Job Info for 0972-03-023

County: JONES Highway: FM 1082 Date: 03/06/2024 (8 months ago) Engineer's Estimate: $3,488,205 Control Number: 0972-03-023
Project: F 2024(776) District: ABILENE Time: 141 WORKING DAYS Type: SURFACING/ROADWAY RESTORATION
Bidder's List
Email All | Notice | Questions
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $3,488,205.15
J. H. STRAIN & SONS, INC.   $3,582,697.00 1
2.71% | $94,491.85
BONTKE BROTHERS CONSTRUCTION COMPANY   $4,142,610.50 2
18.76% | $654,405.35
15.63% | $559,913.50
GILVIN-TERRILL, LTD.   $4,256,960.56 3
22.04% | $768,755.41
18.82% | $674,263.56
2.76% | $114,350.06
FNH CONSTRUCTION, LLC   $4,540,711.00 4
30.17% | $1,052,505.85
26.74% | $958,014.00
6.67% | $283,750.44
CK NEWBERRY, LLC   $4,797,696.85 5
37.54% | $1,309,491.70
33.91% | $1,214,999.85
5.66% | $256,985.85
Subcontractor Percentage Amount
O. TREVINO CONSTRUCTION, LLC 27.39% $981,300.71
FLAT LINE, INC. 1.76% $63,055.47
CONTRACTORS SERVICE, LTD. 0.53% $18,988.29
AWP SAFETY 0.43% $15,405.60
PROFESSIONAL TRAFFIC CONTROL LLC 0.32% $11,464.63
Total: 30.43% $1,090,214.70

Bid Items

Items: 43, 0 filtered
JONES FM 1082  |  ABILENE  |  0972-03-023  |  03/06/2024  |  $3,488,205  |  F 2024(776)  |  SURF/ROADWAY RESTOR  |  141 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate J. H. STRAIN & SONS, INC. BONTKE BROTHERS CONSTRUCTION COMPANY GILVIN-TERRILL, LTD. FNH CONSTRUCTION, LLC CK NEWBERRY, LLC
104 6001 REMOVING CONC (PAV) SY 3,117.000 $40.000 $25.000 $50.000 $10.000 $20.000 $50.000
110 6001 EXCAVATION (ROADWAY) CY 2,678.000 $40.000 $40.000 $22.000 $25.000 $20.000 $50.000
132 6001 EMBANKMENT (FINAL)(ORD COMP)(TY A) CY 339.000 $70.000 $40.000 $42.000 $10.000 $100.000 $75.000
134 6002 BACKFILL (TY B) STA 190.330 $225.000 $325.000 $250.000 $250.000 $450.000 $500.000
164 6035 DRILL SEEDING (PERM) (RURAL) (CLAY) SY 11,143.000 $1.250 $0.500 $1.000 $0.500 $2.000 $1.000
164 6051 DRILL SEED (TEMP)(WARM OR COOL) SY 11,143.000 $1.250 $0.500 $1.000 $0.500 $2.000 $0.700
168 6001 VEGETATIVE WATERING MG 94.000 $45.000 $50.000 $350.000 $51.000 $100.000 $100.000
247 6053 FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS) CY 502.000 $80.000 $80.000 $68.000 $65.000 $100.000 $250.000
310 6009 PRIME COAT (MC-30) GAL 1,128.000 $6.000 $12.000 $10.000 $15.000 $10.000 $10.000
351 6013 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") SY 1,466.000 $65.000 $65.000 $54.000 $60.000 $55.000 $50.000
360 6002 CONC PVMT (CONT REINF - CRCP) (8") SY 4,244.000 $165.000 $185.000 $250.000 $240.000 $325.000 $250.000
432 6010 RIPRAP (CONC)(CL B)(5 IN) CY 319.000 $700.000 $1,005.000 $900.000 $1,365.000 $650.000 $1,000.000
500 6001 MOBILIZATION LS 1.000 $275,000.000 $350,000.000 $600,000.000 $425,000.000 $450,000.000 $475,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 8.000 $13,500.000 $10,000.000 $10,000.000 $50,000.000 $8,500.000 $25,000.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 1,214.000 $8.000 $8.000 $8.000 $5.000 $4.000 $10.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 1,214.000 $2.000 $2.250 $4.000 $2.000 $2.000 $3.000
508 6001 CONSTRUCTING DETOURS SY 2,086.000 $60.000 $40.000 $55.000 $60.000 $50.000 $100.000
510 6003 ONE-WAY TRAF CONT (PORT TRAF SIG) MO 3.000 $10,000.000 $10,000.000 $15,000.000 $5,000.000 $8,500.000 $15,000.000
530 6002 INTERSECTIONS (ACP) SY 225.000 $60.000 $55.000 $55.000 $80.000 $45.000 $150.000
530 6016 DRIVEWAYS (BASE) SY 324.000 $25.000 $35.000 $48.000 $100.000 $45.000 $75.000
533 6001 RUMBLE STRIPS (SHOULDER) LF 41,454.000 $0.500 $0.200 $1.000 $0.500 $0.500 $0.250
533 6002 RUMBLE STRIPS (CENTERLINE) LF 20,777.000 $0.500 $0.250 $1.000 $0.500 $0.500 $0.250
644 6001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 15.000 $900.000 $13.750 $1,200.000 $700.000 $1,500.000 $1,200.000
644 6008 IN SM RD SN SUP&AM TY10BWG(1)SA(U-EXAL) EA 4.000 $1,000.000 $2,000.000 $2,500.000 $1,200.000 $1,500.000 $2,100.000
644 6076 REMOVE SM RD SN SUP&AM EA 16.000 $125.000 $125.000 $350.000 $150.000 $100.000 $325.000
662 6067 WK ZN PAV MRK REMOV (W)6"(SLD) LF 3,100.000 $2.500 $0.700 $1.000 $0.550 $3.000 $4.000
662 6075 WK ZN PAV MRK REMOV (W)24"(SLD) LF 24.000 $25.000 $6.250 $1.000 $5.000 $20.000 $20.000
662 6111 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 EA 2,169.000 $1.500 $3.500 $1.000 $2.000 $6.000 $2.000
666 6309 RE PM W/RET REQ TY I (W)6"(SLD)(100MIL) LF 41,360.000 $0.800 $0.650 $1.000 $0.520 $2.000 $1.000
666 6318 RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL) LF 2,760.000 $0.800 $0.650 $1.000 $0.520 $2.000 $1.250
666 6321 RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL) LF 26,633.000 $0.800 $0.650 $1.000 $0.520 $2.000 $1.000
668 6076 PREFAB PAV MRK TY C (W) (24") (SLD) LF 60.000 $20.000 $25.000 $20.000 $20.000 $20.000 $30.000
672 6009 REFL PAV MRKR TY II-A-A EA 531.000 $9.000 $5.000 $6.000 $4.000 $6.000 $8.000
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 400.000 $10.000 $1.500 $8.000 $1.000 $2.000 $3.000
678 6002 PAV SURF PREP FOR MRK (6") LF 4,760.000 $1.000 $0.500 $3.000 $0.400 $2.000 $0.750
3077 6001 SP MIXES SP-B PG64-22 TON 460.000 $210.000 $175.000 $135.000 $170.000 $170.000 $250.000
3077 6023 SP MIXES SP-C SAC-B PG70-22 TON 7,630.000 $150.000 $155.000 $135.000 $148.000 $180.000 $175.000
3077 6044 SP MIXES SP-D PG64-22 (LEVEL-UP) TON 310.000 $200.000 $175.000 $135.000 $165.000 $200.000 $225.000
3077 6075 TACK COAT GAL 7,465.000 $5.000 $3.000 $10.000 $6.000 $6.000 $5.000
6038 6004 MULTIPOLYMER PAV MRK (W)(6")(SLD) LF 2,380.000 $2.500 $5.000 $4.000 $4.000 $3.000 $4.000
6038 6017 MULTIPOLYMER PAV MRK (Y)(6")(SLD) LF 2,380.000 $2.500 $5.000 $4.000 $4.000 $3.000 $4.000
6185 6002 TMA (STATIONARY) DAY 60.000 $300.000 $250.000 $350.000 $650.000 $250.000 $500.000
6185 6005 TMA (MOBILE OPERATION) DAY 27.000 $600.000 $250.000 $500.000 $650.000 $550.000 $500.000
Totals: $3,488,205.15 $3,582,697.00 $4,142,610.50 $4,256,960.56 $4,540,711.00 $4,797,696.85