUFMAN
Length: N/A
Highway: US 175
District: DALLAS
Control Number: 0197-04-086
DBE Goal: 450.0%
Project: F 2B24(336)
Guaranty: N/A
Time: 240 WORKING DAYS
Engineer's Estimate: $6,095,724.53
Date: 08/02/2024 (1 year ago)
Contract Number: N/A
Type: INTERSECTION IMPROVEMENT
Mail/Deliver Bids To: N/A
LANE SELMAN
NICHOLAS WADLINGTON
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$6,095,724.53
$5,405,602.01
Over/Under Est: -11.32% -$690,122.52
Over/Under Est: -10.63% -$647,732.89
Amt Left: 0.78% $42,389.63
Over/Under Est: 0.16% $10,031.72
Amt Left: 12.95% $700,154.24
Delta: -12.07% -$657,764.61
$6,732,618.45
Over/Under Est: 10.45% $636,893.92
Amt Left: 24.55% $1,327,016.44
Delta: -10.27% -$626,862.20
$7,264,209.05
Over/Under Est: 19.17% $1,168,484.52
Amt Left: 34.38% $1,858,607.04
Delta: -7.90% -$531,590.60
Subcontractor Percentage Amount
PEACHTREE CONSTRUCTION, LTD. 28.30% $1,563,083.16
Q. ROBERTS TRUCKING INCORPORATED 8.66% $478,314.49
TRP CONSTRUCTION GROUP, LLC 6.51% $359,564.36
Q. ROBERTS TRUCKING INCORPORATED 4.94% $272,849.15
USA SWPPP INSPECTIONS, INC.DBA USA EROSION 2.09% $115,436.18
TEX OP CONSTRUCTION, LP 1.56% $86,162.89
SK CONCRETE SERVICES LLC 0.86% $47,500.05
AWP SAFETY 0.58% $32,034.92
J. RUEDAS TRUCKING, LLC 0.53% $29,273.29
FC TRAFFIC CONTROL, INC. 0.37% $20,436.07
NEXT GENERATION CONSTRUCTION & ENVIRONMENTAL, LLC 0.36% $19,883.74
DALLAS LITE AND BARRICADE, INC. 0.18% $9,941.87
COWBOY TRUCKING 0.02% $1,104.65
Total: 54.96% $3,035,584.82

Bid Items & Bid Tabulations

66 Total 0 of 66
KAUFMAN  |  US 175  |  DALLAS  |  0197-04-086  |  08/02/2024  |  $6,095,724.53  |  F 2B24(336)  |  INTERS IMPRV  |  240 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
GRANITE CONSTRUCTION COMPANY
ED BELL CONSTRUCTION COMPANY
TEXAS MATERIALS GROUP, INC.
A. L. HELMCAMP, INC.
FNH CONSTRUCTION, LLC
PREPARING ROW
STA 117.000 $4,239.100 $4,500.000 $1,000.000 $2,100.000 $1,000.000 $5,500.000
REMOVING STAB BASE & ASP PAV (18"-24")
SY 15,100.000 $21.000 $17.000 $10.000 $12.000 $38.000 $30.000
EXCAVATION (ROADWAY)
CY 14,865.000 $20.000 $15.000 $5.250 $23.000 $40.000 $20.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 6,452.000 $32.000 $10.000 $10.500 $28.000 $52.000 $50.000
BACKFILL (TY A OR B)
STA 117.000 $456.500 $460.000 $525.000 $255.000 $440.000 $450.000
ROAD GRADER WORK (ORD COMP)
STA 117.000 $379.000 $300.000 $525.000 $246.000 $100.000 $250.000
COMPOST MANUF TOPSOIL (4")
SY 34,570.000 $2.000 $1.050 $1.500 $1.350 $2.600 $8.000
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 34,570.000 $1.000 $0.350 $0.360 $0.280 $0.180 $1.000
DRILL SEED (TEMP)(WARM OR COOL)
SY 34,570.000 $0.300 $0.340 $0.340 $0.220 $0.160 $1.000
VEGETATIVE WATERING
MG 5,292.000 $20.000 $29.000 $2.100 $0.010 $1.000 $30.000
FL BS (CMP IN PLACE) (TY D GR 1-2)(10")
SY 32,400.000 $27.000 $18.000 $35.000 $33.000 $42.000 $28.000
LIME (HYDRATED LIME (SLURRY))
TON 570.000 $320.000 $325.000 $375.000 $370.000 $380.000 $450.000
LIME TRT (EXST MATL) (6")
SY 32,400.000 $4.000 $7.000 $5.250 $9.500 $7.000 $8.000
PRIME COAT (MC-30 OR EC-30)
GAL 6,489.000 $7.000 $5.850 $6.600 $5.000 $8.000 $10.000
PLAN & TEXT ASPH CONC PAV(0" TO 2")
SY 2,318.000 $15.000 $5.000 $7.350 $5.350 $8.000 $20.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 6.000 $2,150.000 $4,000.000 $3,150.000 $4,000.000 $2,100.000 $2,500.000
REMOV STR (BOX CULVERT)
EA 1.000 $8,000.000 $6,000.000 $5,250.000 $6,000.000 $6,500.000 $5,000.000
REMOV STR (HEADWALL)
EA 2.000 $2,500.000 $4,000.000 $4,200.000 $1,800.000 $3,300.000 $5,000.000
MOBILIZATION
LS 1.000 $545,572.000 $550,000.000 $538,000.000 $650,499.000 $400,000.000 $700,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 15.000 $15,000.000 $4,000.000 $26,250.000 $22,000.000 $7,000.000 $8,500.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 440.000 $40.000 $40.000 $53.030 $56.000 $45.000 $30.000
ROCK FILTER DAMS (REMOVE)
LF 440.000 $11.000 $12.000 $23.100 $21.000 $16.000 $15.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 560.000 $32.000 $45.000 $16.000 $46.000 $10.000 $40.000
CONSTRUCTION EXITS (REMOVE)
SY 560.000 $12.000 $12.000 $8.000 $15.000 $5.000 $20.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,634.000 $6.000 $5.000 $3.260 $5.500 $4.500 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,634.000 $2.000 $1.000 $1.050 $1.400 $0.600 $2.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 200.000 $11.000 $8.000 $6.830 $11.000 $6.500 $18.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 200.000 $5.000 $1.250 $1.310 $4.000 $1.000 $9.000
CONSTRUCTING DETOURS
SY 1,563.000 $100.000 $200.000 $157.500 $145.000 $140.000 $75.000
RUMBLE STRIPS (SHOULDER) CONCRETE
LF 386.000 $0.750 $9.000 $10.000 $6.000 $13.000 $10.000
CONC DIRECTIONAL ISLAND
SY 295.000 $450.000 $45.000 $126.000 $160.000 $175.000 $150.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 36.000 $750.000 $671.720 $787.500 $700.000 $700.000 $1,500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 4.000 $895.000 $762.630 $840.000 $800.000 $850.000 $1,500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 1.000 $1,000.000 $959.600 $892.500 $1,000.000 $1,100.000 $1,500.000
IN SM RD SN SUP&AM TY10BWG(1)SB(P)
EA 6.000 $830.800 $722.220 $945.000 $635.000 $700.000 $1,500.000
REMOVE SM RD SN (FOUNDATION ONLY)
EA 32.000 $110.000 $116.160 $262.500 $135.000 $130.000 $200.000
WK ZN PAV MRK REMOV (W)6"(BRK)
LF 4,813.000 $2.000 $0.880 $2.100 $0.900 $0.900 $3.000
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 20,846.000 $1.500 $0.830 $1.840 $0.850 $0.850 $2.000
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 12.000 $10.400 $7.290 $21.000 $7.350 $7.500 $20.000
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 22,119.000 $2.000 $0.830 $1.840 $0.860 $0.850 $2.000
REFL PAV MRK TY I(W)(UTURN ARW)(090MIL)
EA 10.000 $205.500 $260.260 $288.750 $275.000 $270.000 $300.000
REF PAV MRK TY I(W)36"(YLD TRI)(090MIL)
EA 3.000 $70.000 $72.870 $210.000 $75.000 $75.000 $250.000
PAVEMENT SEALER 6"
LF 57,516.000 $0.800 $0.210 $0.320 $0.210 $0.200 $0.500
PAVEMENT SEALER 8"
LF 9,867.000 $0.740 $0.310 $0.530 $0.320 $0.300 $0.650
PAVEMENT SEALER 24"
LF 16,582.000 $2.350 $1.770 $2.890 $1.800 $1.700 $3.000
PAVEMENT SEALER (ARROW)
EA 15.000 $45.000 $33.310 $78.750 $34.000 $32.000 $300.000
PAVEMENT SEALER (WORD)
EA 10.000 $50.000 $40.600 $131.250 $41.000 $39.000 $250.000
PAVEMENT SEALER (UTURN ARROW)
EA 10.000 $35.000 $49.970 $157.500 $51.000 $48.000 $250.000
PAVEMENT SEALER (YLD TRI)
EA 3.000 $20.000 $14.310 $105.000 $15.000 $14.000 $250.000
RE PM TY I(W)6"(BRK)(090MIL)(CALLOUT)
LF 5,538.000 $0.650 $0.770 $0.790 $0.780 $0.800 $1.000
RE PM TY I(W)6"(SLD)(090MIL)(CALLOUT)
LF 24,462.000 $0.650 $0.730 $0.740 $0.740 $0.750 $1.000
RE PM TY I(W)8"(SLD)(090MIL)(CALLOUT)
LF 9,867.000 $0.850 $1.070 $1.260 $1.100 $1.100 $1.500
RE PM TY I(W)24"(SLD)(090MIL)(CALLOUT)
LF 48.000 $7.500 $10.410 $7.880 $10.700 $10.000 $8.000
RE PM TY I(W)(ARROW)(090MIL)(CALLOUT)
EA 15.000 $97.500 $193.630 $157.500 $193.000 $186.000 $250.000
RE PM TY I(W)(WORD)(090MIL)(CALLOUT)
EA 10.000 $125.000 $237.360 $199.500 $240.000 $230.000 $250.000
RE PM TY I(Y)24"(SLD)(090MIL)(CALLOUT)
LF 16,534.000 $6.750 $7.550 $4.520 $7.650 $7.500 $5.000
REF PROF PAV MRK TY I(Y)6"(SLD)(090MIL)
LF 27,516.000 $1.200 $1.410 $1.580 $1.420 $1.400 $2.000
REFL PAV MRKR TY II-A-A
EA 25.000 $7.000 $5.210 $6.300 $5.450 $5.000 $6.000
REFL PAV MRKR TY II-C-R
EA 220.000 $5.250 $5.210 $6.300 $5.450 $5.000 $6.000
ELIM EXT PAV MRK & MRKS (6")
LF 98,317.000 $1.000 $0.830 $0.710 $0.900 $0.800 $1.000
FULL - WIDTH MOWING
CYC 3.000 $6,400.000 $10,000.000 $10,000.000 $2,900.000 $2,800.000 $5,000.000
SP MIXES SP-B PG64-22
TON 6,338.000 $150.000 $145.000 $144.000 $145.000 $172.000 $140.000
SP MIXES SP-C SAC-B PG70-22
TON 3,462.000 $155.000 $150.000 $142.000 $165.000 $186.000 $200.000
TACK COAT
GAL 2,004.000 $5.000 $2.000 $2.350 $4.500 $7.000 $10.000
THERMOPLASTIC PIPE (PP) (24")
LF 608.000 $40.000 $78.730 $63.000 $150.000 $80.000 $250.000
TMA (MOBILE OPERATION)
DAY 15.000 $500.000 $908.590 $1,155.000 $435.000 $200.000 $250.000
Totals: $6,095,724.530 $5,405,602.010 $5,447,991.640 $6,105,756.250 $6,732,618.450 $7,264,209.050