REMOVING CONCRETE(MOW STRIP)
|
LF
|
5,385.000
|
$3.000
|
$7.000
|
|
|
BACKFILL (TY A OR B)
|
STA
|
719.210
|
$150.000
|
$331.000
|
|
|
BLADING
|
STA
|
719.210
|
$50.000
|
$76.000
|
|
|
COMPOST MANUF TOPSOIL (4")
|
SY
|
47,947.000
|
$0.850
|
$0.900
|
|
|
DRILL SEEDING (PERM) (RURAL) (CLAY)
|
SY
|
47,947.000
|
$0.120
|
$0.130
|
|
|
VEGETATIVE WATERING
|
MG
|
4,160.000
|
$12.000
|
$0.010
|
|
|
FL BS (CMP IN PLC)(TY D GR1-2)(12")
|
SY
|
1,412.000
|
$20.000
|
$45.000
|
|
|
SUPERPAVE MIXTURES SP-B PG64-22
|
TON
|
800.000
|
$73.000
|
$115.000
|
|
|
STONE-MTRX-ASPH SMA-C SAC-A PG76-22
|
TON
|
27,212.030
|
$95.000
|
$130.000
|
|
|
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
|
TON
|
41,264.720
|
$95.000
|
$130.000
|
|
|
FLEX PAVEMENT STRUCTURE REPAIR (8"-12")
|
SY
|
2,200.000
|
$75.000
|
$110.000
|
|
|
PLAN & TEXT ASPH CONC PAV(10" TO 12")
|
SY
|
7,649.000
|
$2.000
|
$5.100
|
|
|
PLAN & TEXT ASPH CONC PAV(0" TO 6")
|
SY
|
92,038.000
|
$1.800
|
$2.650
|
|
|
PLAN & TEXT CONC PAV(0" TO 2")
|
SY
|
27,809.000
|
$5.200
|
$1.600
|
|
|
FULL - DEPTH REPAIR CPCD (12")
|
SY
|
800.000
|
$155.000
|
$320.000
|
|
|
FULL - DEPTH REPAIR CPCD (13")
|
SY
|
2,800.000
|
$170.000
|
$330.000
|
|
|
REINF CONC SLAB (HPC)
|
SF
|
33,191.000
|
$19.500
|
$29.000
|
|
|
APPROACH SLAB (HPC)
|
CY
|
427.000
|
$550.000
|
$525.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
1,193.000
|
$460.000
|
$500.000
|
|
|
RAIL (TY SSTR)(HPC)
|
LF
|
1,126.700
|
$70.000
|
$150.000
|
|
|
RETROFIT RAIL (TY SSTR)(HPC)
|
LF
|
144.000
|
$250.000
|
$200.000
|
|
|
RETROFIT RAIL (TY 501)
|
LF
|
13.000
|
$250.000
|
$200.000
|
|
|
SEALED EXPANSION JOINT (4 IN) (SEJ - A)
|
LF
|
262.000
|
$100.000
|
$165.000
|
|
|
REMOV STR (BRIDGE SLAB)
|
EA
|
2.000
|
$150,000.000
|
$164,000.000
|
|
|
REMOV STR (APPROACH SLAB)
|
EA
|
12.000
|
$15,000.000
|
$2,000.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$1,550,000.000
|
$2,199,645.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
12.000
|
$23,000.000
|
$39,900.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
468.000
|
$20.000
|
$25.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
468.000
|
$7.000
|
$8.250
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
5,364.000
|
$2.500
|
$2.650
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
5,364.000
|
$0.500
|
$0.550
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
2,750.000
|
$4.000
|
$5.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
2,750.000
|
$1.000
|
$1.050
|
|
|
CONSTRUCTING DETOURS
|
SY
|
233.000
|
$80.000
|
$150.000
|
|
|
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
|
LF
|
1,260.000
|
$30.000
|
$55.000
|
|
|
PORT CTB (MOVE)(F-SHAPE)(TY 1)
|
LF
|
1,620.000
|
$5.000
|
$11.000
|
|
|
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
|
LF
|
1,260.000
|
$8.000
|
$15.550
|
|
|
RUMBLE STRIPS (SHOULDER) ASPHALT
|
LF
|
47,265.000
|
$0.120
|
$0.160
|
|
|
RUMBLE STRIPS (SHOULDER) CONCRETE
|
LF
|
400.000
|
$1.500
|
$24.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
4,470.000
|
$18.000
|
$20.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
20.000
|
$1,725.000
|
$1,500.000
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
8.000
|
$1,450.000
|
$1,100.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
3,975.000
|
$2.750
|
$3.050
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
6.000
|
$260.000
|
$115.000
|
|
|
CABLE BARRIER SYSTEM (TL-4)
|
LF
|
21,480.000
|
$11.000
|
$12.350
|
|
|
CABLE BARRIER TERMINAL SECTION (TL-4)
|
EA
|
10.000
|
$2,350.000
|
$3,000.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
26.000
|
$2,500.000
|
$2,800.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
27.000
|
$240.000
|
$275.000
|
|
|
CRASH CUSH ATTEN (INSTL)
|
EA
|
2.000
|
$12,000.000
|
$8,500.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
3.000
|
$12,000.000
|
$1,650.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
2.000
|
$800.000
|
$1,650.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
7.000
|
$600.000
|
$685.000
|
|
|
IN BRIDGE MNT CLEARANCE SGN ASSM(TY N)
|
EA
|
4.000
|
$2,250.000
|
$2,100.000
|
|
|
IN BRIDGE MNT CLEARANCE SGN ASSM(TY S)
|
EA
|
2.000
|
$2,000.000
|
$2,150.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
7.000
|
$80.000
|
$80.000
|
|
|
REMOVE BRDG MNT CLEARANCE SIGN ASSM
|
EA
|
6.000
|
$500.000
|
$550.000
|
|
|
RELOCATE LRSS (SIGN ONLY)
|
EA
|
2.000
|
$900.000
|
$1,600.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(FLX)GND
|
EA
|
197.000
|
$70.000
|
$54.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
|
EA
|
43.000
|
$25.000
|
$30.000
|
|
|
INSTL DEL ASSM (D-SY)SZ 1(FLX)GND
|
EA
|
31.000
|
$70.000
|
$54.000
|
|
|
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
|
EA
|
43.000
|
$19.000
|
$30.000
|
|
|
INSTL DEL ASSM (D-DW)SZ 1(FLX)GND
|
EA
|
104.000
|
$70.000
|
$54.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
|
EA
|
59.000
|
$27.000
|
$36.000
|
|
|
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
|
EA
|
48.000
|
$23.000
|
$36.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
|
LF
|
78,957.000
|
$0.290
|
$0.420
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
|
LF
|
78,925.000
|
$0.310
|
$0.420
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
4,016.000
|
$0.900
|
$1.050
|
|
|
WK ZN PAV MRK REMOV (W)8"(SLD)
|
LF
|
285.000
|
$1.800
|
$4.200
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
4,045.000
|
$0.900
|
$1.050
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
2,220.000
|
$0.730
|
$1.040
|
|
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
|
LF
|
240.000
|
$1.500
|
$1.550
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
25,526.000
|
$1.100
|
$0.780
|
|
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
|
LF
|
1,775.000
|
$4.200
|
$3.300
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
78.000
|
$6.000
|
$6.450
|
|
|
PAVEMENT SEALER 4"
|
LF
|
5,480.000
|
$0.150
|
$0.260
|
|
|
PAVEMENT SEALER 6"
|
LF
|
2,760.000
|
$0.200
|
$0.380
|
|
|
PAVEMENT SEALER 8"
|
LF
|
835.000
|
$0.600
|
$0.520
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
86,984.000
|
$0.320
|
$0.480
|
|
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
|
LF
|
22,200.000
|
$0.480
|
$0.680
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
86,475.000
|
$0.320
|
$0.490
|
|
REFL PAV MRK TY I (W)12"(DOT)(100MIL)
|
LF
|
60.000
|
$2.000
|
$5.450
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
22.000
|
$4.500
|
$6.450
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
895.000
|
$3.000
|
$4.300
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
44,219.000
|
$0.400
|
$0.540
|
|
|
ELIM EXT PAV MRK & MRKS (8")
|
LF
|
835.000
|
$0.750
|
$1.050
|
|
|
PAV SURF PREP FOR MRK (4")
|
LF
|
5,480.000
|
$0.100
|
$0.260
|
|
|
PAV SURF PREP FOR MRK (6")
|
LF
|
2,760.000
|
$0.100
|
$0.260
|
|
|
PAV SURF PREP FOR MRK (8")
|
LF
|
835.000
|
$0.200
|
$0.260
|
|
|
LITTER REMOVAL
|
CYC
|
4.000
|
$2,500.000
|
$1,200.000
|
|
|
DEBRIS REMOVAL (CNTR MEDIANS/MAINLANES)
|
CYC
|
36.000
|
$2,300.000
|
$1,200.000
|
|
|
CLEANING / SWEEPING (CENTER MEDIAN)
|
CYC
|
6.000
|
$2,000.000
|
$1,700.000
|
|
|
POST AND CABLE FENCE (REMOVAL)
|
LF
|
21,480.000
|
$4.000
|
$3.100
|
|
|
POST AND CABLE FENCE (REMV CONC ANCHOR)
|
EA
|
10.000
|
$1,300.000
|
$545.000
|
|
|
BRIDGE JOINT REPAIR (ARMOR)
|
LF
|
324.000
|
$350.000
|
$160.000
|
|
|
NO. OF DAYS MILESTONE 1
|
$/D
|
8,000.000
|
$56.000
|
$56.000
|
|
|
NO. OF DAYS MILESTONE 2
|
$/D
|
8,000.000
|
$56.000
|
$56.000
|
|
|
CAM (ASPHALT) PG(76-22)
|
TON
|
1,375.480
|
$98.000
|
$165.000
|
|
|
CAM (AGGREGATE)
|
TON
|
17,194.330
|
$98.000
|
$165.000
|
|
|
MEMBRANE UNDERSEAL
|
GAL
|
33,450.000
|
$2.500
|
$2.000
|
|
|
RUBBILIZING EXISTING CONCRETE PAVEMENT
|
SY
|
132,991.110
|
$2.500
|
$2.890
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
6.000
|
$13,000.000
|
$12,000.000
|
|
|
TMA (STATIONARY)
|
EA
|
6.000
|
$14,000.000
|
$0.100
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
96.000
|
$65.000
|
$55.000
|
|
|
TEMP Q-DETECT SYS
|
EA
|
1.000
|
$100,000.000
|
$75,000.000
|
|
|
TEMP Q-DETECT SYS (RELOCATE)
|
EA
|
2.000
|
$15,000.000
|
$1,500.000
|
|
Totals: |
$16,456,438.855
|
$22,030,032.938
|