Job Info for 0972-03-021

County: JONES Highway: FM 1082 Date: 08/03/2023 (1 year ago) Engineer's Estimate: $8,058,458 Control Number: 0972-03-021
Project: F 2B23(134) District: ABILENE Time: 261 WORKING DAYS Type: CONSTRUCT NEW ROAD
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $8,058,457.50
GILVIN-TERRILL, LTD.   $8,867,738.98 1
10.04% | $809,281.48
A. L. HELMCAMP, INC.   $12,756,115.56 2
58.29% | $4,697,658.06
43.85% | $3,888,376.58
Subcontractor Percentage Amount
BLACK JACK ENERGY SERVICES, LLC 38.55% $3,418,513.38
ALAMO BROTHERS CONCRETE INC 4.35% $385,746.65
HJC FARMS, INC. 2.66% $235,881.86
HODGES AND SON CONSTRUCTION COMPANY, INC. 1.55% $137,449.95
FLAT LINE, INC. 0.75% $66,508.04
WOLFE CONSTRUCTION GROUP, INCORPORATED 0.41% $36,357.73
MURRAY CONSTRUCTION 0.37% $32,810.63
TORO BRAVO CONSTRUCTION, LLC 0.20% $17,735.48
BARRICADES UNLIMITED 0.16% $14,188.38
SCOTT DERR PAINTING CO, LLC 0.16% $14,188.38
PENHALL COMPANY 0.06% $5,320.64
TORO BRAVO CONSTRUCTION, LLC 0.06% $5,320.64
Total: 49.28% $4,370,021.76

Bid Items

Items: 85, 0 filtered
JONES FM 1082  |  ABILENE  |  0972-03-021  |  08/03/2023  |  $8,058,458  |  F 2B23(134)  |  CONSTRUCT NEW ROAD  |  261 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate GILVIN-TERRILL, LTD. A. L. HELMCAMP, INC.
100 6002 PREPARING ROW STA 58.000 $6,000.000 $10,000.000 $4,000.000
105 6008 REMOVING STAB BASE AND ASPH PAV (6") SY 4,725.000 $8.000 $10.000 $4.000
110 6001 EXCAVATION (ROADWAY) CY 174,882.000 $13.000 $15.000 $37.000
132 6008 EMBANKMENT (FINAL)(DENS CONT)(TY D) CY 40,515.000 $15.000 $8.000 $24.000
164 6036 DRILL SEEDING (PERM) (RURAL) (CLAY) AC 18.060 $2,000.000 $1,000.000 $1,265.000
164 6042 DRILL SEEDING (TEMP) (WARM) AC 9.040 $850.000 $1,000.000 $910.000
164 6044 DRILL SEEDING (TEMP) (COOL) AC 9.020 $850.000 $1,000.000 $935.000
168 6001 VEGETATIVE WATERING MG 735.900 $60.000 $76.540 $46.000
169 6001 SOIL RETENTION BLANKETS (CL 1) (TY A) SY 2,910.000 $7.000 $3.000 $2.750
247 6041 FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS) CY 7,004.000 $85.000 $55.000 $59.000
310 6009 PRIME COAT (MC-30) GAL 3,751.000 $12.000 $7.000 $5.500
316 6001 ASPH (MULTI OPTION) GAL 7,501.000 $10.000 $8.000 $5.500
316 6017 ASPH (AC-20-5TR) GAL 7,467.000 $10.000 $8.000 $5.500
316 6222 AGGR(TY-PB GR-3 SAC-B) CY 164.000 $350.000 $200.000 $310.000
316 6519 AGGR (TY-PB GR-4 MOD) CY 173.000 $380.000 $200.000 $275.000
400 6005 CEM STABIL BKFL CY 62.000 $350.000 $500.000 $220.000
400 6006 CUT & RESTORING PAV SY 11.000 $350.000 $500.000 $500.000
401 6001 FLOWABLE BACKFILL CY 6.000 $700.000 $1,000.000 $580.000
416 6004 DRILL SHAFT (36 IN) LF 512.000 $320.000 $510.000 $510.000
420 6014 CL C CONC (ABUT)(HPC) CY 51.200 $1,900.000 $2,500.000 $3,000.000
420 6030 CL C CONC (CAP)(HPC) CY 28.600 $2,150.000 $2,500.000 $4,400.000
420 6038 CL C CONC (COLUMN)(HPC) CY 31.600 $2,100.000 $2,500.000 $2,600.000
422 6001 REINF CONC SLAB SF 11,050.000 $45.000 $40.000 $62.000
422 6015 APPROACH SLAB CY 51.300 $1,200.000 $2,500.000 $1,900.000
425 6039 PRESTR CONC GIRDER (TX54) LF 1,294.000 $310.000 $400.000 $310.000
427 6004 SILICONE RESIN PAINT FINISH SF 1,400.000 $15.000 $12.000 $14.000
432 6001 RIPRAP (CONC)(4 IN) CY 182.000 $800.000 $800.000 $890.000
432 6010 RIPRAP (CONC)(CL B)(5 IN) CY 180.000 $850.000 $800.000 $795.000
432 6026 RIPRAP (STONE COMMON)(DRY)(18 IN) CY 62.000 $300.000 $600.000 $155.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 64.000 $650.000 $800.000 $800.000
450 6023 RAIL (TY SSTR) LF 698.000 $165.000 $150.000 $210.000
454 6018 SEALED EXPANSION JOINT (4 IN) (SEJ - M) LF 68.000 $230.000 $300.000 $340.000
464 6003 RC PIPE (CL III)(18 IN) LF 236.000 $100.000 $120.000 $136.000
464 6005 RC PIPE (CL III)(24 IN) LF 130.000 $150.000 $150.000 $144.000
467 6358 SET (TY II) (18 IN) (RCP) (4: 1) (C) EA 2.000 $2,000.000 $3,500.000 $2,313.000
467 6363 SET (TY II) (18 IN) (RCP) (6: 1) (P) EA 2.000 $2,500.000 $4,000.000 $2,536.000
467 6394 SET (TY II) (24 IN) (RCP) (6: 1) (C) EA 4.000 $2,800.000 $4,500.000 $3,060.000
496 6004 REMOV STR (SET) EA 2.000 $2,500.000 $3,200.000 $2,118.000
496 6016 REMOV STR (PIPE) EA 1.000 $2,000.000 $3,200.000 $3,877.000
500 6001 MOBILIZATION LS 1.000 $719,000.000 $880,000.000 $825,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 15.000 $10,000.000 $50,000.000 $10,000.000
506 6002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 120.000 $50.000 $60.000 $68.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 120.000 $15.000 $17.500 $22.000
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 230.000 $45.000 $55.000 $65.000
506 6024 CONSTRUCTION EXITS (REMOVE) SY 230.000 $10.000 $15.000 $18.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 1,775.000 $5.000 $5.000 $5.500
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 1,775.000 $2.000 $2.500 $1.500
506 6040 BIODEG EROSN CONT LOGS (INSTL) (8") LF 385.000 $5.000 $7.500 $8.000
506 6042 BIODEG EROSN CONT LOGS (INSTL) (18") LF 575.000 $10.000 $10.000 $11.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 960.000 $4.000 $3.000 $3.000
508 6001 CONSTRUCTING DETOURS SY 3,870.000 $60.000 $45.000 $15.000
510 6003 ONE-WAY TRAF CONT (PORT TRAF SIG) MO 5.000 $8,000.000 $4,500.000 $10,000.000
512 6013 PORT CTB (DES SOURCE)(SGL SLP)(TY 1) LF 1,140.000 $25.000 $15.000 $75.000
512 6025 PORT CTB (MOVE)(SGL SLP)(TY 1) LF 870.000 $20.000 $12.000 $25.000
512 6037 PORT CTB (STKPL)(SGL SLP)(TY 1) LF 1,140.000 $20.000 $15.000 $75.000
512 6041 PORT CTB (STKPL)(F-SHAPE)(TY 1) LF 420.000 $20.000 $15.000 $75.000
530 6005 DRIVEWAYS (ACP) SY 544.000 $50.000 $70.000 $85.000
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 850.000 $30.000 $25.000 $34.000
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 4.000 $2,800.000 $2,025.000 $2,470.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 4.000 $3,500.000 $3,300.000 $3,835.000
545 6003 CRASH CUSH ATTEN (MOVE & RESET) EA 2.000 $3,000.000 $3,200.000 $8,040.000
545 6005 CRASH CUSH ATTEN (REMOVE) EA 4.000 $2,000.000 $1,500.000 $4,020.000
545 6019 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) EA 2.000 $10,000.000 $10,250.000 $17,135.000
550 6001 CHAIN LINK FENCE (INSTALL) (6') LF 4,633.000 $40.000 $20.000 $45.000
550 6021 GATE (INSTALL)(SINGLE)(6' X 24') EA 1.000 $2,000.000 $2,500.000 $4,000.000
552 6003 WIRE FENCE (TY C) LF 1,497.000 $25.000 $20.000 $10.000
644 6004 IN SM RD SN SUP&AM TY10BWG(1)SA(T) EA 14.000 $1,200.000 $851.000 $910.000
644 6060 IN SM RD SN SUP&AM TYTWT(1)WS(P) EA 34.000 $700.000 $542.000 $650.000
644 6076 REMOVE SM RD SN SUP&AM EA 27.000 $150.000 $100.000 $130.000
658 6014 INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) EA 8.000 $50.000 $52.950 $69.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 17.000 $40.000 $57.950 $31.000
658 6073 INSTL OM ASSM (OM-2Y)(WC)GND(BI) EA 4.000 $100.000 $57.000 $97.000
662 6111 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 EA 720.000 $3.000 $1.000 $1.300
666 6174 REFL PAV MRK TY II (W) 6" (SLD) LF 24,847.000 $1.500 $0.550 $0.720
666 6182 REFL PAV MRK TY II (W) 24" (SLD) LF 36.000 $15.000 $25.000 $32.500
666 6210 REFL PAV MRK TY II (Y) 6" (SLD) LF 10,422.000 $1.500 $0.550 $0.720
666 6343 REF PROF PAV MRK TY I(W)6"(SLD)(100MIL) LF 13,670.000 $1.500 $1.250 $1.630
666 6347 REF PROF PAV MRK TY I(Y)6"(SLD)(100MIL) LF 13,570.000 $1.500 $1.250 $1.630
668 6076 PREFAB PAV MRK TY C (W) (24") (SLD) LF 16.000 $20.000 $30.000 $39.000
672 6009 REFL PAV MRKR TY II-A-A EA 341.000 $5.000 $9.000 $11.700
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 35,826.000 $1.000 $0.250 $0.330
677 6007 ELIM EXT PAV MRK & MRKS (24") LF 12.000 $25.000 $25.000 $32.500
6120 6001 DEAD END ROADWAY BARRICADE LF 24.000 $110.000 $125.000 $165.000
6185 6002 TMA (STATIONARY) DAY 30.000 $400.000 $735.000 $250.000
6185 6005 TMA (MOBILE OPERATION) DAY 20.000 $400.000 $950.000 $250.000
Totals: $8,058,457.50 $8,867,738.99 $12,756,115.56