PREPARING ROW
|
STA
|
1,724.000
|
$1,000.000
|
$75.000
|
$350.000
|
$500.000
|
|
|
REMOVING CONC (RIPRAP)
|
CY
|
3.000
|
$492.910
|
$100.000
|
$170.000
|
$110.000
|
|
|
REMOVING CONC (DRIVEWAYS)
|
SY
|
72.000
|
$66.000
|
$15.000
|
$40.000
|
$20.000
|
|
|
OBLITERATING ABANDONED ROAD
|
STA
|
4.510
|
$2,000.000
|
$3,000.000
|
$300.000
|
$1,000.000
|
|
|
EXCAVATION (CHANNEL)
|
CY
|
348.000
|
$15.000
|
$25.000
|
$13.000
|
$30.000
|
|
|
SUBGRADE WIDENING (ORD COMP)
|
STA
|
3,443.580
|
$424.000
|
$225.000
|
$80.000
|
$1,025.000
|
|
|
EMBANKMENT (ORIGINAL)(ORD COMP)(TY B)
|
CY
|
72,154.000
|
$5.000
|
$15.600
|
$14.500
|
$20.000
|
|
|
BACKFILL (TY A OR B)
|
STA
|
1,298.000
|
$119.500
|
$175.000
|
$368.000
|
$600.000
|
|
|
BROADCAST SEED (PERM) (RURAL) (SANDY)
|
AC
|
219.500
|
$361.000
|
$460.000
|
$450.000
|
$550.000
|
|
|
BROADCAST SEED (TEMP) (COOL)
|
AC
|
219.500
|
$445.000
|
$290.000
|
$300.000
|
$500.000
|
|
|
VEGETATIVE WATERING
|
MG
|
11,857.950
|
$59.300
|
$35.000
|
$8.000
|
$25.000
|
|
|
PROOF ROLLING
|
HR
|
460.000
|
$64.300
|
$75.000
|
$70.000
|
$75.000
|
|
|
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
|
CY
|
54,458.000
|
$36.200
|
$38.000
|
$54.000
|
$41.000
|
|
|
FL BS (CMP IN PLC)(TY D GR-1-2)(9")
|
SY
|
5,000.000
|
$9.190
|
$10.000
|
$15.000
|
$14.750
|
|
|
CEMENT
|
TON
|
45.000
|
$155.200
|
$200.000
|
$210.000
|
$160.000
|
|
|
CEM TRT (MX EXST MTL & NEW BS) (9"-13")
|
SY
|
5,000.000
|
$3.500
|
$4.750
|
$4.200
|
$15.000
|
|
|
PRIME COAT & BLOTTER (MC-30)
|
GAL
|
78,312.000
|
$4.100
|
$5.000
|
$4.800
|
$4.000
|
|
|
ASPH (MULTI OPTION)
|
GAL
|
84,368.000
|
$3.850
|
$4.500
|
$3.500
|
$2.750
|
|
|
AGGR(TY-PB GR-3 SAC-B)
|
CY
|
1,785.000
|
$70.000
|
$105.000
|
$155.000
|
$110.000
|
|
|
AGGR(TY-PB GR-4 SAC-B)
|
CY
|
3,403.000
|
$86.000
|
$105.000
|
$110.000
|
$110.000
|
|
|
ASPH (AC-20-5TR OR AC-20XP)
|
GAL
|
140,871.000
|
$3.050
|
$4.500
|
$4.200
|
$3.700
|
|
|
SUPERPAVE MIXTURES SP-D SAC-B PG70-22
|
TON
|
8,090.000
|
$120.000
|
$103.000
|
$96.000
|
$125.000
|
|
|
PLAN & TEXT ASPH CONC PAV(0" TO 2")
|
SY
|
14,395.000
|
$6.960
|
$3.000
|
$3.500
|
$4.000
|
|
|
CUT AND RESTORE PAV (FLEX BASE)
|
SY
|
49.000
|
$92.000
|
$125.000
|
$50.000
|
$125.000
|
|
|
FLOWABLE BACKFILL
|
CY
|
186.000
|
$288.890
|
$275.000
|
$300.000
|
$250.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
405.000
|
$5.000
|
$100.000
|
$40.000
|
$75.000
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
64.000
|
$450.000
|
$650.000
|
$550.000
|
$750.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
103.000
|
$695.500
|
$650.000
|
$500.000
|
$600.000
|
|
|
RAIL (TY T223)
|
LF
|
105.000
|
$110.000
|
$120.000
|
$160.000
|
$300.000
|
|
|
GABION MATTRESSES (GALV)(12 IN)
|
SY
|
282.000
|
$167.600
|
$100.000
|
$75.000
|
$150.000
|
|
|
CMP (GAL STL 18 IN)
|
LF
|
60.000
|
$41.400
|
$65.000
|
$50.000
|
$65.000
|
|
|
CMP (GAL STL 24 IN)
|
LF
|
1,001.000
|
$56.580
|
$70.000
|
$65.000
|
$70.000
|
|
|
CMP (GAL STL 30 IN)
|
LF
|
21.000
|
$86.440
|
$100.000
|
$80.000
|
$75.000
|
|
|
CMP (GAL STL 36 IN)
|
LF
|
68.000
|
$120.120
|
$115.000
|
$95.000
|
$80.000
|
|
|
CMP AR (GAL STL DES 3)
|
LF
|
1,494.000
|
$50.000
|
$80.000
|
$75.000
|
$70.000
|
|
|
CMP AR (GAL STL DES 4)
|
LF
|
598.000
|
$52.140
|
$110.000
|
$90.000
|
$75.000
|
|
|
CMP AR (GAL STL DES 5)
|
LF
|
324.000
|
$65.460
|
$150.000
|
$135.000
|
$80.000
|
|
|
CMP AR (GAL STL DES 6)
|
LF
|
231.000
|
$200.000
|
$210.000
|
$200.000
|
$90.000
|
|
|
CONC BOX CULV (7 FT X 3 FT)
|
LF
|
56.000
|
$318.930
|
$1,000.000
|
$475.000
|
$550.000
|
|
|
CONC BOX CULV (7 FT X 5 FT)
|
LF
|
56.000
|
$325.540
|
$1,100.000
|
$575.000
|
$650.000
|
|
|
CONC BOX CULV (4 FT X 4 FT)(EXTEND)
|
LF
|
128.000
|
$264.330
|
$550.000
|
$425.000
|
$850.000
|
|
|
CONC BOX CULV (5 FT X 3 FT)(EXTEND)
|
LF
|
77.000
|
$308.630
|
$575.000
|
$475.000
|
$1,200.000
|
|
|
CONC BOX CULV (8 FT X 6 FT)(EXTEND)
|
LF
|
20.000
|
$745.580
|
$1,100.000
|
$900.000
|
$2,300.080
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
85.000
|
$100.000
|
$180.000
|
$85.000
|
$120.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 36 IN)
|
EA
|
2.000
|
$5,257.140
|
$7,500.000
|
$8,000.000
|
$20,000.000
|
|
|
HEADWALL (CH - PW - A - 0) (DES= 3)
|
EA
|
2.000
|
$9,000.000
|
$4,200.000
|
$4,000.000
|
$10,000.000
|
|
|
HEADWALL (CH - PW - A - 0) (DES= 6)
|
EA
|
4.000
|
$5,482.000
|
$9,100.000
|
$9,000.000
|
$25,000.000
|
|
|
HEADWALL (CH - PW - A - S) (DES= 3)
|
EA
|
2.000
|
$6,320.000
|
$4,400.000
|
$4,500.000
|
$10,000.000
|
|
|
HEADWALL (CH - PW - A - S) (DES= 4)
|
EA
|
2.000
|
$9,963.000
|
$5,000.000
|
$5,500.000
|
$12,000.000
|
|
|
WINGWALL (FW - 0) (HW=11 FT)
|
EA
|
2.000
|
$23,000.000
|
$13,000.000
|
$20,000.000
|
$30,000.000
|
|
|
WINGWALL (FW - 0) (HW=8 FT)
|
EA
|
2.000
|
$7,500.000
|
$12,000.000
|
$16,000.000
|
$29,000.000
|
|
|
WINGWALL (PW - 2) (HW=5 FT)
|
EA
|
8.000
|
$7,488.890
|
$10,000.000
|
$10,000.000
|
$28,000.000
|
|
|
WINGWALL (PW - 2) (HW=6 FT)
|
EA
|
2.000
|
$11,360.000
|
$12,000.000
|
$13,000.000
|
$28,000.000
|
|
|
WINGWALL (PW - 2) (HW=7 FT)
|
EA
|
2.000
|
$13,250.000
|
$14,000.000
|
$21,000.000
|
$29,000.000
|
|
|
SET (TY II) (18 IN) (CMP) (3: 1) (C)
|
EA
|
8.000
|
$933.330
|
$1,000.000
|
$850.000
|
$2,000.000
|
|
|
SET (TY II) (24 IN) (CMP) (3: 1) (C)
|
EA
|
4.000
|
$1,513.880
|
$1,200.000
|
$950.000
|
$2,100.000
|
|
|
SET (TY II) (24 IN) (CMP) (6: 1) (P)
|
EA
|
64.000
|
$1,288.380
|
$1,500.000
|
$950.000
|
$2,300.000
|
|
|
SET (TY II) (24 IN) (RCP) (3: 1) (C)
|
EA
|
28.000
|
$883.820
|
$1,800.000
|
$950.000
|
$2,350.000
|
|
|
SET (TY II) (30 IN) (CMP) (3: 1) (C)
|
EA
|
2.000
|
$1,200.000
|
$1,800.000
|
$2,000.000
|
$2,400.000
|
|
|
SET (TY II) (36 IN) (CMP) (3: 1) (C)
|
EA
|
10.000
|
$2,582.190
|
$2,000.000
|
$3,000.000
|
$3,000.000
|
|
|
SET (TY II) (DES 3) (CMP) (3: 1) (C)
|
EA
|
74.000
|
$1,200.000
|
$1,800.000
|
$950.000
|
$2,000.000
|
|
|
SET (TY II) (DES 3) (CMP) (6: 1) (P)
|
EA
|
76.000
|
$1,710.600
|
$1,700.000
|
$1,250.000
|
$2,500.000
|
|
|
SET (TY II) (DES 4) (CMP) (3: 1) (C)
|
EA
|
26.000
|
$1,350.000
|
$2,000.000
|
$2,700.000
|
$3,000.000
|
|
|
SET (TY II) (DES 4) (CMP) (6: 1) (P)
|
EA
|
24.000
|
$2,425.000
|
$2,800.000
|
$3,200.000
|
$4,500.000
|
|
|
SET (TY II) (DES 5) (CMP) (3: 1) (C)
|
EA
|
10.000
|
$3,000.000
|
$2,500.000
|
$3,200.000
|
$4,500.000
|
|
|
SET (TY II) (DES 5) (CMP) (6: 1) (P)
|
EA
|
16.000
|
$2,753.610
|
$3,500.000
|
$3,700.000
|
$5,500.000
|
|
|
SET (TY II) (DES 6) (CMP) (3: 1) (C)
|
EA
|
6.000
|
$3,450.000
|
$2,000.000
|
$4,800.000
|
$7,000.000
|
|
|
JACK BOR TUN BOX CULV (7 FT X 3 FT)
|
LF
|
60.000
|
$1,200.000
|
$1,800.000
|
$1,500.000
|
$2,000.000
|
|
|
JACK BOR TUN BOX CULV (7 FT X 5 FT)
|
LF
|
60.000
|
$3,408.000
|
$2,600.000
|
$1,900.000
|
$2,100.000
|
|
|
JACK BOR TUN BOX CULV (8 FT X 7 FT)
|
LF
|
72.000
|
$4,000.000
|
$3,000.000
|
$2,200.000
|
$2,200.000
|
|
|
REMOV STR (PIPE)
|
LF
|
3,072.000
|
$21.000
|
$20.000
|
$15.000
|
$50.000
|
|
|
REMOVE STR (CONC)
|
EA
|
3.000
|
$7,800.000
|
$6,500.000
|
$2,500.000
|
$4,000.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$1,500,000.000
|
$1,250,000.000
|
$1,350,000.000
|
$2,000,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
36.000
|
$10,000.000
|
$2,700.000
|
$13,000.000
|
$5,500.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
1,260.000
|
$34.100
|
$25.000
|
$25.000
|
$37.500
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
1,260.000
|
$8.100
|
$10.000
|
$5.000
|
$10.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
2,003.000
|
$20.000
|
$10.000
|
$8.000
|
$32.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
2,003.000
|
$5.000
|
$5.000
|
$1.000
|
$10.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
52,052.000
|
$3.700
|
$3.500
|
$3.000
|
$2.500
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
52,052.000
|
$1.250
|
$1.500
|
$0.800
|
$0.800
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
13,330.000
|
$5.100
|
$5.000
|
$3.500
|
$6.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
13,330.000
|
$0.500
|
$1.000
|
$0.800
|
$0.600
|
|
|
PORT CTB (MOVE)(SGL SLP)(TY 1)
|
LF
|
3,000.000
|
$15.270
|
$15.000
|
$15.000
|
$10.000
|
|
|
PORT CTB (STKPL)(SGL SLP)(TY 1)
|
LF
|
600.000
|
$13.730
|
$35.000
|
$19.000
|
$10.000
|
|
|
PORT CTB (REMOVE)(SGL SLP)(TY 1)
|
LF
|
600.000
|
$20.000
|
$35.000
|
$19.000
|
$10.000
|
|
|
INTERSECTIONS (SURF TREAT)
|
SY
|
623.000
|
$25.000
|
$20.000
|
$33.000
|
$37.000
|
|
|
DRIVEWAYS (SURF TREAT)
|
SY
|
31,992.000
|
$16.000
|
$20.000
|
$20.000
|
$37.000
|
|
|
TURNOUTS (SURF TREAT)
|
SY
|
2,249.000
|
$25.000
|
$20.000
|
$20.000
|
$37.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
325.000
|
$25.350
|
$23.000
|
$23.000
|
$25.000
|
|
|
MTL W-BEAM GD FEN (STEEL POST)
|
LF
|
250.000
|
$25.680
|
$40.000
|
$38.000
|
$25.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
12.000
|
$2,200.000
|
$2,125.000
|
$2,100.000
|
$2,000.000
|
|
|
SHORT RADIUS
|
LF
|
25.000
|
$30.560
|
$30.000
|
$30.000
|
$35.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
125.000
|
$3.210
|
$2.250
|
$2.500
|
$3.000
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
6.000
|
$250.000
|
$225.000
|
$250.000
|
$500.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
22.000
|
$2,217.730
|
$3,000.000
|
$3,000.000
|
$2,500.000
|
|
|
MAILBOX INSTALL-S (TWW-POST) TY 4
|
EA
|
127.000
|
$500.000
|
$225.000
|
$200.000
|
$175.000
|
|
|
MAILBOX INSTALL-D (TWW-POST) TY 4
|
EA
|
11.000
|
$500.000
|
$315.000
|
$280.000
|
$280.000
|
|
|
MAILBOX INSTALL-M (TWW-POST) TY 4
|
EA
|
12.000
|
$500.000
|
$530.000
|
$470.000
|
$550.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
244.000
|
$752.000
|
$390.000
|
$280.000
|
$350.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
18.000
|
$869.740
|
$490.000
|
$480.000
|
$450.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
|
EA
|
4.000
|
$963.510
|
$530.000
|
$510.000
|
$750.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T)
|
EA
|
8.000
|
$1,134.880
|
$735.000
|
$710.000
|
$850.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U)
|
EA
|
1.000
|
$1,061.990
|
$670.000
|
$650.000
|
$1,150.000
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(P)
|
EA
|
21.000
|
$739.960
|
$250.000
|
$250.000
|
$260.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
278.000
|
$87.490
|
$50.000
|
$50.000
|
$40.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(FLX)GF2(BI)
|
EA
|
72.000
|
$22.000
|
$28.000
|
$30.000
|
$30.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
|
EA
|
30.000
|
$21.400
|
$22.000
|
$25.000
|
$25.000
|
|
|
INSTL OM ASSM (OM-2Y)(WC)GND
|
EA
|
112.000
|
$78.930
|
$60.000
|
$60.000
|
$40.000
|
|
|
REMOVE DELIN & OBJECT MARKER ASSMS
|
EA
|
142.000
|
$15.000
|
$10.000
|
$10.000
|
$25.000
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
|
LF
|
22,020.000
|
$0.250
|
$0.350
|
$0.350
|
$0.350
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
|
LF
|
64,944.000
|
$0.350
|
$0.330
|
$0.350
|
$0.350
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
7,591.000
|
$0.200
|
$2.000
|
$0.600
|
$1.000
|
|
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
|
LF
|
105.000
|
$1.190
|
$1.100
|
$2.100
|
$2.000
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
1,073.000
|
$8.910
|
$13.200
|
$6.800
|
$6.450
|
|
|
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
|
LF
|
339,420.000
|
$0.550
|
$0.770
|
$0.730
|
$0.680
|
|
|
REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL)
|
LF
|
35,270.000
|
$0.550
|
$1.050
|
$1.000
|
$0.900
|
|
|
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
|
LF
|
108,294.000
|
$0.550
|
$0.770
|
$0.730
|
$0.680
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
3,097.000
|
$6.400
|
$3.100
|
$3.800
|
$3.600
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
8.000
|
$10,155.000
|
$15,000.000
|
$4,000.000
|
$15,000.000
|
|
|
PREFORMED CENTERLINE RUMBLE STRIP
|
LF
|
9,875.000
|
$4.600
|
$4.500
|
$4.600
|
$4.500
|
|
|
TMA (STATIONARY)
|
DAY
|
544.000
|
$250.000
|
$250.000
|
$200.000
|
$345.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
20.000
|
$350.000
|
$500.000
|
$300.000
|
$950.000
|
|
Totals: |
$15,249,964.555
|
$13,833,694.000
|
$14,248,301.120
|
$20,314,748.620
|