Bid Cobra

KARNES BS 72-B (0270-04-006)

Items: 95

County: KARNES
Length: N/A
Highway: BS 72-B
District: CORPUS CHRISTI
Control Number: 0270-04-006
DBE Goal: N/A
Project: STP 2018(977)
Guaranty: N/A
Time: 88 WORKING DAYS
Engineer's Estimate: $1,856,605.90
Date: 06/05/2018 (8 years ago)
Contract Number: N/A
Type: REHAB ROADWAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$1,856,605.90
$1,573,309.64
Over/Under Est: -15.26% -$283,296.26
Over/Under Est: -9.77% -$181,453.41
Amt Left: 6.47% $101,842.85
Over/Under Est: -3.06% -$56,839.45
Amt Left: 14.39% $226,456.81
Delta: -7.44% -$124,613.96
Over/Under Est: 2.51% $46,673.72
Amt Left: 20.97% $329,969.98
Delta: -5.75% -$103,513.17
Over/Under Est: 5.39% $100,094.91
Amt Left: 24.37% $383,391.17
Delta: -2.81% -$53,421.19
Over/Under Est: 21.35% $396,389.74
Amt Left: 43.2% $679,686.00
Delta: -15.14% -$296,294.83

Bid Items & Bid Tabulations

95 Total 0 of 95
KARNES  |  BS 72-B  |  CORPUS CHRISTI  |  0270-04-006  |  06/05/2018  |  $1,856,605.90  |  STP 2018(977)  |  REHAB ROADWAY  |  88 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HUNTER INDUSTRIES, LTD.
CURRAN CONTRACTING COMPANY
ANGEL BROTHERS HOLDINGS CORP.
CAPITAL EXCAVATION COMPANY
J. CARROLL WEAVER, INC.
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
REMOVING CONC (MEDIANS)
SY 94.000 $10.000 $12.270 $12.200 $22.000 $52.130 $55.500 $24.270
REMOVING CONC (DRIVEWAYS)
SY 60.000 $15.000 $12.270 $19.150 $29.500 $37.670 $26.640 $38.020
REMOVING STAB BASE AND ASPH PAV (2")
SY 512.000 $2.000 $2.560 $6.450 $3.300 $5.000 $7.770 $11.360
REMOVING STAB BASE AND ASPH PAV (3")
SY 1,472.000 $5.000 $2.560 $4.000 $3.300 $5.000 $9.990 $7.440
EXCAVATION (ROADWAY)
CY 1,259.000 $10.000 $29.970 $15.600 $29.900 $18.000 $11.230 $18.930
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 397.000 $15.000 $23.310 $3.250 $15.000 $8.000 $15.540 $16.260
BACKFILL (TY A OR B)
STA 77.000 $85.000 $111.750 $144.350 $270.000 $300.000 $435.810 $145.060
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 28,330.000 $0.300 $0.250 $0.300 $0.300 $0.250 $0.280 $0.380
FERTILIZER
TON 1.100 $1,000.000 $1,200.000 $398.150 $1,350.000 $1,200.000 $1,332.000 $1,848.860
VEGETATIVE WATERING
MG 457.000 $38.000 $23.310 $29.950 $40.000 $15.000 $25.530 $61.540
PROOF ROLLING
HR 32.000 $86.000 $68.400 $102.450 $64.000 $100.000 $68.820 $67.360
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 820.000 $60.000 $61.050 $70.300 $72.600 $60.000 $90.130 $95.450
LIME (HYD, COM, OR QK(SLURRY))
TON 42.000 $160.000 $210.000 $172.300 $145.000 $150.000 $183.150 $177.290
LIME TRT (SUBGRADE)(8")
SY 3,123.000 $3.000 $2.850 $2.250 $6.000 $7.000 $8.290 $5.870
PRIME COAT (MC-30)
GAL 541.000 $5.500 $4.380 $7.150 $5.000 $4.500 $5.630 $6.970
ASPH (MULTI OPTION)
GAL 7,448.000 $2.350 $3.120 $3.950 $3.000 $3.600 $2.940 $3.850
AGGR(TY-PB GR-4S OR TY-PB GR-4)(SAC-B)
CY 174.000 $73.000 $111.210 $147.000 $130.000 $140.000 $145.430 $166.820
D-GR HMA TY B SAC-B PG (64-22)
TON 4,191.000 $65.000 $63.210 $64.550 $75.000 $82.000 $88.070 $84.990
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
TON 3,492.000 $95.000 $101.100 $101.500 $109.000 $133.000 $137.630 $128.370
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 2,271.000 $50.000 $30.260 $37.800 $53.000 $47.000 $42.180 $62.920
FLEXIBLE PAV STRUCTURE REPAIR (1.5")
SY 1,813.000 $25.000 $9.330 $13.200 $12.000 $10.000 $19.980 $20.480
PLANE ASPH CONC PAV (3")
SY 17,554.000 $2.000 $1.590 $1.800 $2.000 $2.000 $2.590 $3.820
RC PIPE (CL III)(18 IN)
LF 152.000 $50.000 $67.840 $116.800 $86.500 $95.000 $86.580 $76.390
RC PIPE (CL III)(24 IN)
LF 104.000 $75.000 $79.310 $147.250 $105.000 $110.000 $108.780 $109.050
RC PIPE (CL III)(36 IN)
LF 4.000 $110.000 $86.000 $765.400 $470.000 $286.210 $355.200 $486.280
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 8.000 $700.000 $1,399.140 $1,236.350 $1,170.000 $1,586.840 $999.000 $880.150
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 4.000 $1,000.000 $1,399.140 $1,624.750 $1,500.000 $2,170.820 $1,665.000 $1,752.600
SET (TY II) (36 IN) (RCP) (6: 1) (P)
EA 1.000 $2,700.000 $2,934.780 $3,128.950 $4,300.000 $4,067.390 $3,552.000 $6,002.250
RING & COVER
EA 1.000 $1,500.000 $1,260.010 $925.350 $1,140.000 $1,345.290 $2,775.000 $2,043.120
CLEAN EXIST CULVERTS
EA 17.000 $2,500.000 $2,520.030 $1,274.000 $1,060.000 $1,500.000 $222.000 $3,244.720
REMOV STR (SET)
EA 8.000 $495.000 $945.010 $270.350 $295.000 $380.420 $166.500 $464.220
REMOV STR (HEADWALL)
EA 1.000 $700.000 $1,260.010 $1,122.100 $845.000 $1,717.480 $888.000 $1,525.930
REMOV STR (PIPE)
LF 255.000 $20.000 $12.600 $30.450 $21.000 $12.060 $8.880 $14.560
MOBILIZATION
LS 1.000 $180,000.000 $156,874.090 $160,000.000 $95,000.000 $160,000.000 $190,501.720 $254,654.340
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $4,500.000 $2,049.030 $3,995.450 $9,000.000 $1,000.000 $999.000 $4,790.690
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 111.000 $30.500 $27.700 $44.450 $31.000 $27.500 $30.750 $13.360
CONSTRUCTION EXITS (REMOVE)
SY 111.000 $10.000 $8.500 $11.850 $9.500 $8.500 $9.440 $5.520
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 415.000 $5.000 $4.500 $5.200 $5.000 $4.500 $5.000 $11.210
BIODEG EROSN CONT LOGS (REMOVE)
LF 415.000 $1.000 $1.500 $1.150 $1.700 $1.500 $1.110 $1.340
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 580.000 $35.000 $16.800 $29.350 $29.300 $14.000 $25.890 $92.100
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 200.000 $60.000 $16.800 $31.450 $30.600 $14.000 $25.900 $93.510
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 580.000 $10.000 $16.800 $20.100 $17.400 $14.000 $25.890 $14.390
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 200.000 $15.000 $16.800 $22.950 $18.750 $14.000 $25.900 $17.880
DRIVEWAYS (CONC)
SY 67.000 $85.000 $68.250 $98.500 $86.350 $142.990 $55.500 $146.310
TURNOUTS (ACP)
SY 175.000 $30.000 $31.710 $76.850 $70.600 $27.900 $38.850 $65.370
DRIVEWAYS (ACP)(TYPE 1)
SY 1,337.000 $30.000 $26.280 $24.950 $34.000 $20.410 $27.750 $43.080
DRIVEWAYS (ACP) (TYPE 2)
SY 127.000 $40.000 $40.560 $44.800 $32.000 $39.660 $31.080 $83.250
INTERSECTIONS (ACP) (TYPE 1)
SY 815.000 $15.000 $26.280 $26.550 $27.500 $26.740 $31.080 $39.900
INTERSECTIONS (ACP) (TYPE 2)
SY 1,161.000 $30.000 $38.190 $39.600 $50.000 $37.440 $46.620 $34.120
DRIVEWAYS (ACP)(TYPE 3)
SY 1,109.000 $65.000 $31.710 $62.150 $41.000 $61.360 $49.950 $34.780
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 4.000 $225.000 $182.570 $180.500 $190.000 $170.000 $249.750 $257.560
MAILBOX INSTALL-D (TWG-POST) TY 2
EA 1.000 $260.000 $198.680 $196.400 $210.000 $185.000 $283.050 $290.560
MAILBOX INSTALL-M (TWG-POST) TY 4
EA 3.000 $400.000 $300.700 $297.250 $315.000 $280.000 $496.170 $501.760
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 47.000 $450.000 $381.250 $467.150 $400.000 $440.000 $493.950 $499.560
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 2.000 $530.000 $563.820 $557.400 $590.000 $525.000 $692.640 $696.460
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 3.000 $580.000 $671.210 $663.550 $700.000 $625.000 $852.480 $854.860
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
EA 1.000 $800.000 $687.320 $679.500 $715.000 $640.000 $849.150 $850.860
REMOVE SM RD SN SUP&AM
EA 53.000 $50.000 $42.960 $42.450 $45.000 $40.000 $79.920 $90.590
ISRSA TYS80(1)SA(P) (EXCLUDING SIGN)
EA 7.000 $310.000 $424.210 $419.350 $440.000 $395.000 $419.580 $425.860
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 4.000 $60.000 $55.850 $55.200 $58.000 $52.000 $79.920 $89.260
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 6,700.000 $0.150 $0.160 $0.150 $0.200 $0.160 $0.180 $0.190
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 210.000 $0.300 $0.500 $0.550 $0.550 $0.500 $0.560 $1.030
WK ZN PAV MRK NON-REMOV (W)(ARROW)
EA 4.000 $60.000 $63.000 $66.900 $70.400 $63.000 $69.930 $79.360
WK ZN PAV MRK NON-REMOV(W)(WORD)
EA 4.000 $85.000 $63.000 $66.900 $70.400 $63.000 $69.930 $79.360
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 22,879.000 $0.150 $0.160 $0.150 $0.200 $0.160 $0.180 $0.190
WK ZN PAV MRK REMOV (TRAF BTN) TY W
LF 6,910.000 $1.500 $0.430 $0.450 $0.500 $0.430 $0.480 $0.500
WK ZN PAV MRK REMOV (TRAF BTN) TY Y
LF 10,550.000 $1.500 $0.430 $0.450 $0.500 $0.430 $0.480 $0.490
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 188.000 $1.500 $1.760 $2.200 $0.600 $1.000 $0.370 $2.200
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 1,276.000 $1.500 $1.760 $1.750 $0.600 $1.000 $0.370 $1.200
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 770.000 $0.600 $0.700 $0.750 $0.800 $0.700 $0.780 $1.030
REFL PAV MRK TY I (W)24"(SLD)(090MIL)
LF 300.000 $5.000 $5.000 $5.300 $5.600 $5.000 $5.550 $5.840
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 5,209.000 $0.250 $0.340 $0.350 $0.400 $0.340 $0.380 $0.390
RE PM W/RET REQ TY I (W)6"(SLD)(090MIL)
LF 11,186.000 $0.500 $0.480 $0.500 $0.550 $0.480 $0.530 $0.550
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 7,844.000 $0.250 $0.340 $0.350 $0.400 $0.340 $0.380 $0.390
RE PM W/RET REQ TY I (Y)6"(SLD)(090MIL)
LF 10,442.000 $0.500 $0.480 $0.500 $0.550 $0.480 $0.530 $0.550
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 192.000 $12.000 $10.430 $11.050 $11.650 $10.430 $11.580 $12.520
PREFAB PAV MRK TY C (W) (ARROW)
EA 2.000 $200.000 $188.000 $199.600 $210.000 $188.000 $208.680 $231.950
PREFAB PAV MRK TY C (W) (LNDP ARROW)
EA 2.000 $500.000 $533.000 $565.900 $600.000 $533.000 $591.630 $611.450
PREFAB PAV MRK TY C (W) (WORD)
EA 2.000 $300.000 $203.000 $215.500 $230.000 $203.000 $225.330 $248.450
PREFAB PAV MRK TY C (W) (18")(YLD TRI)
EA 21.000 $25.000 $33.000 $35.050 $37.000 $33.000 $36.630 $45.880
REFL PAV MRKR TY I-C
EA 54.000 $2.600 $8.000 $8.500 $9.000 $8.000 $8.880 $10.660
REFL PAV MRKR TY II-A-A
EA 596.000 $2.600 $2.800 $2.950 $3.000 $2.800 $3.110 $3.420
ELIM EXT PAV MRK & MRKS (4")
LF 10,550.000 $1.200 $0.500 $0.450 $0.700 $2.000 $0.110 $1.390
ELIM EXT PAV MRK & MRKS (8")
LF 210.000 $0.800 $0.500 $6.450 $3.000 $43.000 $0.110 $2.130
ELIM EXT PAV MRK & MRKS (ARROW)
EA 4.000 $40.000 $43.000 $45.650 $48.000 $43.000 $47.730 $72.450
ELIM EXT PAV MRK & MRKS (WORD)
EA 4.000 $40.000 $43.000 $45.650 $48.000 $39.000 $47.730 $72.450
REMOV RDSD FLSH BCN AM (SOLAR PWRD)
EA 4.000 $250.000 $475.000 $286.650 $300.000 $270.000 $299.700 $322.150
TREE TRIMMING / BRUSH REMOVAL
MI 1.100 $20,000.000 $17,850.000 $21,950.300 $17,600.000 $44,005.140 $22,949.250 $8,256.360
TREE REMOVAL (12" - 18" DIA)
EA 1.000 $800.000 $1,050.000 $1,210.300 $1,120.000 $1,000.000 $1,265.400 $1,846.970
TREE REMOVAL (18" - 24" DIA)
EA 1.000 $400.000 $1,575.000 $1,210.300 $1,120.000 $2,000.000 $1,265.400 $2,119.430
DITCH CLEANING AND RESHAPING (FOOT)
LF 10,687.000 $15.000 $2.280 $1.300 $1.700 $4.130 $1.980 $3.890
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 312.000 $65.000 $55.660 $35.850 $50.000 $50.300 $46.620 $91.180
TMA (STATIONARY)
DAY 176.000 $230.000 $135.310 $160.850 $335.000 $99.560 $35.520 $109.510
TMA (MOBILE OPERATION)
HR 128.000 $25.000 $54.130 $41.400 $50.000 $40.870 $43.290 $108.640
SOLAR POWERED LED ROADSIDE SIGN
EA 7.000 $4,700.000 $3,850.000 $3,609.700 $3,800.000 $3,400.000 $3,774.000 $3,840.590
Totals: $1,856,605.900 $1,573,309.640 $1,675,152.495 $1,799,766.450 $1,903,279.624 $1,956,700.815 $2,252,995.652