Job Info for 0197-04-086

County: KAUFMAN Highway: US 175 Date: 08/02/2024 (3 months ago) Engineer's Estimate: $6,095,725 Control Number: 0197-04-086
Project: F 2B24(336) District: DALLAS Time: 240 WORKING DAYS Type: INTERSECTION IMPROVEMENT
Bidder's List
Informational:

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $6,095,724.53
GRANITE CONSTRUCTION COMPANY   $5,405,602.01 1
-11.32% | -$690,122.52
ED BELL CONSTRUCTION COMPANY   $5,447,991.64 2
-10.63% | -$647,732.89
0.78% | $42,389.63
TEXAS MATERIALS GROUP, INC.   $6,105,756.25 3
0.16% | $10,031.72
12.95% | $700,154.24
12.07% | $657,764.61
A. L. HELMCAMP, INC.   $6,732,618.45 4
10.45% | $636,893.92
24.55% | $1,327,016.44
10.27% | $626,862.20
FNH CONSTRUCTION, LLC   $7,264,209.05 5
19.17% | $1,168,484.52
34.38% | $1,858,607.04
7.90% | $531,590.60

Bid Items

Items: 66, 0 filtered
KAUFMAN US 175  |  DALLAS  |  0197-04-086  |  08/02/2024  |  $6,095,725  |  F 2B24(336)  |  INTERS IMPRV  |  240 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate GRANITE CONSTRUCTION COMPANY ED BELL CONSTRUCTION COMPANY TEXAS MATERIALS GROUP, INC. A. L. HELMCAMP, INC. FNH CONSTRUCTION, LLC
100 6002 PREPARING ROW STA 117.000 $4,239.100 $4,500.000 $1,000.000 $2,100.000 $1,000.000 $5,500.000
105 6168 REMOVING STAB BASE & ASP PAV (18"-24") SY 15,100.000 $21.000 $17.000 $10.000 $12.000 $38.000 $30.000
110 6001 EXCAVATION (ROADWAY) CY 14,865.000 $20.000 $15.000 $5.250 $23.000 $40.000 $20.000
132 6006 EMBANKMENT (FINAL)(DENS CONT)(TY C) CY 6,452.000 $32.000 $10.000 $10.500 $28.000 $52.000 $50.000
134 6004 BACKFILL (TY A OR B) STA 117.000 $456.500 $460.000 $525.000 $255.000 $440.000 $450.000
152 6001 ROAD GRADER WORK (ORD COMP) STA 117.000 $379.000 $300.000 $525.000 $246.000 $100.000 $250.000
161 6017 COMPOST MANUF TOPSOIL (4") SY 34,570.000 $2.000 $1.050 $1.500 $1.350 $2.600 $8.000
164 6035 DRILL SEEDING (PERM) (RURAL) (CLAY) SY 34,570.000 $1.000 $0.350 $0.360 $0.280 $0.180 $1.000
164 6051 DRILL SEED (TEMP)(WARM OR COOL) SY 34,570.000 $0.300 $0.340 $0.340 $0.220 $0.160 $1.000
168 6001 VEGETATIVE WATERING MG 5,292.000 $20.000 $29.000 $2.100 $0.010 $1.000 $30.000
247 6304 FL BS (CMP IN PLACE) (TY D GR 1-2)(10") SY 32,400.000 $27.000 $18.000 $35.000 $33.000 $42.000 $28.000
260 6002 LIME (HYDRATED LIME (SLURRY)) TON 570.000 $320.000 $325.000 $375.000 $370.000 $380.000 $450.000
260 6006 LIME TRT (EXST MATL) (6") SY 32,400.000 $4.000 $7.000 $5.250 $9.500 $7.000 $8.000
310 6028 PRIME COAT (MC-30 OR EC-30) GAL 6,489.000 $7.000 $5.850 $6.600 $5.000 $8.000 $10.000
354 6002 PLAN & TEXT ASPH CONC PAV(0" TO 2") SY 2,318.000 $15.000 $5.000 $7.350 $5.350 $8.000 $20.000
467 6395 SET (TY II) (24 IN) (RCP) (6: 1) (P) EA 6.000 $2,150.000 $4,000.000 $3,150.000 $4,000.000 $2,100.000 $2,500.000
496 6001 REMOV STR (BOX CULVERT) EA 1.000 $8,000.000 $6,000.000 $5,250.000 $6,000.000 $6,500.000 $5,000.000
496 6006 REMOV STR (HEADWALL) EA 2.000 $2,500.000 $4,000.000 $4,200.000 $1,800.000 $3,300.000 $5,000.000
500 6001 MOBILIZATION LS 1.000 $545,572.000 $550,000.000 $538,000.000 $650,499.000 $400,000.000 $700,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 15.000 $15,000.000 $4,000.000 $26,250.000 $22,000.000 $7,000.000 $8,500.000
506 6002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 440.000 $40.000 $40.000 $53.030 $56.000 $45.000 $30.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 440.000 $11.000 $12.000 $23.100 $21.000 $16.000 $15.000
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 560.000 $32.000 $45.000 $16.000 $46.000 $10.000 $40.000
506 6024 CONSTRUCTION EXITS (REMOVE) SY 560.000 $12.000 $12.000 $8.000 $15.000 $5.000 $20.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 1,634.000 $6.000 $5.000 $3.260 $5.500 $4.500 $4.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 1,634.000 $2.000 $1.000 $1.050 $1.400 $0.600 $2.000
506 6042 BIODEG EROSN CONT LOGS (INSTL) (18") LF 200.000 $11.000 $8.000 $6.830 $11.000 $6.500 $18.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 200.000 $5.000 $1.250 $1.310 $4.000 $1.000 $9.000
508 6001 CONSTRUCTING DETOURS SY 1,563.000 $100.000 $200.000 $157.500 $145.000 $140.000 $75.000
533 6005 RUMBLE STRIPS (SHOULDER) CONCRETE LF 386.000 $0.750 $9.000 $10.000 $6.000 $13.000 $10.000
536 6004 CONC DIRECTIONAL ISLAND SY 295.000 $450.000 $45.000 $126.000 $160.000 $175.000 $150.000
644 6001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 36.000 $750.000 $671.720 $787.500 $700.000 $700.000 $1,500.000
644 6004 IN SM RD SN SUP&AM TY10BWG(1)SA(T) EA 4.000 $895.000 $762.630 $840.000 $800.000 $850.000 $1,500.000
644 6007 IN SM RD SN SUP&AM TY10BWG(1)SA(U) EA 1.000 $1,000.000 $959.600 $892.500 $1,000.000 $1,100.000 $1,500.000
644 6009 IN SM RD SN SUP&AM TY10BWG(1)SB(P) EA 6.000 $830.800 $722.220 $945.000 $635.000 $700.000 $1,500.000
644 6113 REMOVE SM RD SN (FOUNDATION ONLY) EA 32.000 $110.000 $116.160 $262.500 $135.000 $130.000 $200.000
662 6064 WK ZN PAV MRK REMOV (W)6"(BRK) LF 4,813.000 $2.000 $0.880 $2.100 $0.900 $0.900 $3.000
662 6067 WK ZN PAV MRK REMOV (W)6"(SLD) LF 20,846.000 $1.500 $0.830 $1.840 $0.850 $0.850 $2.000
662 6075 WK ZN PAV MRK REMOV (W)24"(SLD) LF 12.000 $10.400 $7.290 $21.000 $7.350 $7.500 $20.000
662 6098 WK ZN PAV MRK REMOV (Y)6"(SLD) LF 22,119.000 $2.000 $0.830 $1.840 $0.860 $0.850 $2.000
666 6062 REFL PAV MRK TY I(W)(UTURN ARW)(090MIL) EA 10.000 $205.500 $260.260 $288.750 $275.000 $270.000 $300.000
666 6101 REF PAV MRK TY I(W)36"(YLD TRI)(090MIL) EA 3.000 $70.000 $72.870 $210.000 $75.000 $75.000 $250.000
666 6225 PAVEMENT SEALER 6" LF 57,516.000 $0.800 $0.210 $0.320 $0.210 $0.200 $0.500
666 6226 PAVEMENT SEALER 8" LF 9,867.000 $0.740 $0.310 $0.530 $0.320 $0.300 $0.650
666 6230 PAVEMENT SEALER 24" LF 16,582.000 $2.350 $1.770 $2.890 $1.800 $1.700 $3.000
666 6231 PAVEMENT SEALER (ARROW) EA 15.000 $45.000 $33.310 $78.750 $34.000 $32.000 $300.000
666 6232 PAVEMENT SEALER (WORD) EA 10.000 $50.000 $40.600 $131.250 $41.000 $39.000 $250.000
666 6236 PAVEMENT SEALER (UTURN ARROW) EA 10.000 $35.000 $49.970 $157.500 $51.000 $48.000 $250.000
666 6243 PAVEMENT SEALER (YLD TRI) EA 3.000 $20.000 $14.310 $105.000 $15.000 $14.000 $250.000
666 6257 RE PM TY I(W)6"(BRK)(090MIL)(CALLOUT) LF 5,538.000 $0.650 $0.770 $0.790 $0.780 $0.800 $1.000
666 6258 RE PM TY I(W)6"(SLD)(090MIL)(CALLOUT) LF 24,462.000 $0.650 $0.730 $0.740 $0.740 $0.750 $1.000
666 6259 RE PM TY I(W)8"(SLD)(090MIL)(CALLOUT) LF 9,867.000 $0.850 $1.070 $1.260 $1.100 $1.100 $1.500
666 6265 RE PM TY I(W)24"(SLD)(090MIL)(CALLOUT) LF 48.000 $7.500 $10.410 $7.880 $10.700 $10.000 $8.000
666 6267 RE PM TY I(W)(ARROW)(090MIL)(CALLOUT) EA 15.000 $97.500 $193.630 $157.500 $193.000 $186.000 $250.000
666 6273 RE PM TY I(W)(WORD)(090MIL)(CALLOUT) EA 10.000 $125.000 $237.360 $199.500 $240.000 $230.000 $250.000
666 6279 RE PM TY I(Y)24"(SLD)(090MIL)(CALLOUT) LF 16,534.000 $6.750 $7.550 $4.520 $7.650 $7.500 $5.000
666 6289 REF PROF PAV MRK TY I(Y)6"(SLD)(090MIL) LF 27,516.000 $1.200 $1.410 $1.580 $1.420 $1.400 $2.000
672 6009 REFL PAV MRKR TY II-A-A EA 25.000 $7.000 $5.210 $6.300 $5.450 $5.000 $6.000
672 6010 REFL PAV MRKR TY II-C-R EA 220.000 $5.250 $5.210 $6.300 $5.450 $5.000 $6.000
677 6002 ELIM EXT PAV MRK & MRKS (6") LF 98,317.000 $1.000 $0.830 $0.710 $0.900 $0.800 $1.000
730 6107 FULL - WIDTH MOWING CYC 3.000 $6,400.000 $10,000.000 $10,000.000 $2,900.000 $2,800.000 $5,000.000
3077 6001 SP MIXES SP-B PG64-22 TON 6,338.000 $150.000 $145.000 $144.000 $145.000 $172.000 $140.000
3077 6023 SP MIXES SP-C SAC-B PG70-22 TON 3,462.000 $155.000 $150.000 $142.000 $165.000 $186.000 $200.000
3077 6075 TACK COAT GAL 2,004.000 $5.000 $2.000 $2.350 $4.500 $7.000 $10.000
4216 6002 THERMOPLASTIC PIPE (PP) (24") LF 608.000 $40.000 $78.730 $63.000 $150.000 $80.000 $250.000
6185 6005 TMA (MOBILE OPERATION) DAY 15.000 $500.000 $908.590 $1,155.000 $435.000 $200.000 $250.000
Totals: $6,095,724.53 $5,405,602.01 $5,447,991.64 $6,105,756.25 $6,732,618.45 $7,264,209.05