Job Info for 1360-01-031

County: JONES Highway: FM 1226 Date: 05/03/2024 (6 months ago) Engineer's Estimate: $7,466,433 Control Number: 1360-01-031
Project: C 1360-1-31 District: ABILENE Time: 289 WORKING DAYS Type: WIDEN ROAD - ADD SHOULDERS
Bidder's List
Informational:
Email All | Notice | Questions
HCS
Pay Estimates: 1 | 2 | 3
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $7,466,432.95
J. H. STRAIN & SONS, INC.   $9,538,047.57 1
27.75% | $2,071,614.62
BONTKE BROTHERS CONSTRUCTION COMPANY   $10,501,878.90 2
40.65% | $3,035,445.95
10.11% | $963,831.33
GILVIN-TERRILL, LTD.   $11,316,281.69 3
51.56% | $3,849,848.74
18.64% | $1,778,234.12
7.75% | $814,402.79
CK NEWBERRY, LLC   $12,258,164.25 4
64.18% | $4,791,731.30
28.52% | $2,720,116.68
8.32% | $941,882.56
Subcontractor Percentage Amount
HJC FARMS, INC. 2.88% $274,695.77
FLAT LINE, INC. 2.32% $221,282.70
DK CONTRACTING, LLC 0.80% $76,304.38
CONTRACTORS SERVICE, LTD. 0.66% $62,951.11
Total: 6.66% $635,233.96

Bid Items

Items: 72, 0 filtered
JONES FM 1226  |  ABILENE  |  1360-01-031  |  05/03/2024  |  $7,466,433  |  C 1360-1-31  |  WIDEN ROAD - ADD SHOULDERS  |  289 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate J. H. STRAIN & SONS, INC. BONTKE BROTHERS CONSTRUCTION COMPANY GILVIN-TERRILL, LTD. CK NEWBERRY, LLC
110 6004 EXCAVATION (ROADWAY AND CHANNEL) CY 512.000 $20.000 $45.000 $30.000 $100.000 $125.000
112 6002 SUBGRADE WIDENING (DENS CONT) STA 626.000 $500.000 $1,800.000 $1,700.000 $1,200.000 $700.000
132 6001 EMBANKMENT (FINAL)(ORD COMP)(TY A) CY 400.000 $40.000 $45.000 $40.000 $100.000 $70.000
134 6002 BACKFILL (TY B) STA 626.000 $120.000 $375.000 $400.000 $700.000 $400.000
164 6036 DRILL SEEDING (PERM) (RURAL) (CLAY) AC 46.000 $750.000 $750.000 $1,200.000 $700.000 $1,000.000
164 6053 DRILL SEEDING (TEMP)(WARM OR COOL) AC 46.000 $415.000 $550.000 $1,200.000 $500.000 $550.000
168 6001 VEGETATIVE WATERING MG 313.000 $55.000 $100.000 $500.000 $60.000 $65.000
247 6041 FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS) CY 21,658.000 $70.000 $71.000 $60.000 $70.000 $125.000
310 6009 PRIME COAT (MC-30) GAL 14,195.000 $6.000 $7.000 $10.000 $7.500 $7.000
316 6001 ASPH (MULTI OPTION) GAL 32,732.000 $5.000 $6.000 $10.000 $7.000 $6.000
316 6017 ASPH (AC-20-5TR) GAL 90,644.000 $4.000 $6.000 $11.000 $7.000 $5.000
316 6222 AGGR(TY-PB GR-3 SAC-B) CY 678.000 $250.000 $175.000 $300.000 $250.000 $200.000
316 6224 AGGR(TY-PB GR-4 SAC-B) CY 1,813.000 $150.000 $175.000 $300.000 $250.000 $175.000
351 6013 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") SY 5,448.000 $50.000 $65.000 $45.000 $100.000 $60.000
402 6001 TRENCH EXCAVATION PROTECTION LF 512.000 $15.000 $25.000 $25.000 $25.000 $20.000
403 6001 TEMPORARY SPL SHORING SF 3,832.000 $50.000 $40.000 $33.000 $40.000 $80.000
432 6006 RIPRAP (CONC)(CL B) CY 846.000 $400.000 $815.000 $900.000 $635.000 $1,200.000
450 6018 RAIL (TY T631) LF 389.000 $115.000 $120.000 $110.000 $100.000 $125.000
462 6067 CONC BOX CULV (8 FT X 8 FT)(EXTEND) LF 20.000 $1,500.000 $1,440.000 $3,500.000 $1,600.000 $2,200.000
462 6078 CONC BOX CULV (10 FT X 10 FT)(EXTEND) LF 20.000 $2,000.000 $1,560.000 $3,500.000 $2,150.000 $3,200.000
464 6019 RC PIPE (CL IV)(30 IN) LF 166.000 $325.000 $300.000 $330.000 $250.000 $375.000
464 6020 RC PIPE (CL IV)(36 IN) LF 44.000 $350.000 $415.000 $400.000 $340.000 $425.000
464 6046 RC PIPE (ARCH)(CL IV)(DES 3) LF 1,262.000 $300.000 $415.000 $500.000 $380.000 $425.000
464 6047 RC PIPE (ARCH)(CL IV)(DES 5) LF 238.000 $500.000 $725.000 $410.000 $570.000 $725.000
466 6171 WINGWALL (PW - 1) (HW=10 FT) EA 2.000 $45,000.000 $40,000.000 $60,000.000 $75,000.000 $85,000.000
466 6173 WINGWALL (PW - 1) (HW=12 FT) EA 2.000 $75,000.000 $48,000.000 $90,000.000 $130,000.000 $150,000.000
467 6417 SET (TY II) (30 IN) (RCP) (3: 1) (C) EA 8.000 $5,000.000 $4,925.000 $3,500.000 $2,800.000 $5,000.000
467 6448 SET (TY II) (36 IN) (RCP) (3: 1) (C) EA 2.000 $6,000.000 $6,400.000 $4,000.000 $4,000.000 $6,000.000
467 6540 SET (TY II) (DES 3) (RCP) (3: 1) (C) EA 40.000 $2,000.000 $4,250.000 $5,000.000 $2,550.000 $4,000.000
467 6545 SET (TY II) (DES 3) (RCP) (6: 1) (P) EA 26.000 $3,500.000 $5,000.000 $5,500.000 $4,250.000 $4,500.000
467 6611 SET (TY II) (DES 5) (RCP) (3: 1) (C) EA 12.000 $6,000.000 $7,000.000 $7,500.000 $6,250.000 $6,000.000
496 6016 REMOV STR (PIPE) EA 44.000 $500.000 $1,000.000 $50.000 $500.000 $2,500.000
500 6001 MOBILIZATION LS 1.000 $650,412.450 $700,000.000 $750,000.000 $1,100,000.000 $1,250,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 17.000 $20,000.000 $10,000.000 $10,000.000 $50,000.000 $35,000.000
506 6002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 450.000 $30.000 $70.000 $60.000 $65.000 $80.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 450.000 $10.000 $30.000 $40.000 $30.000 $35.000
506 6042 BIODEG EROSN CONT LOGS (INSTL) (18") LF 1,800.000 $6.500 $10.000 $10.000 $7.000 $15.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 1,800.000 $2.000 $2.000 $6.000 $2.000 $2.000
510 6003 ONE-WAY TRAF CONT (PORT TRAF SIG) MO 3.000 $8,000.000 $6,500.000 $15,000.000 $5,000.000 $10,000.000
512 6013 PORT CTB (DES SOURCE)(SGL SLP)(TY 1) LF 1,350.000 $30.000 $32.000 $26.000 $90.000 $40.000
512 6025 PORT CTB (MOVE)(SGL SLP)(TY 1) LF 900.000 $20.000 $24.000 $22.000 $10.000 $35.000
512 6037 PORT CTB (STKPL)(SGL SLP)(TY 1) LF 1,350.000 $20.000 $28.200 $29.000 $20.000 $40.000
530 6016 DRIVEWAYS (BASE) SY 3,536.000 $20.000 $25.000 $16.000 $45.000 $30.000
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 900.000 $28.000 $31.250 $29.000 $26.000 $55.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 400.000 $3.000 $2.400 $3.000 $6.000 $5.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 8.000 $3,400.000 $3,960.000 $3,600.000 $3,100.000 $5,000.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 4.000 $350.000 $240.000 $220.000 $500.000 $500.000
545 6003 CRASH CUSH ATTEN (MOVE & RESET) EA 4.000 $2,500.000 $3,000.000 $3,000.000 $1,500.000 $2,000.000
545 6004 CRASH CUSH ATTEN (STKPL) EA 6.000 $2,000.000 $1,800.000 $2,000.000 $1,500.000 $1,500.000
545 6019 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) EA 6.000 $1,500.000 $9,000.000 $8,400.000 $8,000.000 $10,000.000
560 6006 MAILBOX INSTALL-M (TWG-POST) TY 2 EA 17.000 $500.000 $660.000 $750.000 $450.000 $600.000
644 6001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 81.000 $600.000 $930.000 $770.000 $650.000 $800.000
644 6076 REMOVE SM RD SN SUP&AM EA 81.000 $150.000 $100.000 $100.000 $75.000 $100.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 16.000 $50.000 $30.000 $30.000 $52.950 $75.000
658 6073 INSTL OM ASSM (OM-2Y)(WC)GND(BI) EA 32.000 $65.000 $120.000 $60.000 $75.000 $125.000
662 6051 WK ZN PAV MRK REMOV (REFL) TY II-A-A LF 711.000 $5.000 $3.600 $1.000 $3.000 $10.000
662 6111 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 EA 2,717.000 $2.000 $3.500 $0.500 $1.500 $2.000
666 6174 REFL PAV MRK TY II (W) 6" (SLD) LF 2,808.000 $0.750 $0.360 $0.500 $0.300 $1.000
666 6182 REFL PAV MRK TY II (W) 24" (SLD) LF 48.000 $5.000 $12.000 $25.000 $10.000 $25.000
666 6210 REFL PAV MRK TY II (Y) 6" (SLD) LF 28,422.000 $1.000 $0.360 $1.500 $0.300 $1.000
666 6343 REF PROF PAV MRK TY I(W)6"(SLD)(100MIL) LF 118,499.000 $1.000 $0.830 $1.200 $0.690 $1.250
666 6346 REF PROF PAV MRK TY I(Y)6"(BRK)(100MIL) LF 14,980.000 $1.000 $0.830 $1.300 $0.690 $1.250
666 6347 REF PROF PAV MRK TY I(Y)6"(SLD)(100MIL) LF 31,962.000 $1.000 $0.830 $1.300 $0.690 $1.250
668 6076 PREFAB PAV MRK TY C (W) (24") (SLD) LF 48.000 $20.000 $30.000 $30.000 $25.000 $25.000
672 6009 REFL PAV MRKR TY II-A-A EA 1,149.000 $6.000 $5.100 $6.000 $4.250 $7.000
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 9,223.000 $1.500 $0.540 $4.000 $0.450 $1.000
677 6002 ELIM EXT PAV MRK & MRKS (6") LF 22,008.000 $1.500 $0.540 $4.000 $0.450 $1.000
3077 6044 SP MIXES SP-D PG64-22 (LEVEL-UP) TON 3,850.000 $140.000 $175.000 $140.000 $300.000 $200.000
3077 6075 TACK COAT GAL 7,026.000 $6.000 $6.000 $10.000 $6.000 $8.000
6056 6002 PREFORMED CENTERLINE RUMBLE STRIP LF 12,645.000 $6.000 $7.200 $1.000 $6.000 $15.000
6185 6002 TMA (STATIONARY) DAY 216.000 $350.000 $500.000 $250.000 $510.000 $500.000
6185 6005 TMA (MOBILE OPERATION) DAY 18.000 $500.000 $500.000 $500.000 $550.000 $700.000
Totals: $7,466,432.95 $9,538,047.57 $10,501,878.90 $11,316,281.69 $12,258,164.25